Food Truck Project

PERT-CPM

Below is a table showing all activities with their immediate predecessors and timeframe:

Activities

Immediate Predecessors

Time

A. SWOT ANALYSIS

--

4

B. PROJECT PLANNING

--

1

C. Tram Assignment

A

1

D. Survey

--

12

E. Survey Analysis

D

1

F. Social Media

D

2

G. Website Dev. Tool

B

10

H. Graphing

G

3

I. Developing

H

4

J. Menu

B

21

K. Cooking

B

1

L. Mechanical T Survey

F,E

2

M. PowerPoint

L

2

/Users/Yazeed/Desktop/PERT.png

After creating the PERT-CPM chart shown above the project completion time will be 23 days, according to the critical path B-J-K.

Those activities were B. Project planning followed by J. Menu and finally K. Cooking.