COMPLETE THESE SPREADSHEETS FOR A KNOWN CRITICAL INFRASTRUCTURE

profileabbey621
carver_tools_1_.pdf

CARVER   CARVER  is  a  methodology  first  used  by  the  Department  of  Defense  Special  Forces  to   rank  targets  so  that  their  resources  could  be  used  efficiently.  The  user  would   estimate  Criticality,  Accessibility,  Recuperability,  Vulnerability,  Effect,  and   Recognizability  as  nominal  scores  that  were  added  and  then  ranked.  The   methodology  was  later  adapted  for  Homeland  Security.  The  CARVER  tool  that  was   used  by  practitioners  had  proprietary  data  tables  behind  it  to  weigh  user  inputs   appropriately.  This  tool  makes  those  tables  available  so  that  the  user  can   experiment  with  weighting  and  modeling  if  desired.    

Using  the  Tool   For  this  simple  tool,  only  one  asset  can  be  evaluated  for  each  spreadsheet.  To   evaluate  a  set  of  assets,  we  recommend  making  a  number  of  copies  of  the  Excel  file   with  one  evaluation  for  each  file.  All  data  is  input  into  the  Worksheet  tab  while  all   the  tables  are  on  the  Tables  tab.  The  Menu  Items  and  Results  tabs  are  used  to   store  values  temporarily  and  are  it  is  not  recommended  that  users  modify  these.     To  begin,  input  enough  data  to  uniquely  identify  the  asset  to  be  evaluated.  This  is   not  used  in  any  calculation  so  not  all  is  required,  but  at  a  minimum,  a  unique  name  is   helpful.  You  may  also  place  this  asset  into  a  specific  sector.     Criticality  assesses  the  impact  of  the  loss  of  this  asset.  Note  that  CARVER  is  not   threat  mode  specific  so  you  are  to  consider  any  threat  possible.    

• Users  Affected  is  not  casualties,  but  rather  people  impacted  by  the  loss  of  this   asset.  If  it  is  a  bridge  and  100,000  people  will  not  be  able  to  get  to  work,  then   these  people  are  affected.    

• Economic  Loss  and  Rebuild  Cost  is  and  estimate  of  the  financial  damage   associated  with  the  loss  of  this  asset.  Economic  loss  and  rebuild  cost  are   summed  together  in  this  estimate,  so  be  sure  that  if  you  include  economic   loss  for  one  asset,  you  include  it  throughout  your  assessment.  

• Potential  Deaths  form  Attack  is  an  estimate  of  casualties  associated  with  an   attack  on  this  asset.  Again,  CARVER  is  not  threat  specific  so  assume  worst   case  scenario.  

  Accessibility  allows  you  to  indicate  what  security  may  be  in  place  to  limit  access  to   this  asset.  You  may  choose  from  Patrolled,  Perimeter  Fencing,  Armed  Security,   Unarmed  Security,  Access  Control,  Alarm  System,  Locked  Area,  Open  to  the  Public,   and  No  Control.     Recoverability  is  the  time  needed  to  replace  or  repair  this  asset,  if  possible.  Choose   an  estimate  from  the  menu.    

Vulnerability  is  the  susceptibility  of  this  asset  to  damage  or  destruction.  Ignore   anything  related  to  access  (we  covered  that  under  Accessibility)  and  focus  instead   on  features  of  the  asset  that  will  help  it  to  withstand  or  survive  an  attack.    

• Massive  refers  to  the  size  of  the  structure.  A  massive  structure,  like  a  major   bridge,  has  low  vulnerability  due  to  its  size.  

• Building  Purpose  Unknown  to  Public  would  be  like  a  water  pumping  station   that  looks  like  a  non-­‐descript  house  in  a  neighborhood.  

• Operations  Structurally  Dispersed  would  be  a  facility  that  has  a  back-­‐up   location  or  can  otherwise  function  without  all  of  its  parts  operating  at  the   same  time.  

• Concrete/Stone  refers  to  the  structural  material  used  in  the  asset.   • Structural  Steel  also  refers  to  the  structural  material  used  in  the  asset.   • Flammable/Explosive  should  be  selected  if  either  the  asset  itself  burns  easily  

or  if  it  contains  materials  that  burn  easily  or  are  potentially  explosive.     • Minor  Metal  Frame  again  refers  to  the  structural  material  used  in  the  asset.   • Wood  Design  refers  to  the  structural  material  used  in  the  asset.   • No  Security  Design  means  that  there  is  nothing  special  in  the  design  of  this  

asset  to  reduce  vulnerability.     Espyability  refers  to  whether  or  not  the  asset  is  merely  functional  or  if  it  has  iconic   status  at  the  Local,  State,  Regional,  National,  or  World  level.  Choose  from:  

• Locally  significant,  non-­‐government     • Locally  significant,  government   • State  icon  only   • State  icon  +  function   • Regional  icon  only   • Regional  icon  +  function   • National  icon  only   • National  icon  +  function   • World  icon  only   • World  icon  +  function  

  Redundancy  is  an  estimate  of  the  percentage  overlap  or  back-­‐up  capacity  there  is  to   offset  the  loss  of  this  asset.       Interdependency  is  a  list  of  sectors  that  might  be  interdependent  with  this  asset.   For  example,  if  this  is  a  power  station,  it  might  be  interdependent  with  the  water   sector,  commercial  facilities,  defense  industrial  base,  etc.  Interdependency  is  not   calculated  into  the  CARVER  score  but  is  represented  by  the  smaller  number  in  the   score.  A  CARVER  score  of  122-­‐5  means  that  this  asset  has  a  score  of  122  with  5   interdependencies.     CARVER  scores  are  calculated  but  are  dimensionless.  The  score  does  not  represent   Risk,  Resilience,  Vulnerability,  or  anything  else.  The  higher  the  score,  the  more  likely  

that  asset  may  require  resourcing.  But  you  cannot  say  that  an  asset  with  a  score  of   100  is  half  as  important  as  an  asset  with  a  score  of  200.    

Modifications   The  best  place  to  experiment  with  CARVER  is  in  the  Tables  tab.  Here  you  will  see  all   of  the  categories  we  just  described  here  with  all  of  the  items  in  the  menus  that  you   can  select.  Notice  that  for  each  menu  selection,  there  is  an  associated  Score.    Do  not   change  the  Value  column.  That  is  there  as  an  identifier  for  that  menu  selection.  But   do  experiment  with  changing  the  Scores.       Should  a  criticality  that  impacts  500,000  people  (score  of  40)  be  only  four  times   higher  than  that  for  25,000  people  (score  of  10)?  Maybe  it  should  be  higher.   Experiment  with  changing  scores.  Test  your  configurations  with  a  set  of  assets  to   make  sure  that  it  makes  sense.  Does  the  overall  CARVER  score  go  up  when  you   expect  it  to?  Does  it  decrease  when  you  expect  it  to?  By  default,  the  data  tables  we   provide  are  all  independent  but  they  don’t  have  to  be.  You  could  experiment  by   having  a  score  linked  to  another  value.  For  example,  what  if  you  wanted  the   Criticality  score  to  be  higher  if  the  Recoverability  time  was  longer?  How  would  you   do  that?