Assignment Overview
This Assignment relates to the following Project:
19735 Project 1 Medium Rise Apartments
|
Job Address: |
2135 The Boulevard, Strathfield, NSW |
|
Job Title: |
Proposed Commercial and Residential Development |
|
Client: |
AKM Developments |
|
Architect: |
Olympic Designs, 55 Olympic Pde, Homebush, NSW |
You should obtain the following documents, from the OLS, for the job:
Plans: Page 1 Site Plan
Page 2 Basement 1
Page 3 Basement 2
Page 4 Basement 1 Setout
Page 5 Basement 2 Setout
Page 6 Floor Plan Level 1
Page 7 Floor Plan Level 2
Page 8 Floor Plan Level 3
Page 9 Floor Plan Level 4
Page 10 Floor Plan Level 5
Page 11 Setout Level 1 and 2
Page 12 Setout Level 3 and 4
Page 13 Setout Level 5
Page 14 South Elevation
Page 15 North Elevation
Page 16 East and West Elevations
Bill of Quantities: Preliminary Estimate (6 pages)
Specification of Works (60 pages)
Your Task for this assessment
Assume you are the construction manager for a building company contracted to build the Boulevard Strathfield Apartments project.
You should use the Precedence Diagram for the project that you prepared in CPCCBC5002A.
(If you did not complete CPCCBC5002A you will find the information to prepare the diagram at the end of this assessment as an appendix)
Review the overall target schedule for the project carefully, and answer the following questions:
1. Critique the program provided – find and discuss any inconsistencies that you can find. Would you ask for changes to be made, and why? (10 marks)
2. Overall is the schedule realistic or optimistic? (10 marks)
3. Would you accept the schedule and provide it to your client or architect? (10 marks)
4. Assume that construction activities have fallen behind program. Task compression is required. Select Two tasks and outline:
a. Time cost and compression impacts of working overtime each day. (10 marks)
b. Time cost and compression impacts of working 6 days per week. (10 marks)
c. Outline other ways to compress the project schedule (10 marks)
END OF ASSESSMENT
Appendix for students who have not completed CPOCCBC5002A.
Assignment Overview
This Assignment relates to the following Project:
19735 Project 1 Medium Rise Apartments
Job Address: 2135 The Boulevard, Strathfield, NSW
Job Title: Proposed Commercial and Residential Development
Client: AKM Developments
Architect: Olympic Designs, 55 Olympic Pde, Homebush, NSW
You should obtain the following documents, from the OLS, for the job:
Plans: Page 1 – Site Plan
Page 2 – Basement 1
Page 3 – Basement 2
Page 4 - Basement 1 Setout
Page 5 - Basement 2 Setout
Page 6 – Floor Plan Level 1
Page 7 - Floor Plan Level 2
Page 8 - Floor Plan Level 3
Page 9 - Floor Plan Level 4
Page 10 - Floor Plan Level 5
Page 11 – Setout Level 1 and 2
Page 12 - Setout Level 3 and 4
Page 13 - Setout Level 5
Page 14 – South Elevation
Page 15 - North Elevation
Page 16 – East and West Elevations
Bill of Quantities: Preliminary Estimate (6 pages)
Specification of Works (60 pages)
Question 1
Use the following information to prepare a Precedence Diagram to establish Early Start/Early Finish, Late Start/Late Finish, and Float and identify the critical path.
You can prepare the diagram manually or using a computer program such as Microsoft Project.
You should use a 5 day calendar to allow for the fact that this is a preliminary estimate. The project will work on a 6 day schedule once construction starts and this will provide a contingency allowance for the project.
The project is scheduled to start on 13th January 2014.
PROGRAM ACTIVITY SCHEDULE
|
ID |
Task Name |
Duration |
Predecessors |
|
1 |
Job Duration |
255 days |
|
|
2 |
Start |
0 days |
|
|
3 |
Preliminaries |
Whole of Job |
2 |
|
