six sigma

profileMalansari23
caaccs109261620.pptx

Application of Six Sigma Methodology to Reduce Defects of a Grinding Process

Case study 1

Done by: Connor Austin & Abdulla Aldhaheri

CODE: CAACCS1092616

Company Profile

Name: Unknown

Location: India

Type: Automotive Company

The company with manpower of approximately 2550 people is manufacturing common rail direct injection (CRDI) system pumps for vehicles.

Drivers For Change

Rejection level was too high.

The goal of visually inspecting all parts could not be reached.

Six Sigma Project

Define

Measure

Analyze

Improve

Control

Define

The team selected for this project includes the Senior Manager—Manufacturing as the Black Belt (BB). The other members of the team were Planning Manager, Maintenance Manager, Quality Control Senior Engineer and one Machine Operator.

Reduce rejection by 50%

The scope of the project was focusing in the fine grinding for improvement.

Measure

The Six Sigma team found the rejection were mainly due to the occurrence of different types of defects, such as burr, shades, deep lines, patches and damage on the component after machining.

Measure Cont.

Company used an equation called the Kappa equation to determine if their measurement system was acceptable.

The Kappa value that was calculated was .814, which is greater than .6. So, the measurement system was accpetalbe.

Measure Cont.

Analyze

Find the potential causes of defects.

Gather data from the process in order to obtain a better picture of the potential causes.

Analyze Cont.

Improve

The parameters selected through these discussions were load applied, initial load setting, coolant flow rate, upper wheel rpm, lower wheel rpm and cage rpm.

decided to experiment all these parameters at three levels.

Improve Cont.

The team concluded from the risk analysis that each method had its own impact on the process.

A program was started to implement each method in order to improve the process. A two week timeframe was used to implement the solutions.

Control Phase

The solutions that the team found were standardized in order to produce consistent results.

Control Phase Cont.

A control chart was implemented to keep an eye on assignable causes in the future.

For every shift, data on number of defects observed during 100% visual inspection were collected and these values were plotted.

Six Sigma Tools Used

Pareto Chart

Cause and Effect Diagram

Histogram

KPIV and KPOV

Key Process Input Variables

Load Applied

Initial Load setting

Coolant Flow Rate

RPMs

Key Process Output Variable

Reduction in rejection by 50%

Results Achieved

After implementation the rejection percentage went from 16% to 1.19%

The approximate Six Sigma level increased from 2.47 to 3.76.

Goal was achieved as the rejection rate was significantly improved.

Lessons Learned

The company learned the power of statistical thinking and its impact on processes.

The results obtained by this project will provide start-up data for further implementations in future.

Management cooperation was important to complete the project.

Questions?

References

http://pure.strath.ac.uk/portal/files/5714277/jiju.pdf