1. Seventeen gear boxes are on hand at the beginning of Week 1, and five gear boxes are currently on order to be delivered at the start of Week 2.
2. Forty input shafts are on hand at the start of Week 1, and 22 are scheduled for delivery at the beginning of Week 2.
Questions:
1.) Initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for- lot (L4L).
2.) Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. These costs are as follows:
Part Cost
Gear Box Setup 5 $90/order
Inventory carrying cost 5 $2/unit/week
Input Shaft Setup 5 $45/order
Inventory carrying cost 5 $1/unit/week
Model 1000 master schedule
Week 1 2 3 4 5 6 7 8 9 10 11 12
Demand 15 5 7 10 15 20 10 8 2 16
Model 1000 product structure
Engine assembly
Gear box
Crankcase Lead time = 2 weeks
Used: 1 per engine
Input shaft
Lead time = 3 weeks
Used: 2 per gear box
Given the cost structure, evaluate the cost of the schedule from question 1. Assume inventory is valued at the end of each week.
3.) Find a better schedule by reducing the number of orders and carrying some inventory. What are the savings with this new schedule?
Engine assembly master schedule
Week 1 2 3 4 5 6 7 8 9 10 11 12
Quantity
Gear box requirements
Week 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order release
Input shaft requirements
Week 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order release
This is what I have so far, not sure if it’s correct:
Gear box requirements
Week 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 15 5 7 10 15 20 10 8 2 16
Scheduled receipts 5 5 10 15 20 10 8 2 16
Projected available balance 2 2
Net requirements 5 10 15 20 10 8 2 16
Planned order release 5 10 15 20 10 8 2 16
Input shaft requirements
Week 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 10 20 30 40 20 16 4 32
Scheduled receipts 22 38 20 16 4 32
Projected available balance 30 32 32 2
Net requirements 38 20 16 4 32
Planned order release 38 20 16 4 32