4 |
Groundworks |
20 days |
3 |
|
5 |
Concrete |
155 days |
|
|
6 |
Concrete Basement 2 |
17 days |
4,36,51 |
|
7 |
Concrete Basement 1 |
16 days |
6,14 |
|
8 |
Concrete Level 1 |
22 days |
7,15 |
|
9 |
Concrete Level 2 |
15 days |
8,24,16 |
|
10 |
Concrete Level 3 |
13 days |
9,25,17 |
|
11 |
Concrete Level 4 |
14 days |
10,26,18 |
|
12 |
Concrete Level 5 |
15 days |
4,11,27,19 |
|
13 |
Masonry |
144 days |
|
|
14 |
Masonry Basement 2 |
6 days |
6 |
|
15 |
Masonry Basement 1 |
4 days |
14,7 |
|
16 |
Masonry Level 1 |
11 days |
15,8 |
|
17 |
Masonry Level 2 |
8 days |
16,9 |
|
18 |
Masonry Level 3 |
6 days |
17,10 |
|
19 |
Masonry Level 4 |
8 days |
18,11 |
|
20 |
Masonry Level 5 |
6 days |
19,12 |
|
21 |
Metalwork |
197 days |
|
|
22 |
Metalwork Basement 2 |
2 days |
6,14SS+1 day |
|
23 |
Metalwork Basement 1 |
2 days |
22,15SS+1 day |
|
24 |
Metalwork level 1 Windows and Doors |
3 days |
23,16SS+1 day |
|
25 |
Metalwork level 2 Windows and Doors |
3 days |
24,17SS+1 day |
|
26 |
Metalwork level 3 Windows and Doors |
3 days |
25,18SS+1 day |
|
27 |
Metalwork level 4 Windows and Doors |
3 days |
26,19SS+1 day |
|
28 |
Metalwork level 5 Windows and Doors |
3 days |
27,20SS+1 day |
|
29 |
Metalwork level 1 Fitout |
3 days |
93,115 |
|
30 |
Metalwork level 2 Fitout |
3 days |
29,94,116 |
|
31 |
Metalwork level 3 Fitout |
3 days |
30,95,117 |
|
32 |
Metalwork level 4 Fitout |
3 days |
31,96,118 |
|
33 |
Metalwork level 5 Fitout |
3 days |
32,97,119 |
|
34 |
Hydraulics |
224 days |
|
|
35 |
Hydraulics Rough In Sub basement |
7 days |
4 |
|
36 |
Hydraulics Rough In Basement 2 |
7 days |
4 |
|
37 |
Hydraulics Rough In Basement 1 |
7 days |
36,6 |
|
38 |
Hydraulics Rough In Level 1 |
7 days |
37,7 |
|
39 |
Hydraulics Rough In Level 2 |
7 days |
38,8 |
|
40 |
Hydraulics Rough In Level 3 |
7 days |
39,9 |
|
41 |
Hydraulics Rough In Level 4 |
7 days |
40,10 |
|
42 |
Hydraulics Rough In Level 5 |
7 days |
41,11 |
|
43 |
Hydraulics Fitoff Basement 2 |
5 days |
115,42 |
|
44 |
Hydraulics Fitoff Basement 1 |
5 days |
43,115 |
|
45 |
Hydraulics Fitoff Level 1 |
5 days |
44,115 |
|
46 |
Hydraulics Fitoff Level 2 |
5 days |
45,116 |
|
47 |
Hydraulics Fitoff Level 3 |
5 days |
46,117 |
|
48 |
Hydraulics Fitoff Level 4 |
5 days |
47,118 |
|
49 |
Hydraulics Fitoff Level 5 |
5 days |
36,7,89,97,48,119 |
|
50 |
Electrical |
221 days |
|
|
51 |
Electrical Rough in Below Basement Level |
3 days |
4 |
|
52 |
Electrical Rough in Basement 2 |
2 days |
51,14 |
|
53 |
Electrical Rough in Basement 1 |
2 days |
52,15 |
|
54 |
Electrical Rough in Level 1 |
2 days |
53,16 |
|
55 |
Electrical Rough in Level 2 |
2 days |
54,17 |
|
56 |
Electrical Rough in Level 3 |
2 days |
55,18 |
|
57 |
Electrical Rough in Level 4 |
2 days |
56,19 |
|
58 |
Electrical Rough in Level 5 |
2 days |
57,20 |
|
59 |
Electrical Fitoff Basement 2 |
2 days |
52,91,58 |
|
60 |
Electrical Fitoff Basement 1 |
2 days |
59,53,92 |
|
61 |
Electrical Fitoff Level 1 |
2 days |
60,54,115 |
|
62 |
Electrical Fitoff Level 2 |
2 days |
61,55,116 |
|
63 |
Electrical Fitoff Level 3 |
2 days |
62,56,117 |
|
64 |
Electrical Fitoff Level 4 |
2 days |
63,57,118 |
|
65 |
Electrical Fitoff Level 5 |
2 days |
64,58,119 |
|
66 |
Mechanical |
138 days |
|
|
67 |
Mechanincal Rough in Lift |
5 days |
7 |
|
68 |
Mechanincal Fitoff Lift |
3 days |
67,97 |
|
69 |
Mechanincal Rough in AC to Basement 2 |
2 days |
7 |
|
70 |
Mechanincal Rough in AC to Basement 1 |
2 days |
69,8 |
|
71 |
Mechanincal Rough in AC to Level 1 |
2 days |
70,9 |
|
72 |
Mechanincal Rough in AC to Level 2 |
2 days |
71,10 |
|
73 |
Mechanincal Rough in AC to Level 3 |
2 days |
72,11 |
|
74 |
Mechanincal Rough in AC to Level 4 |
2 days |
73,12 |
|
75 |
