Activity Description Immediate Predecessor Duration
A Receive raw materials - 0.5
B Bolt cutting A 1.0
C Transfer Machine (series of drilling and cutting operations) A 1.5
D Transfer Machine (barrells) B 1.4
E Barrel pinning D 1.2
F Shackle groove cutting B 0.8
G Shackle bending F 1.0
H Inset Shackle into body C, E, G 0.4
I Insert barrel into body and test key set H 1.4
J Packaging of padlock I 0.5