financial report

profileashley016
20161109010944d___j_plastics_project_info.xls

Sheet

Name Group Period Est Hours Est Cost Action
Business evaluation (NPV, etc.) Market Assessment 1 32 4000
Customer preference study Market Assessment 1 168 8400
Develop Business opportunity Market Assessment 1 112 10080
Evaluate market Market Assessment 1 96 4800
Project Management Period 1 Project Management 1 200 25000
Design and development plan Design 2 48 2400
Design specs. Design 2 176 8800
Develop marketing program Commercialization 2 120 10800
Develop preliminary marketing plan Commercialization 2 40 3600
Project Management Period 2 Project Management 2 112 14000
Advertising campaign Commercialization 3 224 11200
Identify testing requirements Design 3 80 4000
Project Management Period 3 Project Management 3 112 14000
Risk analysis Design 3 80 10000
Train sales team Commercialization 3 176 8800
Approve design Design 4 32 1600
Design labeling Design 4 40 2000
Initial engineering specs. Engineering 4 40 2000
Project Management Period 4 Project Management 4 104 13000
Design verification activities Engineering 5 56 4200
Project Management Period 5 Project Management 5 120 15000
Release pre-production specifications Engineering 5 80 4000
Verification design review Engineering 5 32 1600
Build functional model Engineering 6 144 10800
Develop and Issue RFQ Procurement 6 48 2400
Evaluate design specifications Engineering Quality 6 80 4000
Identify vendors Procurement 6 56 2800
Project Management Period 6 Project Management 6 72 9000
Develop testing protocol for prototype Engineering Quality 7 64 3200
Issue sample (production equivalent) Procurement 7 40 3000
Perform supplier process capability Supplier Quality 7 112 5600
Project Management Period 7 Project Management 7 88 11000
Approve sample parts Supplier Quality 8 64 4800
Design validation activities Engineering 8 40 2000
Process engineering plan Manufacturing 8 120 6000
Project Management Period 8 Project Management 8 24 3000
Show functional model at trade show Commercialization 8 24 2160
Test prototype Engineering Quality 8 80 4000
Approve model design Engineering 9 32 2400
Evaluate results of tests and identify weaknesses Engineering Quality 9 48 2400
Project Management Period 9 Project Management 9 32 4000
Validation design review Engineering 9 32 4000
Design transfer activities Engineering 10 56 4200
Develop production plan Manufacturing 10 48 2400
Product release meetings Engineering Quality 10 24 3000
Project Management Period 10 Project Management 10 40 5000
Qualify Supplier Supplier Quality 10 80 4000
Approve production parts Manufacturing 11 40 2000
Assess RFQ responses and select vendors Procurement 11 80 4000
Contracting for deliveries Manufacturing 11 64 3200
Develop production control plan Manufacturing 11 68 3400
Project Management Period 11 Project Management 11 104 13000
Debugging production system Manufacturing 12 32 1600
Product launch Commercialization 12 24 3000
Production pilot test Manufacturing 12 40 2000
Production release Manufacturing 12 24 1200
Project Management Period 12 Project Management 12 80 10000
Submit production purchase order Manufacturing 12 16 800
4300 332640