Mechanincal Rough in AC to Level 5 |
2 days |
74,13 |
|
76 |
Mechanincal Fitoff to Basement 2 |
2 days |
91,75 |
|
77 |
Mechanincal Fitoff to Basement 1 |
2 days |
76,92 |
|
78 |
Mechanincal Fitoff to Level 1 |
2 days |
77,93 |
|
79 |
Mechanincal Fitoff to Level 2 |
2 days |
78,94 |
|
80 |
Mechanincal Fitoff to Level 3 |
2 days |
79,95 |
|
81 |
Mechanincal Fitoff to Level 4 |
2 days |
80,96 |
|
82 |
Mechanincal Fitoff to Level 5 |
2 days |
81,97 |
|
83 |
Waterproofing |
87 days |
|
|
84 |
Waterproofing to Level 1 |
2 days |
93FS+5 days |
|
85 |
Waterproofing to Level 2 |
2 days |
84,94FS+5 days |
|
86 |
Waterproofing to Level 3 |
2 days |
85,95FS+5 days |
|
87 |
Waterproofing to Level 4 |
2 days |
86,96FS+5 days |
|
88 |
Waterproofing to Level 5 |
2 days |
87,97FS+5 days |
|
89 |
Roofer |
7 days |
12,20 |
|
90 |
Plasterer |
143 days |
|
|
91 |
Plasterer to Basement 2 |
3 days |
14,52 |
|
92 |
Plasterer to Basement 1 |
3 days |
91,53 |
|
93 |
Plasterer to Level 1 |
5 days |
92,54 |
|
94 |
Plasterer to Level 2 |
5 days |
93,55 |
|
95 |
Plasterer to Level 3 |
5 days |
94,56 |
|
96 |
Plasterer to Level 4 |
5 days |
95,57 |
|
97 |
Plasterer to Level 5 |
5 days |
96,58 |
|
98 |
Carpenter Fitout |
19 days |
|
|
99 |
Carpenter Fitout to Basement 2 |
2 days |
76 |
|
100 |
Carpenter Fitout to Basement 1 |
2 days |
99,77 |
|
101 |
Carpenter Fitout to Level 1 |
3 days |
100,78 |
|
102 |
Carpenter Fitout to Level 2 |
3 days |
101,79 |
|
103 |
Carpenter Fitout to Level 3 |
3 days |
102,80 |
|
104 |
Carpenter Fitout to Level 4 |
3 days |
103,81 |
|
105 |
Carpenter Fitout to Level 5 |
3 days |
104,82 |
|
106 |
Painter |
53 days |
|
|
107 |
Painter to Basement 2 |
3 days |
59 |
|
108 |
Painter to Basement 1 |
3 days |
107,60 |
|
109 |
Painter to Level 1 |
4 days |
108,61 |
|
110 |
Painter to Level 2 |
4 days |
109,62 |
|
111 |
Painter to Level 3 |
4 days |
110,63 |
|
112 |
Painter to Level 4 |
4 days |
111,64 |
|
113 |
Painter to Level 5 |
4 days |
112,65 |
|
114 |
Ceramic Tiler |
40 days |
|
|
115 |
Ceramic Tiler to Level 1 |
8 days |
101,84FS+5 days |
|
116 |
Ceramic Tiler to Level 2 |
8 days |
115,102,85FS+5 days |
|
117 |
Ceramic Tiler to Level 3 |
8 days |
116,103,86FS+5 days |
|
118 |
Ceramic Tiler to Level 4 |
8 days |
117,104,87FS+5 days |
|
119 |
Ceramic Tiler to Level 5 |
8 days |
118,105,88FS+5 days |
|
120 |
Carpet |
40 days |
|
|
121 |
Carpet to Level 1 |
8 days |
109 |
|
122 |
Carpet to Level 2 |
8 days |
121,110 |
|
123 |
Carpet to Level 3 |
8 days |
122,111 |
|
124 |
Carpet to Level 4 |
8 days |
123,112 |
|
125 |
Carpet to Level 5 |
8 days |
124,113 |
|
126 |
Cleaner |
33 days |
|
|
127 |
Cleaner to Basement 2 |
1 day |
109,121 |
|
128 |
Cleaner to Basement 1 |
1 day |
109,121 |
|
129 |
Cleaner to Level 1 |
1 day |
109,121 |
|
130 |
Cleaner to Level 2 |
1 day |
129,110,122 |
|
131 |
Cleaner to Level 3 |
1 day |
130,111,123 |
|
132 |
Cleaner to Level 4 |
1 day |
131,112,124 |
|
133 |
Cleaner to Level 5 |
1 day |
132,113,125 |
|
134 |
External Works |
21 days |
97 |
|
135 |
Finish |
0 days |
133,134 |
20161021092937q1__monitor_costing_systems_gantt_chart.pdf
Start
Milestone Date: Mon 13/01/14 ID: 2
Preliminaries Start: 13/01/14 ID: 3 Finish: 2/01/15 Dur: 255 days Res:
Groundworks Start: 13/01/14 ID: 4 Finish: 7/02/14 Dur: 20 days Res:
Concrete Basement 2 Start: 19/02/14 ID: 6 Finish: 13/03/14 Dur: 17 days Res:
Concrete Basement 1 Start: 24/03/14 ID: 7 Finish: 14/04/14 Dur: 16 days Res:
Concrete Level 1 Start: 21/04/14 ID: 8 Finish: 20/05/14 Dur: 22 days Res:
Concrete Level 2 Start: 5/06/14 ID: 9 Finish: 25/06/14 Dur: 15 days Res:
Concrete Level 3 Start: 8/07/14 ID: 10 Finish: 24/07/14 Dur: 13 days Res:
