Business Management

profilemcbvic
individual_project_info_3.docx

Individual Project Information

The goal of the individual project is for the student to act as project manager for a virtual project that will start with a project charter and utilize key project templates throughout the life cycle of the project. The project will culminate in a minimum 1000-word closeout paper. The individual project will demonstrate that the student can appropriately apply the project management templates throughout the life cycle of his or her project and can evaluate and articulate the project team’s performance of actual work as it relates to plan values as well as capture valuable lessons learned for knowledge sharing. We encourage you to be creative in this process.

Individual Project Background info:

Your project will be to remodel a master bathroom for a good friend. You have a reputation for being skilled in home improvement and your friend has asked you to undertake this project to help save money on the project. Your friend’s bathroom is very outdated and in disrepair.

Scope: You and your friend have met to discuss options and have settled on the following: you will replace the bathtub, vanity/sink, toilet and all light fixtures. You will re-tile the shower, replace the linoleum with tile flooring and re-paint the bathroom. You will also install GFIs, since the bathroom currently has none.

Cost: Your budget is $6,000. Budget is extremely important and cannot be exceeded. You plan to do most of the work yourself at a low hourly rate, which will help meet this tight budget. The customer will also help with some tasks.

Schedule: You hope to have this project completed within 30 days but some schedule slippage is allowed if needed. The project will start on Month 1, day 15.

Quality: Quality is important and your friend has selected good quality materials to ensure a long life for this new bathroom space. If money becomes an issue, your friend will consider reducing the quality of some materials.

Project Charter

Please use the information provided above to complete your charter.

WBS

For the WBS, use the info provided in the project task info table below. You must also define what your deliverable(s) will be for each task and which of your stakeholders will be responsible, accountable, informed, consulted for each task. Your stakeholders are: project manager (you), customer (your friend), sponsor (your friend’s parents who are paying for most of the project), plumber, electrician and contractor (to supplement labor as needed). The following table contains the activities you will execute for your project. NOTE: Do not add or delete tasks. This is the list of activities everyone must use.

Task

Dur (days)

Owner

Pred

Succ

Demo: Remove tub, toilet, vanity/sink, shower tile and light fixtures

2

PM

None

Paint, Re-tile shower

Paint

2

Customer

Demo

Install light fixtures and GFIs, Install new tub, toilet, vanity/sink

Install new tub, toilet, vanity/sink

3

PM

Paint

Lay flooring

Install light fixtures and GFIs

1

PM

Paint

Walk-through and punch-list creation with customer

Re-tile shower

2

PM

Demo

Walk-through and punch-list creation with customer

Lay new flooring

3

Customer

Install new tub, toilet, vanity/sink

Walk-through and punch-list creation with customer

Walk-through and punch-list creation with customer

1

PM

Install light fixtures and GFIs, Re-tile shower, Lay new flooring

Address all punch-list items

Address all punch-list items

2

PM

Walk-through and punch-list creation with customer

Turnover bathroom to customer.

Turnover bathroom to customer.

1

PM

Address all punch-list items

None

PERT Diagram

Use the info in your WBS to create your PERT diagram

Risk plan

Identify at least 6 key risks that you feel might impact your project, define risk triggers, rate/rank the risks and develop response strategies and contingency plans.

Project Budget

Planned efforts for stakeholders are provided in the following table.

To complete the Budget, please use the following costs for labor rates; Customer $10.00/hour, Contractors, Plumber and Electrician $50/hour and you as Project Manager $15.00/hour.

Task

Stakeholders/ Planned effort

Demo: Remove tub, toilet, vanity/sink, shower tile and light fixtures

Project manager- 12 hours, Customer- 8 hours, Contractor- 4 hours

Paint

Customer- 12 hours $45 materials

Install new tub, toilet, vanity/sink

Project manager- 12 hours, Customer- 10 hours, Plumber- 4 hours, Contractor- 8 hours, $1250 materials

Install light fixtures and GFIs

Project manager- 2 hours, Electrician- 12 hours, $420 materials

Re-tile shower

Project manager- 12 hours, Customer- 8 hours, $285 materials

Lay new flooring

Customer- 20 hours, Contractor- 4 hours, $875 materials

Walk-through and punch-list creation with customer

Project manager- 1 hour, Customer- 1 hour

Address all punch-list items

Project manager- 4 hours, Customer- 2 hours, Contractor- 2 hours

Turnover bathroom to customer

Project manager- 1 hour, Customer- 1 hour

Project Schedule

Your first project task will begin on Day 15 of Month 1. Please use the calendar provided below when setting your schedule dates.

Month 1 Month 2 Month 3

S

M

T

W

T

F

S

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

S

M

T

W

T

F

S

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

S

M

T

W

T

F

S

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

Non Work Days

Project update cycles

Update cycle information will be provided to you by the instructor 1-2 weeks prior to the due date of the update cycle. Please keep in mind the priorities you chose for your project (Cost, Time, Quality) as you make recommendations for your update cycles. You will need to discuss those priorities in each update cycle.

Final report

The final report must be 1000 words minimum. Please be creative in the creation of the final paper. Please demonstrate your understanding of Project Management terminology and theories. The exact format of and application used for the final report is at the discretion of the student but the report must address the following:

Project Closure (30 pts):

· Brief description of project closure and what value you think proper closure adds to a project.

· Identify what your project objectives and goals were (from Charter) and whether or not those were met. If something was not met, discuss why.

· Identify your intended project scope and deliverables were (from Charter). Discuss any changes (if there were any) to the scope baseline and how those changes positively or negatively impacted the project.

· Identify what your intended project benefits were (from Charter) and whether or not the benefits were achieved. Also, highlight any unintended consequences (negative impacts) that occurred during execution of the project.

· Compare project baseline schedule (from Project plan) to final project schedule and point out any variations from that original plan. Provide reasons for variations, actions taken along the way to address/mitigate variations and whether or not those actions were effective. Discuss variances in relation to project priorities.

· Compare your planned cost (from Project plan) against the actual cost from Update cycle 3. Provide reasons for variations, actions taken along the way to address/mitigate variations and whether or not those actions were effective. Discuss variances in relation to project priorities.

· Discuss your top risks (from Risk plan) and whether or not those risks occurred. If so, did contingency plans work?

· Share the top 4 lessons you have learned during this class.

3