Gant chart
Food Truck Project
PERT-CPM
Below is a table showing all activities with their immediate predecessors and timeframe:
|
Activities |
Immediate Predecessors |
Time |
|
A. SWOT ANALYSIS |
-- |
4 |
|
B. PROJECT PLANNING |
-- |
1 |
|
C. Tram Assignment |
A |
1 |
|
D. Survey |
-- |
12 |
|
E. Survey Analysis |
D |
1 |
|
F. Social Media |
D |
2 |
|
G. Website Dev. Tool |
B |
10 |
|
H. Graphing |
G |
3 |
|
I. Developing |
H |
4 |
|
J. Menu |
B |
21 |
|
K. Cooking |
B |
1 |
|
L. Mechanical T Survey |
F,E |
2 |
|
M. PowerPoint |
L |
2 |
After creating the PERT-CPM chart shown above the project completion time will be 23 days, according to the critical path B-J-K.
Those activities were B. Project planning followed by J. Menu and finally K. Cooking.