Concrete Level 4 Start: 4/08/14 ID: 11 Finish: 21/08/14 Dur: 14 days Res:
Concrete Level 5 Start: 3/09/14 ID: 12 Finish: 23/09/14 Dur: 15 days Res:
Masonry Start: Fri 14/03/14ID: 13 Finish: Wed 1/10/1Dur: 144 days Comp: 0%
Masonry Basement 2 Start: 14/03/14 ID: 14 Finish: 21/03/14 Dur: 6 days Res:
Masonry Basement 1 Start: 15/04/14 ID: 15 Finish: 18/04/14 Dur: 4 days Res:
Masonry Level 1 Start: 21/05/14 ID: 16 Finish: 4/06/14 Dur: 11 days Res:
Masonry Level 2 Start: 26/06/14 ID: 17 Finish: 7/07/14 Dur: 8 days Res:
Masonry Level 3 Start: 25/07/14 ID: 18 Finish: 1/08/14 Dur: 6 days Res:
Masonry Level 4 Start: 22/08/14 ID: 19 Finish: 2/09/14 Dur: 8 days Res:
Masonry Level 5 Start: 24/09/14 ID: 20 Finish: 1/10/14 Dur: 6 days Res:
Metalwork Start: Mon 17/03/1ID: 21 Finish: Wed 10/12/Dur: 193 days Comp: 0%
Metalwork Basement 2 Start: 17/03/14 ID: 22 Finish: 18/03/14 Dur: 2 days Res:
Metalwork Basement 1 Start: 16/04/14 ID: 23 Finish: 17/04/14 Dur: 2 days Res:
Metalwork level 1 Windows and Door Start: 22/05/14 ID: 24 Finish: 26/05/14 Dur: 3 days Res:
Metalwork level 2 Windows and Door Start: 27/06/14 ID: 25 Finish: 1/07/14 Dur: 3 days Res:
Metalwork level 3 Windows and Door Start: 28/07/14 ID: 26 Finish: 30/07/14 Dur: 3 days Res:
Metalwork level 4 Windows and Door Start: 25/08/14 ID: 27 Finish: 27/08/14 Dur: 3 days Res:
Metalwork level 5 Windows and Door Start: 25/09/14 ID: 28 Finish: 29/09/14 Dur: 3 days Res:
Metalwork level 1 Fitout Start: 23/10/14 ID: 29 Finish: 27/10/14 Dur: 3 days Res:
Metalwork level 2 Fitout Start: 4/11/14 ID: 30 Finish: 6/11/14 Dur: 3 days Res:
Metalwork level 3 Fitout Start: 14/11/14 ID: 31 Finish: 18/11/14 Dur: 3 days Res:
Metalwork level 4 Fitout Start: 26/11/14 ID: 32 Finish: 28/11/14 Dur: 3 days Res:
Metalwork level 5 Fitout Start: 8/12/14 ID: 33 Finish: 10/12/14 Dur: 3 days Res:
Hydraulics Start: Mon 10/02/1ID: 34 Finish: Fri 12/12/14Dur: 220 days Comp: 0%
Hydraulics Rough In Sub basement Start: 10/02/14 ID: 35 Finish: 18/02/14 Dur: 7 days Res:
Hydraulics Rough In Basement 2 Start: 10/02/14 ID: 36 Finish: 18/02/14 Dur: 7 days Res:
Hydraulics Rough In Basement 1 Start: 14/03/14 ID: 37 Finish: 24/03/14 Dur: 7 days Res:
Hydraulics Rough In Level 1 Start: 15/04/14 ID: 38 Finish: 23/04/14 Dur: 7 days Res:
Hydraulics Rough In Level 2 Start: 21/05/14 ID: 39 Finish: 29/05/14 Dur: 7 days Res:
Hydraulics Rough In Level 3 Start: 26/06/14 ID: 40 Finish: 4/07/14 Dur: 7 days Res:
Hydraulics Rough In Level 4 Start: 25/07/14 ID: 41 Finish: 4/08/14 Dur: 7 days Res:
Hydraulics Rough In Level 5 Start: 22/08/14 ID: 42 Finish: 1/09/14 Dur: 7 days Res:
Hydraulics Fitoff Basement 2 Start: 23/10/14 ID: 43 Finish: 29/10/14 Dur: 5 days Res:
Hydraulics Fitoff Basement 1 Start: 30/10/14 ID: 44 Finish: 5/11/14 Dur: 5 days Res:
Hydraulics Fitoff Level 1 Start: 6/11/14 ID: 45 Finish: 12/11/14 Dur: 5 days Res:
Hydraulics Fitoff Level 2 Start: 13/11/14 ID: 46 Finish: 19/11/14 Dur: 5 days Res:
Hydraulics Fitoff Level 3 Start: 20/11/14 ID: 47 Finish: 26/11/14 Dur: 5 days Res:
Hydraulics Fitoff Level 4 Start: 27/11/14 ID: 48 Finish: 3/12/14 Dur: 5 days Res:
Hydraulics Fitoff Level 5 Start: 8/12/14 ID: 49 Finish: 12/12/14 Dur: 5 days Res:
Electrical Start: Mon 10/02/1ID: 50 Finish: Tue 9/12/14Dur: 217 days Comp: 0%
Electrical Rough in Below Basement Le Start: 10/02/14 ID: 51 Finish: 12/02/14 Dur: 3 days Res:
Electrical Rough in Basement 2 Start: 24/03/14 ID: 52 Finish: 25/03/14 Dur: 2 days Res:
Electrical Rough in Basement 1 Start: 21/04/14 ID: 53 Finish: 22/04/14 Dur: 2 days Res:
Electrical Rough in Level 1 Start: 5/06/14 ID: 54 Finish: 6/06/14 Dur: 2 days Res:
Electrical Rough in Level 2 Start: 8/07/14 ID: 55 Finish: 9/07/14 Dur: 2 days Res:
