1- roles and responsibilities 2- WBS dictionary

profileOm-rossol
project_directory.docx

Roles and Responsibilities

In order to successfully manage a projects’ scope it’s important that all roles and responsibilities for scope management are clearly defined. This section defines the role of the Project Manager, Project Team, Stakeholders and other key persons who are involved in managing the scope of the project. It should state who is responsible for scope management and who is responsible for accepting the deliverables of the project as defined by the projects’ scope. Any other roles in scope management should also be stated in this section.

The Project Manager, Sponsor and team will all play key roles in managing the scope of this project. As such, the project sponsor, manager, and team members must be aware of their responsibilities in order to ensure that work performed on the project is within the established scope throughout the entire duration of the project. The table below defines the roles and responsibilities for the scope management of this project.

Name

Role

Responsibilities

John Doe

Sponsor

· Approve or deny scope change requests as appropriate

· Evaluate need for scope change requests

· Accept project deliverables

Jane Doe

Project Manager

· Measure and verify project scope

· Facilitate scope change requests

· Facilitate impact assessments of scope change requests

· Organize and facilitate scheduled change control meetings

· Communicate outcomes of scope change requests

· Update project documents upon approval of all scope changes

Bob Jones

Team Lead

· Measure and verify project scope

· Validate scope change requests

· Participate in impact assessments of scope change requests

· Communicate outcomes of scope change requests to team

· Facilitate team level change review process

John Smith

Team Member

· Participate in defining change resolutions

· Evaluate the need for scope changes and communicate them to the project manager as necessary

Tom Brown

Team Member

· Participate in defining change resolutions

· Evaluate the need for scope changes and communicate them to the project manager as necessary

Table 1.1, Scope Management Roles and Responsibilities

WBS Dictionary

The WBS Dictionary contains all the details of the WBS which are necessary to successfully complete the project. Most importantly it contains a definition of each Work Package which can be thought of as a mini scope statement. Resources on the project will look at the WBS

Level

WBS Code

Element Name

Definition

1

1

Widget Management System

All work to implement a new widget management system.

2

1.1

Initiation

The work to initiate the project.

3

1.1.1

Evaluation & Recommendations

Working group to evaluate solution sets and make recommendations.

3

1.1.2

Develop Project Charter

Project Manager to develop the Project Charter.

3

1.1.3

Deliverable: Submit Project Charter

Project Charter is delivered to the Project Sponsor.

3

1.1.4

Project Sponsor Reviews Project Charter

Project sponsor reviews the Project Charter.

3

1.1.5

Project Charter Signed/Approved

The Project Sponsor signs the Project Charter which authorizes the Project Manager to move to the Planning Process.

2

1.2

Planning

The work for the planning process for the project.

3

1.2.1

Create Preliminary Scope Statement

Project Manager creates a Preliminary Scope Statement.

3

1.2.2

Determine Project Team

The Project Manager determines the project team and requests the resources.

3

1.2.3

Project Team Kickoff Meeting

The planning process is officially started with a project kickoff meeting which includes the Project Manager, Project Team and Project Sponsor (optional).

3

1.2.4

Develop Project Plan

Under the direction of the Project Manager the team develops the project plan.

3

1.2.5

Submit Project Plan

Project Manager submits the project plan for approval.

3

1.2.6

Milestone: Project Plan Approval

The project plan is approved and the Project Manager has permission to proceed to execute the project according to the project plan.

2

1.3

Execution

Work involved to execute the project.

3

1.3.1

Project Kickoff Meeting

Project Manager conducts a formal kick off meeting with the project team, project stakeholders and project sponsor.

3

1.3.2

Verify & Validate User Requirements

The original user requirements is reviewed by the project manager and team, then validated with the users/stakeholders. This is where additional clarification may be needed.

3

1.3.3

Design System

The technical resources design the new widget management system.

3

1.3.4

Procure Hardware/Software

The procurement of all hardware, software and facility needs for the project.

3

1.3.5

Install Development System

Team installs a development system for testing and customizations of user interfaces.

3

1.3.6

Testing Phase

The system is tested with a select set of users.

3

1.3.7

Install Live System

The actual system is installed and configured.

3

1.3.8

User Training

All users are provided with a four hours training class. Additionally, managers are provided with an additional two hours class to cover advanced reporting.

3

1.3.9

Go Live

System goes live with all users.

2

1.4

Control

The work involved for the control process of the project.

3

1.4.1

Project Management

Overall project management for the project.

3

1.4.2

Project Status Meetings

Weekly team status meetings.

3

1.4.3

Risk Management

Risk management efforts as defined in the Risk Management Plan.

3

1.4.4

Update Project Management Plan

Project Manager updates the Project Management Plan as the project progresses.

2

1.5

Closeout

The work to close-out the project.

3

1.5.1

Audit Procurement

An audit of all hardware and software procured for the project, ensures that all procured products are accounted for and in the asset management system.

3

1.5.2

Document Lessons Learned

Project Manager along with the project team performs a lessons learned meeting and documents the lessons learned for the project.

3

1.5.3

Update Files/Records

All files and records are updated to reflect the widget management system.

3

1.5.4

Gain Formal Acceptance

The Project Sponsor formally accepts the project by signing the acceptance document included in the project plan.

3

1.5.5

Archive Files/Documents

All project related files and documents are formally archived.

dictionary to determine the scope of the Work Package they've been assigned, so it's important to be clear when writing the definition. Most WBS dictionaries contain more information than we show in our sample. These things usually include Level of Effort, Cost Control Numbers, Resource Assignments, Responsibility Assignments