Electrical Rough in Level 3 Start: 4/08/14 ID: 56 Finish: 5/08/14 Dur: 2 days Res:
Electrical Rough in Level 4 Start: 3/09/14 ID: 57 Finish: 4/09/14 Dur: 2 days Res:
Electrical Rough in Level 5 Start: 2/10/14 ID: 58 Finish: 3/10/14 Dur: 2 days Res:
Electrical Fitoff Basement 2 Start: 6/10/14 ID: 59 Finish: 7/10/14 Dur: 2 days Res:
Electrical Fitoff Basement 1 Start: 8/10/14 ID: 60 Finish: 9/10/14 Dur: 2 days Res:
Electrical Fitoff Level 1 Start: 23/10/14 ID: 61 Finish: 24/10/14 Dur: 2 days Res:
Electrical Fitoff Level 2 Start: 4/11/14 ID: 62 Finish: 5/11/14 Dur: 2 days Res:
Electrical Fitoff Level 3 Start: 14/11/14 ID: 63 Finish: 17/11/14 Dur: 2 days Res:
Electrical Fitoff Level 4 Start: 26/11/14 ID: 64 Finish: 27/11/14 Dur: 2 days Res:
Electrical Fitoff Level 5 Start: 8/12/14 ID: 65 Finish: 9/12/14 Dur: 2 days Res:
Mechanical Start: Tue 15/04/14ID: 66 Finish: Fri 17/10/14Dur: 134 days Comp: 0%
Mechanincal Rough in Lift Start: 15/04/14 ID: 67 Finish: 21/04/14 Dur: 5 days Res:
Mechanincal Fitoff Lift Start: 13/10/14 ID: 68 Finish: 15/10/14 Dur: 3 days Res:
Mechanincal Rough in AC to Basemen Start: 15/04/14 ID: 69 Finish: 16/04/14 Dur: 2 days Res:
Mechanincal Rough in AC to Basemen Start: 21/05/14 ID: 70 Finish: 22/05/14 Dur: 2 days Res:
Mechanincal Rough in AC to Level 1 Start: 26/06/14 ID: 71 Finish: 27/06/14 Dur: 2 days Res:
Mechanincal Rough in AC to Level 2 Start: 25/07/14 ID: 72 Finish: 28/07/14 Dur: 2 days Res:
Mechanincal Rough in AC to Level 3 Start: 22/08/14 ID: 73 Finish: 25/08/14 Dur: 2 days Res:
Mechanincal Rough in AC to Level 4 Start: 24/09/14 ID: 74 Finish: 25/09/14 Dur: 2 days Res:
Mechanincal Rough in AC to Level 5 Start: 26/09/14 ID: 75 Finish: 29/09/14 Dur: 2 days Res:
Mechanincal Fitoff to Basement 2 Start: 30/09/14 ID: 76 Finish: 1/10/14 Dur: 2 days Res:
Mechanincal Fitoff to Basement 1 Start: 2/10/14 ID: 77 Finish: 3/10/14 Dur: 2 days Res:
Mechanincal Fitoff to Level 1 Start: 6/10/14 ID: 78 Finish: 7/10/14 Dur: 2 days Res:
Mechanincal Fitoff to Level 2 Start: 8/10/14 ID: 79 Finish: 9/10/14 Dur: 2 days Res:
Mechanincal Fitoff to Level 3 Start: 10/10/14 ID: 80 Finish: 13/10/14 Dur: 2 days Res:
Mechanincal Fitoff to Level 4 Start: 14/10/14 ID: 81 Finish: 15/10/14 Dur: 2 days Res:
Mechanincal Fitoff to Level 5 Start: 16/10/14 ID: 82 Finish: 17/10/14 Dur: 2 days Res:
Waterproofing Start: Mon 23/06/1ID: 83 Finish: Tue 21/10/1Dur: 87 days Comp: 0%
Waterproofing to Level 1 Start: 23/06/14 ID: 84 Finish: 24/06/14 Dur: 2 days Res:
Waterproofing to Level 2 Start: 24/07/14 ID: 85 Finish: 25/07/14 Dur: 2 days Res:
Waterproofing to Level 3 Start: 20/08/14 ID: 86 Finish: 21/08/14 Dur: 2 days Res:
Waterproofing to Level 4 Start: 19/09/14 ID: 87 Finish: 22/09/14 Dur: 2 days Res:
Waterproofing to Level 5 Start: 20/10/14 ID: 88 Finish: 21/10/14 Dur: 2 days Res:
Roofer Start: 2/10/14 ID: 89 Finish: 10/10/14 Dur: 7 days Res:
Plasterer Start: Wed 26/03/1ID: 90 Finish: Fri 10/10/14Dur: 143 days Comp: 0%
Plasterer to Basement 2 Start: 26/03/14 ID: 91 Finish: 28/03/14 Dur: 3 days Res:
Plasterer to Basement 1 Start: 23/04/14 ID: 92 Finish: 25/04/14 Dur: 3 days Res:
Plasterer to Level 1 Start: 9/06/14 ID: 93 Finish: 13/06/14 Dur: 5 days Res:
Plasterer to Level 2 Start: 10/07/14 ID: 94 Finish: 16/07/14 Dur: 5 days Res:
Plasterer to Level 3 Start: 6/08/14 ID: 95 Finish: 12/08/14 Dur: 5 days Res:
Plasterer to Level 4 Start: 5/09/14 ID: 96 Finish: 11/09/14 Dur: 5 days Res:
Plasterer to Level 5 Start: 6/10/14 ID: 97 Finish: 10/10/14 Dur: 5 days Res:
Carpenter Fitout Start: Thu 2/10/14ID: 98 Finish: Tue 28/10/1Dur: 19 days Comp: 0%
Carpenter Fitout to Basement 2 Start: 2/10/14 ID: 99 Finish: 3/10/14 Dur: 2 days Res:
Carpenter Fitout to Basement 1 Start: 6/10/14 ID: 100 Finish: 7/10/14 Dur: 2 days Res:
Carpenter Fitout to Level 1 Start: 8/10/14 ID: 101 Finish: 10/10/14 Dur: 3 days Res:
Carpenter Fitout to Level 2 Start: 13/10/14 ID: 102 Finish: 15/10/14 Dur: 3 days Res:
Carpenter Fitout to Level 3 Start: 16/10/14 ID: 103 Finish: 20/10/14 Dur: 3 days Res:
Carpenter Fitout to Level 4 Start: 21/10/14 ID: 104 Finish: 23/10/14 Dur: 3 days Res:
Carpenter Fitout to Level 5 Start: 24/10/14 ID: 105 Finish: 28/10/14 Dur: 3 days Res:
Painter Start: Wed 8/10/14ID: 106 Finish: Mon 15/12/Dur: 49 days Comp: 0%
Painter to Basement 2 Start: 8/10/14 ID: 107 Finish: 10/10/14 Dur: 3 days Res:
Painter to Basement 1 Start: 13/10/14 ID: 108 Finish: 15/10/14 Dur: 3 days Res:
Painter to Level 1 Start: 27/10/14 ID: 109 Finish: 30/10/14 Dur: 4 days Res:
Painter to Level 2 Start: 6/11/14 ID: 110 Finish: 11/11/14 Dur: 4 days Res:
Painter to Level 3 Start: 18/11/14 ID: 111 Finish: 21/11/14 Dur: 4 days Res:
Painter to Level 4 Start: 28/11/14 ID: 112 Finish: 3/12/14 Dur: 4 days Res:
Painter to Level 5 Start: 10/12/14 ID: 113 Finish: 15/12/14 Dur: 4 days Res:
Ceramic Tiler Start: Mon 13/10/1ID: 114 Finish: Fri 5/12/14 Dur: 40 days Comp: 0%
Ceramic Tiler to Level 1 Start: 13/10/14 ID: 115 Finish: 22/10/14 Dur: 8 days Res:
Ceramic Tiler to Level 2 Start: 23/10/14 ID: 116 Finish: 3/11/14 Dur: 8 days Res:
Ceramic Tiler to Level 3 Start: 4/11/14 ID: 117 Finish: 13/11/14 Dur: 8 days Res:
Ceramic Tiler to Level 4 Start: 14/11/14 ID: 118 Finish: 25/11/14 Dur: 8 days Res:
Ceramic Tiler to Level 5 Start: 26/11/14 ID: 119 Finish: 5/12/14 Dur: 8 days Res:
Carpet Start: Fri 31/10/14ID: 120 Finish: Thu 25/12/1Dur: 40 days Comp: 0%
Carpet to Level 1 Start: 31/10/14 ID: 121 Finish: 11/11/14 Dur: 8 days Res:
Carpet to Level 2 Start: 12/11/14 ID: 122 Finish: 21/11/14 Dur: 8 days Res:
Carpet to Level 3 Start: 24/11/14 ID: 123 Finish: 3/12/14 Dur: 8 days Res:
Carpet to Level 4 Start: 4/12/14 ID: 124 Finish: 15/12/14 Dur: 8 days Res:
Carpet to Level 5 Start: 16/12/14 ID: 125 Finish: 25/12/14 Dur: 8 days Res:
Cleaner Start: Wed 12/11/1ID: 126 Finish: Fri 26/12/14Dur: 33 days Comp: 0%
Cleaner to Basement 2 Start: 12/11/14 ID: 127 Finish: 12/11/14 Dur: 1 day Res:
Cleaner to Basement 1 Start: 12/11/14 ID: 128 Finish: 12/11/14 Dur: 1 day Res:
Cleaner to Level 1 Start: 12/11/14 ID: 129 Finish: 12/11/14 Dur: 1 day Res:
Cleaner to Level 2 Start: 24/11/14 ID: 130 Finish: 24/11/14 Dur: 1 day Res:
Cleaner to Level 3 Start: 4/12/14 ID: 131 Finish: 4/12/14 Dur: 1 day Res:
Cleaner to Level 4 Start: 16/12/14 ID: 132 Finish: 16/12/14 Dur: 1 day Res:
Cleaner to Level 5 Start: 26/12/14 ID: 133 Finish: 26/12/14 Dur: 1 day Res:
External Works Start: 13/10/14 ID: 134 Finish: 10/11/14 Dur: 21 days Res:
Finish
Milestone Date: Fri 2/01/15 ID: 135
Concrete Start: Wed 19/02/1ID: 5 Finish: Tue 23/09/1Dur: 155 days Comp: 0%
Job Duration Start: Mon 13/01/1ID: 1 Finish: Fri 2/01/15 Dur: 255 days Comp: 0%
Page 1
20161021094610construction_program.pdf
ID Duration Start Finish Successors Resource Names
1 255 days Mon 13/01/14 Fri 2/01/15
2 0 days Mon 13/01/14 Mon 13/01/14 3,6,4
3 255 days Mon 13/01/14 Fri 2/01/15 135
4 20 days Mon 13/01/14 Fri 7/02/14 6,12,35,36,51
5 155 days Wed 19/02/14 Tue 23/09/14
6 17 days Wed 19/02/14 Thu 13/03/14 7,14,22,37
7 16 days Mon 24/03/14 Mon 14/04/14 8,15,38,49,67,69
8 22 days Mon 21/04/14 Tue 20/05/14 9,16,39,70
9 15 days Thu 5/06/14 Wed 25/06/14 10,17,40,71
10 13 days Tue 8/07/14 Thu 24/07/14 11,18,41,72
11 14 days Mon 4/08/14 Thu 21/08/14 12,19,42,73
12 15 days Wed 3/09/14 Tue 23/09/14 20,74,89
13 144 days Fri 14/03/14 Wed 1/10/14
14 6 days Fri 14/03/14 Fri 21/03/14 7,15,22SS+1 day,52,91
15 4 days Tue 15/04/14 Fri 18/04/14 8,16,23SS+1 day,53
16 11 days Wed 21/05/14 Wed 4/06/14 9,17,24SS+1 day,54
17 8 days Thu 26/06/14 Mon 7/07/14 10,18,25SS+1 day,55
18 6 days Fri 25/07/14 Fri 1/08/14 11,19,26SS+1 day,56
19 8 days Fri 22/08/14 Tue 2/09/14 12,20,27SS+1 day,57
20 6 days Wed 24/09/14 Wed 1/10/14 28SS+1 day,58,89
21 193 days Mon 17/03/14 Wed 10/12/14
22 2 days Mon 17/03/14 Tue 18/03/14 23
23 2 days Wed 16/04/14 Thu 17/04/14 24
17 days
20 days
24 days
D J F M A M J J A S O N D J F M
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015
Critical
Critical Split
Task
Split
Milestone
Slack
Slippage
Summary
Project Summary
Rolled Up Critical
Rolled Up Critical Split
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
ID Duration Start Finish Successors Resource Names
24 3 days Thu 22/05/14 Mon 26/05/14 9,25
25 3 days Fri 27/06/14 Tue 1/07/14 10,26
26 3 days Mon 28/07/14 Wed 30/07/14 11,27
27 3 days Mon 25/08/14 Wed 27/08/14 12,28
28 3 days Thu 25/09/14 Mon 29/09/14
29 3 days Thu 23/10/14 Mon 27/10/14 30
30 3 days Tue 4/11/14 Thu 6/11/14 31
31 3 days Fri 14/11/14 Tue 18/11/14 32
32 3 days Wed 26/11/14 Fri 28/11/14 33
33 3 days Mon 8/12/14 Wed 10/12/14
34 220 days Mon 10/02/14 Fri 12/12/14
35 7 days Mon 10/02/14 Tue 18/02/14
36 7 days Mon 10/02/14 Tue 18/02/14 6,37,49
37 7 days Fri 14/03/14 Mon 24/03/14 38
38 7 days Tue 15/04/14 Wed 23/04/14 39
39 7 days Wed 21/05/14 Thu 29/05/14 40
40 7 days Thu 26/06/14 Fri 4/07/14 41
41 7 days Fri 25/07/14 Mon 4/08/14 42
42 7 days Fri 22/08/14 Mon 1/09/14 43
43 5 days Thu 23/10/14 Wed 29/10/14 44
44 5 days Thu 30/10/14 Wed 5/11/14 45
45 5 days Thu 6/11/14 Wed 12/11/14 46
46 5 days Thu 13/11/14 Wed 19/11/14 47
7 days
4 days
2 days
4 days
69 days
5 days
5 days
5 days
5 days
17 days
228 days
15 days
19 days
19 days
14 days
13 days
37 days
D J F M A M J J A S O N D J F M
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015
Critical
Critical Split
Task
Split
Milestone
Slack
Slippage
Summary
Project Summary
Rolled Up Critical
Rolled Up Critical Split
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
ID Duration Start Finish Successors Resource Names
47 5 days Thu 20/11/14 Wed 26/11/14 48
48 5 days Thu 27/11/14 Wed 3/12/14 49
49 5 days Mon 8/12/14 Fri 12/12/14
50 217 days Mon 10/02/14 Tue 9/12/14
51 3 days Mon 10/02/14 Wed 12/02/14 6,52
52 2 days Mon 24/03/14 Tue 25/03/14 53,59,91
53 2 days Mon 21/04/14 Tue 22/04/14 54,60,92
54 2 days Thu 5/06/14 Fri 6/06/14 55,61,93
55 2 days Tue 8/07/14 Wed 9/07/14 56,62,94
56 2 days Mon 4/08/14 Tue 5/08/14 57,63,95
57 2 days Wed 3/09/14 Thu 4/09/14 58,64,96
58 2 days Thu 2/10/14 Fri 3/10/14 59,65,97
59 2 days Mon 6/10/14 Tue 7/10/14 60,107
60 2 days Wed 8/10/14 Thu 9/10/14 61,108
61 2 days Thu 23/10/14 Fri 24/10/14 62,109
62 2 days Tue 4/11/14 Wed 5/11/14 63,110
63 2 days Fri 14/11/14 Mon 17/11/14 64,111
64 2 days Wed 26/11/14 Thu 27/11/14 65,112
65 2 days Mon 8/12/14 Tue 9/12/14 113
66 134 days Tue 15/04/14 Fri 17/10/14
67 5 days Tue 15/04/14 Mon 21/04/14 68
68 3 days Mon 13/10/14 Wed 15/10/14
69 2 days Tue 15/04/14 Wed 16/04/14 70
2 days
15 days
4 days
1 day
55 days
124 days
57 days
24 days
D J F M A M J J A S O N D J F M
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015
Critical
Critical Split
Task
Split
Milestone
Slack
Slippage
Summary
Project Summary
Rolled Up Critical
Rolled Up Critical Split
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
ID Duration Start Finish Successors Resource Names
70 2 days Wed 21/05/14 Thu 22/05/14 71
71 2 days Thu 26/06/14 Fri 27/06/14 72
72 2 days Fri 25/07/14 Mon 28/07/14 73
73 2 days Fri 22/08/14 Mon 25/08/14 74
74 2 days Wed 24/09/14 Thu 25/09/14 75
75 2 days Fri 26/09/14 Mon 29/09/14 76
76 2 days Tue 30/09/14 Wed 1/10/14 77,99
77 2 days Thu 2/10/14 Fri 3/10/14 78,100
78 2 days Mon 6/10/14 Tue 7/10/14 79,101
79 2 days Wed 8/10/14 Thu 9/10/14 80,102
80 2 days Fri 10/10/14 Mon 13/10/14 81,103
81 2 days Tue 14/10/14 Wed 15/10/14 82,104
82 2 days Thu 16/10/14 Fri 17/10/14 105
83 87 days Mon 23/06/14 Tue 21/10/14
84 2 days Mon 23/06/14 Tue 24/06/14 85,115FS+5 days
85 2 days Thu 24/07/14 Fri 25/07/14 86,116FS+5 days
86 2 days Wed 20/08/14 Thu 21/08/14 87,117FS+5 days
87 2 days Fri 19/09/14 Mon 22/09/14 88,118FS+5 days
88 2 days Mon 20/10/14 Tue 21/10/14 119FS+5 days
89 7 days Thu 2/10/14 Fri 10/10/14 49
90 143 days Wed 26/03/14 Fri 10/10/14
91 3 days Wed 26/03/14 Fri 28/03/14 59,76,92
92 3 days Wed 23/04/14 Fri 25/04/14 60,77,93
24 days
19 days
18 days
21 days
4 days
20 days
21 days
17 days
20 days
19 days
20 days
40 days
20 days
17 days
30 days
D J F M A M J J A S O N D J F M
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015
Critical
Critical Split
Task
Split
Milestone
Slack
Slippage
Summary
Project Summary
Rolled Up Critical
Rolled Up Critical Split
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
ID Duration Start Finish Successors Resource Names
93 5 days Mon 9/06/14 Fri 13/06/14 29,78,84FS+5 days,94
94 5 days Thu 10/07/14 Wed 16/07/14 30,79,85FS+5 days,95
95 5 days Wed 6/08/14 Tue 12/08/14 31,80,86FS+5 days,96
96 5 days Fri 5/09/14 Thu 11/09/14 32,81,87FS+5 days,97
97 5 days Mon 6/10/14 Fri 10/10/14 33,49,68,82,88FS+5 days,134
98 19 days Thu 2/10/14 Tue 28/10/14
99 2 days Thu 2/10/14 Fri 3/10/14 100
100 2 days Mon 6/10/14 Tue 7/10/14 101
101 3 days Wed 8/10/14 Fri 10/10/14 102,115
102 3 days Mon 13/10/14 Wed 15/10/14 103,116
103 3 days Thu 16/10/14 Mon 20/10/14 104,117
104 3 days Tue 21/10/14 Thu 23/10/14 105,118
105 3 days Fri 24/10/14 Tue 28/10/14 119
106 49 days Wed 8/10/14 Mon 15/12/14
107 3 days Wed 8/10/14 Fri 10/10/14 108
108 3 days Mon 13/10/14 Wed 15/10/14 109
109 4 days Mon 27/10/14 Thu 30/10/14 110,121,127,128,129
110 4 days Thu 6/11/14 Tue 11/11/14 111,122,130
111 4 days Tue 18/11/14 Fri 21/11/14 112,123,131
112 4 days Fri 28/11/14 Wed 3/12/14 113,124,132
113 4 days Wed 10/12/14 Mon 15/12/14 125,133
114 40 days Mon 13/10/14 Fri 5/12/14
115 8 days Mon 13/10/14 Wed 22/10/14 29,43,44,45,61,116
20 days
7 days
D J F M A M J J A S O N D J F M
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015
Critical
Critical Split
Task
Split
Milestone
Slack
Slippage
Summary
Project Summary
Rolled Up Critical
Rolled Up Critical Split
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
ID Duration Start Finish Successors Resource Names
116 8 days Thu 23/10/14 Mon 3/11/14 30,46,62,117
117 8 days Tue 4/11/14 Thu 13/11/14 31,47,63,118
118 8 days Fri 14/11/14 Tue 25/11/14 32,48,64,119
119 8 days Wed 26/11/14 Fri 5/12/14 33,49,65
120 40 days Fri 31/10/14 Thu 25/12/14
121 8 days Fri 31/10/14 Tue 11/11/14 122,127,128,129
122 8 days Wed 12/11/14 Fri 21/11/14 123,130
123 8 days Mon 24/11/14 Wed 3/12/14 124,131
124 8 days Thu 4/12/14 Mon 15/12/14 125,132
125 8 days Tue 16/12/14 Thu 25/12/14 133
126 33 days Wed 12/11/14 Fri 26/12/14
127 1 day Wed 12/11/14 Wed 12/11/14
128 1 day Wed 12/11/14 Wed 12/11/14
129 1 day Wed 12/11/14 Wed 12/11/14 130
130 1 day Mon 24/11/14 Mon 24/11/14 131
131 1 day Thu 4/12/14 Thu 4/12/14 132
132 1 day Tue 16/12/14 Tue 16/12/14 133
133 1 day Fri 26/12/14 Fri 26/12/14 135
134 21 days Mon 13/10/14 Mon 10/11/14 135
135 0 days Fri 2/01/15 Fri 2/01/15
5 days
37 days
37 days
7 days
7 days
7 days
7 days
34 days
D J F M A M J J A S O N D J F M
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015
Critical
Critical Split
Task
Split
Milestone
Slack
Slippage
Summary
Project Summary
Rolled Up Critical
Rolled Up Critical Split
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress