MS Project assignment

profileariel-di
project_assignment_f2015-updated.pdf

SCM435 – Project Management

MICROSOFT PROJECT ASSIGNMENT (COMBINED)

THE PALMERS GOLF COURSE PROJECT

Project background

Palmers Golf Course is a two-year-old signature golf course based in Auckland, NZ. Being unique, the

number of memberships is increasing and putting strain on the existing information system.

The current system is used only by Accounts Department to process Accounts Payables and Receivables.

With the steep increase in the memberships, Bookings and Maintenance the Human Resource department is

getting overwhelmed with the paper work. Therefore, there is a need to add these functions to a new system.

You are the Project Leader for SoftSystems Ltd., which has been contracted by Palmers Golf Course to

undertake this project. You need to advise how to develop the new system in a tightly constrained time

period. Specifically, you have been advised that the project can start no earlier than Mon, January 4th 2016

and must be completed by Thu, May 19th 2016.

You report to Ms Smith, the Project Manager for SoftSystems Ltd, who liaises with Palmers Golf Course.

You will report your progress and plans of the project to Ms Smith.

Note: There is a lot of information included to provide context for what you will do in this assignment.

Please read carefully, and thoroughly to ensure the directions are followed. Also, to make it more clear, the

steps that you will perform in Microsoft Project are all written in the Courier New font.

Setting the Project Start Date

Click on the Project Tab in the Ribbon, and then go to Project

Information. Set the project start date to Mon, January 4th 2016. Do NOT

enter finish date. Click OK.

Setting default values

 Set Current Date

The computer's internal clock initially determines the date listed in the Current Date text box.

To access the Current Date, click again on the Project Tab, then Project

Information.

The current date box appears. Changing this date box has several implications:

• The date determines the location of the dashed (current) date line on the Gantt chart timeline.

• The Current Date appears in the header of the Project Summary standard report. You can also display the

Current Date in headers or footers on other reports.

• You can use the Current Date to track the progress of the project, specifically to record the progress of all

tasks scheduled to be in progress or finished as of the date in the Current Date text box.

For this assignment, you will, initially, leave the Current Date as defined by the computer clock, please

check that it is correct.

Click OK, to close the Project Information box.

Click on File, then in Project Information, choose Advanced Properties,

then Summary tab and in the Title box type PALMERS GOLF COURSE. This names the

project, which will then appear on your printouts. You should also enter your name (Author) and other

optional data.

 Set the Calendar

The calendar in this assignment should match the New Zealand calendar by the addition of non-working

days. Setting a new calendar can be done either (a) by modifying the standard calendar or (b) by creating a

new base calendar. You will do the latter (b).

Microsoft Calendars

Microsoft Project can support a large number of projects including large, complex projects, which are

usually broken down into sub-projects. Changing the working days on the standard calendar affects all

projects, with potentially unanticipated consequences. Therefore, each project should have its own base

calendar.

• Microsoft Project contains an internal standard calendar that defines the default working and non-

working days used for scheduling tasks in your projects. It assumes five working days per week,

Monday - Friday, eight hours of work per day (including an hour off for lunch). The default schedule is

8:00am to 12:00pm and 1:00pm to 5:00pm. No statutory holidays are set in the original standard

calendar.

• The standard calendar forms the basis for the base calendar, which applies to all resources in a project. It

would recognise special dates or circumstances that apply to a specific project. In this assignment the

base calendar will account for statutory holidays.

• The Base calendar is the basis for resource calendars, which apply to specific resources (groups of

people, material, equipment, facilities required to complete a project). Each resource has its own

calendar, which is linked to a designated base calendar (by default the standard calendar). A resource

calendar inherits all the elements of its base calendar. It can be edited to record the days and hours when

the availability of the resource differs from the normal working times such as holidays, differing hours of

work on particular days, or availability of special equipment.

Microsoft Project uses the base calendar and the resource calendars to schedule the start dates for tasks.

When Microsoft Project schedules a task, it notes the earliest possible starting date, based on when the

predecessors to the task will be completed. If resources are required, Microsoft Project consults the resource

calendars to find when they are available and the task is scheduled to start on the next available working

hour for the assigned resources. If no resources are assigned, the project's base calendar is used to schedule

the start and finish of the task.

In this assignment, a group of senior secondary students who are undergoing work experience training will

be made available to assist you in this project. They will be available two afternoons per week. The resource

calendar for these students would initially show them as having the same hours as the base calendar but

would be modified to increase the number of non-working days and show afternoon working hours only.

 Set the Working Time

Note:

• The software checks all time entries for consistency. Each successive time must be later in the day than

the preceding time text box.

• You must use the top From and To text boxes first, only then can you fill the bottom pair. You cannot

leave the top work period row blank.

• You can restore default working hours by clicking on the default button.

• To change more than one day at a time, hold down the ctrl key and click on non-contiguous days; or hold

down the shift key and click to select a block of days. Now your time entries will affect all the selected

days.

• Use either the 24-hour clock, or the 12-hour clock using am and pm suffixes to enter times. If you enter a

time without using an am or pm suffix, the computer uses the first instance of the time following the

Default Start Time. If that is 8:00 am then 3:30 without a suffix is assumed to be 3:30 in the afternoon

and a pm suffix is attached.

• A shortcut hint: on the hour, enter 10 for 10:00 am, and 5 pm for 5:00 pm.

• Noon is entered as 12:00 pm and midnight as 12:00 am.

• To remove a work period delete both the From time and the To time for the period.

 Set the Project Calendar

You will now create a calendar for this project by accounting for the extra non-working times reflected by

statutory holidays.

1. Go to Project Tab in the Ribbon, then click on Change Working Time. 2. Click the Create New Calendar … button at the top right corner. 3. The "Create New Base Calendar" box appears. Enter ‘Palmers Calendar’

in the Name text box.

4. Choose the Create New Base Calendar button and click OK. 5. We will only change holidays, (non-working days) on this calendar.

Scroll to Mon February 1st 2016 (Auckland Anniversary Day), Select that

date, then in the Exceptions Tab in the entry area below, enter

“Auckland Anniversary Day” in the Name field, and then make sure the

Start and Finish date are correct. Repeat this process for:

 Mon February 8th 2016 (Waitangi Day)

 Fri March 25th 2016 (Good Friday)

 Mon March 28th 2016 (Easter Monday)

 Mon April 25th 2016 (Anzac Day)

6. Check the calendar and ensure you have made no errors when entering

the non-working days. Click OK.

7. Choose Timescale dropdown menu from the View Tab in the Ribbon and select Timescale, then click on the Nonworking Time Tab. Click on the

Calendar pull down menu and select Palmers Calendar. Click OK.

8. Within the Project Information box from the Project menu select Palmers Calendar from the Calendar pull down menu. Click OK. This

assigns the Palmers Calendar as the base calendar for this project.

Setting a Finish Date

The Project Information box (choose Project, Project Information) can give you a global view of the whole

project and you can do "what if" type scenarios from this box. For example, you could enter either a start

date or a finish date in the Project Information box to function as an anchor point for scheduling the tasks in

the project. If you enter the start date, Microsoft Project schedules the first task in the project to begin at that

date and calculates the project's finish date based on that starting date. If you enter the finish date, Microsoft

Project schedules the tasks at the end of the project first and works backward. The final task is scheduled to

end by the finish date; the task that precedes the final task is scheduled to end in time for the final task to

begin, and so on. You cannot specify both a start date and a finish date.

Most projects have a deadline. If you don't intend to assign resources or you do not need Microsoft Project to

help you reconcile resource overloads, you can safely schedule the project from a fixed finish date. Most

projects also have limited resources. If you want the program to help you adjust the schedule to resolve

resource overloads (levelling) you must schedule the project from a fixed start date. This is the approach you

will adopt in the assignment.

 Set the Gantt chart bar display

Click on the following in sequence to set the Gantt chart bar display:

1. Gantt Chart Tools Tab 2. Format Tab 3. Make sure the Critical Tasks checkbox is Checked:

What did this do? Now when tasks are added to the Gantt chart the bars will be coloured red if they are on

the critical path and when duration and links are added to the project you will be able to readily identify on

the screen what tasks lie on the critical path. When the project actually gets underway, you will be using a

different Gantt chart display to highlight any variances between ‘planned’ and ‘actual’ activity on the tasks.

Enter tasks in the schedule

The first step in creating your schedule is to enter task headings and tasks. With the Gantt chart on the

screen, begin by typing a list of tasks or events that need to be done in order to move the project forward,

preferably in the approximate order they will happen. Tasks entered are assigned the default duration of one

day (1d). It is easy to delete and insert tasks and to relate tasks so that each task will be scheduled

appropriately.

1. At the bottom left-hand corner of the Project window, click on the

“New Tasks…” button. Make sure all new tasks are entered as Auto

Scheduled.

2. In the first field in the Task Name column type PALMERS GOLF COURSE

PROJECT

3. Press Enter.

4. In field #2 enter, Initial Study

5. Continue entering these task headings, one in each Task Name field:

Feasibility Study

Requirements Analysis

Requirements Specification

System Design

Coding & Testing

System Testing

Now is a good time to save your work using the Save As command under the File menu, ensure you have

selected the appropriate drive (e.g., H:) in the drives box on the "Save As" screen. In the File Name box,

give this file an appropriate name (e.g., Palmers_D1_EnterTasks).

Note:

 If you wish to make corrections you can use the white Entry Bar. Make the corrections and press enter or click on the tick button.

 To delete tasks, select the task and use the Delete key. If you inadvertently delete a task immediately click the Undo button on the toolbar.

 Here and below, do not be concerned about not understanding what this means. This project information is about various stages of systems development project, but it is not necessary for you to understand

systems development terminology to carry out this assignment.

Select the Feasibility Study task. Then either use the Insert key on the

keyboard or choose New Task from the Insert menu. This enters a blank

line above the current task.

Repeat until there are three cells between "Initial Study" and "Feasibility Study". In the three blank cells

enter:

Study Existing System

Carry Out Interview(s)

Prepare Documentation

Continue by inserting the relevant number of blank lines below each task heading and then enter in the

following:

Under "Feasibility Study" enter:

Identify Problems

Understand and Analyse Problems

Estimate Project Cost

Assess Project Risk

Propose Solution

Task Scheduling

Under "Requirements Analysis" enter:

Investigate Current Environment

Investigate and Define Requirements

Under "Requirements Specification" enter:

Prepare Specifications

Prepare Use Case Diagram

Prepare Data Dictionary

Prototyping

Under "System Design" enter:

Design New System

Design Test Plan

Under "Coding & Testing" enter:

Coding

Unit Testing

Integration Testing

Update Data Dictionary

Under "System Testing" enter:

Hardware & System Testing

Acceptance Testing

Prepare Documentation

Some of the Task Name information is not completely visible in the field. To view the full field, place the

cursor on top of the vertical line to the right of “Task Name” in the dark grey title area. Its shape will change

to a thin vertical line with two arrows. You may "drag" the line and view the enlarged Task Name field.

As you progress with your work, you’ll need to regularly save the project. In the File Name box, give this

file an appropriate name (e.g., Palmers_D1_EnterTasks).

Although there will be places in the assignment where it is recommended that you save your data, you

should use common sense and save more regularly. Don’t forget to have a backup file saved too.

Durations and Milestones

With your tasks entered, you are now ready to enter duration for each task in the Duration field. Duration is

an estimate of how long it will take to complete each task. Enter durations by using a number followed by a

letter to indicate the unit of measure: days (d), weeks (w), hours (h), and minutes (m). The default duration is

1d.

Note: Here and below, do not be concerned about calculating the duration yourself. For this project, we are

giving you the durations that should be used throughout the project.

A vital part of project management is to place "milestones" in order to identify significant events in your

schedule or to measure the progress of your project. A milestone is created by declaring it as a task of zero

days duration. Microsoft Project displays the milestone symbol on the Gantt chart at the start of that day. To

the right of the milestone symbol is the start date for the task, such as:

 Set Milestones

You are to add milestones, which are the dates project deliverables are due. To enter the first milestone:

1. Insert a blank task line above Task 13 Requirements Analysis.

2. Type "Deliverable to Project Manager".

Repeat this process one more time at the end of the project, after “Prepare Documentation”.

 Set Durations

The durations shown in the Gantt chart on the next page are to be entered in the Duration column.

1. Select the Duration field for the first task.

2. Type a number for the duration length followed by the duration unit

abbreviation.

3. Press the enter button or the tick mark.

4. Repeat steps 1 through 3 to enter durations for all the tasks in your

project.

Having completed all the duration entries plus adding the two milestones, your Gantt chart should look

similar to the chart below with "PALMERS GOLF COURSE PROJECT” as Task 1 and "Initial Study”

as Task 2.

3

This Gantt chart shows it will take 10 working days (2 weeks, there are 5 working days per week), as defined

by the duration of tasks 26 and 27, to complete the project (the red bars). By definition, these are the critical

paths and are shown in red on your screen. However this assumes each task is independent and running in

parallel with each other, starting at the same time and same date. Nothing could be further from the truth and

it is time to change the Gantt chart to reflect this.

Designating tasks and sub-tasks To show the structure of the project, that is the hierarchical nature of task headings and subtasks, the

subtasks are indented to the right of the task heading.

To do so, select the subtasks and click the Indent button (right pointing arrow on the Formatting toolbar) or choose Outline from the Project menu

and then choose Indent.

Select tasks 3 - 5 and indent them.

Note that the Task Summary "Initial Study" has become bold, its Gantt Bar has changed shape and colour

and the length of the bar is now the same as the longest duration of the subtasks.

Continue indenting the subtasks associated with:

Feasibility Study, Requirements Analysis, Requirements Specification, System Design, Coding & Testing,

System Testing. To check on the structure, it is helpful to show all of the subtasks by clicking on the +

symbol on each Task Summary, as shown below. On completion your chart should look similar to that

below.

Now it is necessary to make all the tasks part of the project. To do so, indent all Task Summaries so that they become a sub-task of PALMERS GOLF COURSE PROJECT.

Note how the PALMERS GOLF COURSE PROJECT Summary Bar now takes on the duration of the

longest Task Summary (10 days) as shown below. Pay attention to the and in front of the project

tasks.

Now is a good time to save your work using the Save As command under the File menu. In the File Name

box, give this file an appropriate name (e.g., Palmers_D1_Indent).

Establishing Relationships between Tasks

The next step is to link the tasks in sequence and see how long it will take to finish the project. When you

link one task to another, you establish a relationship between tasks and specify a sequence of events.

When a task begins after the previous task finishes, this is a finish-to-start relationship. The finish-to-start

relationship is the most common and is the default one in Microsoft Project.

A finish-to-finish relationship is one in which both tasks finish at the same time.

A start-to-start relationship is one in which both tasks start at the same time.

The least common relationship is a start-to-finish relationship in which the completion of one task depends

on the start of a later task.

A task that must start or finish before another task is called a predecessor task. A task that depends on the

start or finish of a preceding task is called a successor task.

As a general guideline, link sub-tasks to sub-tasks within a group and then link Summary Tasks to other

Summary Tasks.

* * * Practice exercise starts here. This is just practice, at completion, Exit WITHOUT saving * * *

The two buttons for creating links and breaking links are represented by the two "chains" shown in the

Standard toolbar.

To create a link:

1. In the Gantt chart select the tasks you want to link in the correct order i.e. predecessor before successor.

2. Click the Link Tasks button on the toolbar.

To remove a task relationship:

1. In the Gantt chart, select the tasks you want to unlink.

2. Click the Unlink Tasks button on the toolbar (the "broken" chain), or choose Unlink Tasks from

the Edit menu.

To change the type of relationship (between two tasks):

1. Select the second sub-task of already linked sub-tasks.

2. Click the right button of the mouse to open a drop-down menu.

3. Click on Information.

4. Click on the Predecessors tab.

5. Click on the Type field (for example, "Finish-to-Start (FS)").

6. Click on the downward arrow above the information, this will open a drop-down menu.

7. Click on the new type of relationship (e.g., Finish-to-Finish).

8. Click OK. Note how the bars for the task and its predecessor now have the same finish date.

* * * Practice exercise ends here. At completion, Exit WITHOUT saving * * *

You will now create links on the PALMERS GOLF COURSE PROJECT. Later you will be called upon to

shorten the duration of the project due to the consequence of either a completion date requirement or the

amount of resources used. Normally there is a third consideration, the cost, but this is beyond the scope of

Deliverable #1.

Select tasks 3 - 5 inclusive and link these in a Finish-to-Start

relationship.

Note:

• The bars are now red because they are currently the critical path.

• The duration of "Initial Study" is the sum of all linked subtasks and equals 10 days (3 days + 2 days + 1

week [which is equivalent to 5 working days]).

Complete linking the tasks by linking them in a Finish-to-Start

relationship:

Link tasks 7 - 13 inclusive

Link tasks 15 - 16 inclusive

Link tasks 18 - 21 inclusive

Link tasks 23 - 24 inclusive

Link tasks 26 - 29 inclusive

Link tasks 31 - 34 inclusive

Tasks 9 and task 10 can go in parallel so they both finish at the same

time (a finish-to-finish relationship). Change the finish-to-start

relationship to finish-to-finish relationship as discussed above.

In order to show the total duration of the project it is necessary to link the Task Summaries. Select a Task summary; click on hide subtasks button (a - (minus) symbol in the

View Tab  Outline) and all its subtasks will become hidden thus making

the next Task Summary become adjacent.

Repeat this process through the rest of the project so that only the Task Summaries are displayed. Select

all Task Summaries then click Link (finish-to-start) button. This method

summarizes the project at the Task Summary level, which is useful for reporting purposes. Click on the show all tasks button (+ + button) under the Outline option in the View

Tab to restore the full Gantt chart display.

Do NOT link the PALMERS GOLF COURSE PROJECT Task to the other Task Summaries.

Now you should analyse and format the chart to give an overall view. Note that the duration of the project is

now 110 days, all tasks are on the critical path, and your Gantt chart is spread over 6 or more pages. To get

an overall view of the project, select Zoom from the View menu, then Entire Project.

Looking further at the Gantt chart shows that the milestones have shifted due to their relationship with their

predecessor. The duration of the whole project is "task-driven". To check the global project information,

view the Project Information box in the Project Tab. This will show you the project start date and the project

finish date as well as the name of the calendar in use (Palmers Calendar). With a starting date of Mon Jan

4th 2016 the project would conclude on Fri June 10 2016. This finish date is completely unsatisfactory as

the project due date is Thu, May 19th 2016. Click cancel.

Setting milestones The final date will be set by the milestone at the end of the project (Task 34).

To adjust the milestone, double click on the task to display “Task Information”. 1. Then click on the “Advanced" tab. 2. In the “Constraint Type” change to "Must Finish On" by using the pull

down menu.

3. Then change Constraint Date to the required date of Thu May 19 2016 for that milestone.

4. Click OK.

If the date is earlier than the one shown prior to changing, a ‘Planning Wizard’ screen will come up advising

of the difficulties being encountered with this deadline. For the purposes of this assignment, the date is not

negotiable, therefore click on the last option, "Continue, A Must Finish On

Constraint will be set". Click Ok. Another screen will now come up advising of a

scheduling conflict. Select, "Continue. Allow the scheduling conflict". Note how on

the Gantt chart the time folds back to the milestone. This means that the duration of the project will have to

be shortened. This will be addressed shortly.

To meet an organizational deadline, the milestone at task 13 must set to

Wed February 10th 2016. Note again there is a problem with this milestone being achieved as shown

by the "fold back" in the Gantt chart.

Despite these changes, note that the total duration for the project as shown on Task 1 remains the same at

110 days. What has just happened? See column “Finish Date” (down two columns from Duration column).

We still have MS Project scheduling the entire project on finish date of Fri June 10th 2016 (showing 110

days). However, the last milestone 34 “Deliverable to Project Manager” has to be handed in on the Thu,

May 19th 2016 (the date specified by the Project Manager, Ms Smith). From now on in the assignment we

are going to use the Thu, May 19th 2016 date and milestone as a critical path to bring the project in on time.

This will happen in Deliverable #3. For now you have finished Deliverable #1 Initial Gantt Chart,

however, keep going to get the necessary paperwork to hand in.

 Formatting the Deliverable

The following formatting steps are required for the first deliverable (such as inserting footers). Microsoft

Project will enter the project start and finish dates for you automatically.

To set footers: 1. Click on the File Tab, choose Print, then choose the Page Setup link

under the Print settings.

2. On the Page tab, choose Landscape orientation. 3. Click on the Footer tab. 4. In the Alignment box, select Left tab and type Project Start Date:

then select Project Start Date from the General drop-down menu below,

then click on Add button.

5. Select Centre tab, delete the page number field and type your name. 6. Select Right tab and type Project Finish Date: then select Project

Finish Date from the General drop-down menu below, then click on Add

button.

7. Click on OK to save these footer settings. 8. Check footer details using Print Preview.

To view the Gantt chart so that the whole project fits on one page: View, then click on Entire project (in the Zoom category), then OK.

Click on Page Setup: select the Page tab: in Scaling, adjust to 80%

normal size; go to View tab, tick "Fit timescale to end of page"; click

Print Preview button to check that the chart takes one page and shows

the columns listed for Deliverable #1. You may need to continue

adjusting the % of scale to get the best fit.

At this stage you have completed the creation of a schedule. You have done a lot of work on this project and

it would be a very good idea to save your work. It also would be a good idea to make a duplicate of this file

at this time, (e.g., save as Palmers_D1_Duplicate)

Deliverable #1: Initial Gantt Chart

Microsoft Project file: Palmers_Deliverable_1

The first Deliverable in this assignment is your Gantt chart with the columns Info (Indicators), Task Name,

and Duration. The footer includes the fields Start Date, your name and Finish Date, as specified. All the

tasks and subtasks are listed with correct durations; no misspelled words; milestones correct; and tasks

linked. Be sure to print preview to ensure that the footer is formatted correctly.

Deliverable #1: Initial Gantt Chart………………………………………..……………………..30 points

Note: This document is the combination of two separate MS Project assignments. Therefore, do not

submit your Project file yet. You will submit the completed Project file for both assignments below

after completing the Deliverable #2 instructions below.

Deliverable 2: Resource Management

Adding Resources to the Project

People and equipment are the resources that do the work in your project. With Microsoft Project, you can

assign resources to tasks and then use the software's tools and views to manage these resources and the

overall project more efficiently. It will ensure you have sufficient people and equipment to meet your

schedule and create work schedules for resources.

Assign resources when your goal is to:

• Track the amount of work done by the people and equipment assigned to the tasks.

• Ensure high accountability and understanding of the project – responsibilities for the implementation of

tasks are made clear and the risk of tasks being overlooked is decreased.

• Have greater flexibility in planning when and how long tasks take to complete.

• Monitor those resources that have too little or too much work assigned.

• Keep track of resource costs.

If you do not enter resource information, Microsoft Project calculates your schedule using just task duration

and task relationship information (i.e., task-driven scheduling in the Gantt chart you have created). This

assumes unlimited resources are available to complete the tasks, which is not a very realistic view of project

management.

Resource assignments affect the length of time it takes to complete a task; this is called resource-driven

scheduling.

Create a resource list

You need to create a resource list. While assigning resources, this will save you time. The software assigns

the amount of work specified for a task to a resource. Scheduling depends on the resource's work schedule,

or resource calendar and other task assignments. For example, if you assign a one-day task to a resource and

the resource works full-time, then the resource will be scheduled to work on the task for the equivalent of a

full day, starting with the earliest available unscheduled time that meets the task constraints. Once a resource

is assigned to a task, the resource name appears next to the task bar on the Gantt chart.

In this project you will assume that your company staff will consist of a Chief Programmer, a Senior

Programmer, three Programming-Analysts and a Programmer. Three high-school students are also able

to work on Wednesday and Thursday afternoons only, excluding any public holidays. They will provide

unskilled assistance but would benefit by getting work experience training. They will have an unimaginative

title, Student. Also, Client will be used in some tasks.

If you haven’t already done so, Open Palmers_Deliverable_1.mpp.

To create a Resource List:

1. From the Task Tab, click on the Gantt chart icon on the far left of

the Ribbon and choose Resource Sheet.

2. In the Resource Name column enter the title of the Staff member.

3. In the Max. Units column, enter the number of resource units available

for this resource (default is 100 % per each one unit). For example to

use 3 Programmer-Analysts you should key in 300%.

4. Verify that the Base Calendar column lists the Palmers Calendar. If it doesn’t choose Palmer’s Calendar from the dropdown menu when you click

on the Base Calendar field for each resource.

5. Repeat steps 2-4 for each of the staff titles, except the student.

6. Repeat steps 2-3 for the three students.

7. Due to the students working Wednesdays and Thursdays only, it will be

necessary to create a new calendar, let's call it the "Students

Calendar". To do so, follow instructions to create a new calendar as

described earlier in "Set the Project Calendar" section (Page 8). The

Students Calendar inherits the characteristics of the Base Calendar.

Ensure that you click on "Make copy of Palmers Calendar" when you

create it. Show working hours are Wednesday and Thursday for a start

time of 1:00pm and a finish time of 5:00pm. Monday, Tuesday and Friday

are to be made non-working days.

8. Repeat step 4 for student, choosing Students Calendar. 9. For each Staff, enter the standard $ rate as shown below.

Your Resource Sheet should look like this:

Return to the Gantt chart by choosing Gantt chart from the View menu.

Assigning and removing a resource

In your Gantt chart, you now have a project of known duration, even though it does not yet meet time

constraints. It currently assumes that one person is working full-time on the project; this is the default value.

This person is operating on the same calendar as the project base calendar (e.g., the project is using the

Palmers Calendar, a resource using the Palmers Calendar is the default). When you allocate one staff to a

task, the duration will not change. Should you allocate a resource using a different calendar (i.e., a student)

then the duration will change.

By assigning resources (people or equipment) to tasks, you can make sure you have enough resources to

accomplish the tasks in your project. You can assign one resource, a part-time resource, multiple resources,

or multiple units of the same resource to a task. The software displays the unit percentages next to the

resource name by the task bar on the Gantt chart.

You can also change the resource quantities allocated to a task. In this case, for resource-driven tasks the task

duration will change when you change the number of units for the same resource assigned to a task. This

enables you to reduce the amount of time required to complete a task to meet a deadline. There are

safeguards in the software to stop you from entering more resources units than you have available – you will

be warned of over-allocation.

How to assign resources: There are several ways of assigning resources. The method you will use is to

employ the Resource Pool just created. It will be helpful to use the Resource Tab that contains the Resource

Assignment button as well as other buttons related to working with resources.

Select a task on the Gantt chart and then open the Assign Resources box by clicking on the Assign Resources

button from the Resource Tab. In the Assign Resources box select a resource and click on the Assign

button. If more than one unit is needed, enter the quantity in the Units field beside the resource name.

Remember that you are not restricted to integers.

Assigning a resource to several tasks: Select the tasks in the Gantt chart (using the ctrl key to select the tasks

that are not adjacent), and then in the Assign Resources box select the resource and then the Assign button.

Changing the number of resources used on a task: To decrease or increase the number of resources allocated

to a task, double click on the task, which opens the Task Information box, then on the Resources tab. Select

the Units field and change the figure.

Removing a resource assignment: Select the task on the Gantt chart, click the Assign Resources button on

the Resource Tab. Select the appropriate resource and click on the Remove button.

Practical example of resource application You are going to do some "what -if" tests to see the impact of resources on the duration of a task as well as

changing some durations. Start with a just-saved file (i.e., save your work before beginning these tests).

* * * Practice exercise starts here. At completion, Exit WITHOUT saving * * *

On the Gantt chart, select Task 26, Coding. This task currently has duration of 2 weeks. Likewise, on the

Gantt chart note the duration of the Task Summary Coding & Testing (24d) and also the total project time

for Palmers Golf Course Project (110d). Double click on task 26 and from the Task Information box note

that the start and finish dates are Thu April 21st 2016 and Thu May 5th, 2016 respectively.

Allocate to this task the resource of one student (“OK” then “continue and allow the scheduling conflict” if

asked). Note how the Gantt bar has now extended and also the Task Summary and Palmers Golf Course

Project duration times have increased. Clicking on the Task to produce the Task Information shows the

finish date has changed as well.

Obviously this resource allocation is not good for the project but it does demonstrate how the Resource

Calendar created for the students is automatically taken into account when those resources are allocated to

a task.

Re-enter the Resource Assignment box and increase the Students assigned from one (100% units) to four

(400% units). You have now allocated more students than are available. To see this graphically

demonstrated, from the Task Tab, click on the Gantt Chart icon at the left of the Ribbon and choose

Resource Graph. In the left-hand window, click on the scroll bar at the bottom to display the Students box.

Note how the title is in red, which shows there is an over-allocation. In the right window, drag the horizontal

scroll bar until the date of around May 1st, 2016 is displayed. You will then see the student allocation in blue

as well as the over-allocation in red. A similar view is in Resource Usage, under the View menu. Against

Student you will see the total work time (80 hours). Drag the cursor until you can see the time allocations on

May 1st, 2016 and you will see, in red, 16 hours per day over 5 days.

As this is not a successful task allocation, firstly reduce the number of students employed on the task to 1.

Then remove the students completely from the task by clicking on the Tools, Assign Resources, click on

Student then on the Remove button. Check on the Gantt chart that the duration for Task 26 has been restored

to 2w.

* * * Practice exercise ends here. At completion, Exit WITHOUT saving * * *

Task constraints One aspect of project management is determining lead and lag times. Microsoft Project assumes all new

tasks can start immediately after the preceding task has finished. However, in real projects some tasks can

start while another is in progress (lead time) and in other situations there may need to be some time between

the finish of one task and the start of the next (lag time). Microsoft Project cannot do this for you; this is your

responsibility as Project Planner.

Lead and Lag Times in Projects

Lead time: The amount of overlap between the completion of one task and the start of its successor. For

example, you might want to start moving furniture into some offices while carpet is still being laid in other

offices.

Lag time: The amount of delay between the completion of one task and the start of its successor. For

example, a lag time of two days might be required between painting a room and laying carpet.

These are the instructions to perform when changing the relationships between the tasks with lag and lead

times added.

Choose the correct successor task and then double click on that task. Select the Predecessors tab, click on

"Finish-to-Start (FS)" in the Type field, click on the downward arrow above to open the drop-down menu,

select the type of relationship required then click in the Lag field to the right if required and enter the

amount, then OK. For lead time, enter the number prefaced with a minus sign.

 To change the relationship between the tasks with lag and lead times:

(Use the instructions above to carry out the tasks below)

Firstly, double check that the following successor tasks have the finish-to-start relationships:

• Task 3 must precede task 4

• Task 4 must precede task 5

• Task 7 must precede task 8

• Task 8 must precede task 9

• Task 10 must precede task 11

• Task 11 must precede task 12

• Task 12 must precede task 13

• Task 15 must precede task 16

• Task 18 must precede task 19

• Task 19 must precede task 20

• Task 20 must precede task 21

• Task 23 must precede task 24

• Task 26 must precede task 27

• Task 27 must precede task 28

• Task 28 must precede task 29

• Task 31 must precede task 32

• Task 32 must precede task 33

• Task 33 must precede task 34

To further expand your Project Management skills, set tasks 26 and 27 with a finish-to-

finish relationship on a one-day lag. Note how the “Coding & Testing” Task Summary has reduced by nine

days (from 24 to 15 days) as task 27 (ten days) now runs in parallel with task 26, minus a one-day lag.

Repeat this process for tasks 19 and 20.

Also, set the relationship between task 3 and task 4 with a start-to-start

relationship.

Note: Tasks 3-13 should now be coloured blue and the duration time for the project should be 94.5 days.

Now would be a good time to SAVE your file with these new task constraints before allocating resources in

the next step. In the File Name box, name this file (Palmers_D3_Lead_Lag_Times).

Allocating resources to Palmers Golf Course Project Make a backup copy of your file BEFORE you start assigning resources and rescheduling tasks to fix the

over-scheduling problem you currently have. As you perform multiple changes of resource allocations, the

software does not keep the original duration and you may have to revert to the saved backup copy.

It is important to grasp the concepts of task allocation as this procedure, if misunderstood, can lead to much

confusion and incorrect results. Microsoft Project does not know if a task needs 1 employee or 10 employees

to undertake the task. At this stage we are going to decide how many staff it is going to take to perform a

task.

 Entering resources for each task

You can adjust each task one-by-one, but if you want to allocate the same number of staff to a number of

tasks, highlight the tasks (use the ctrl key), then select Assign Resources from the Tools menu and make the

assignment.

Enter the following resources for the following tasks. Only these

resources must be entered. Go to Tools, Assign Resources, to enter in the

following resources, all at 100% (the window can stay open to assign all

the resources). While assigning the resources, if the planning wizard

window pops up – choose the option Continue, Allow the schedule conflict.

Task 3 Programming Analyst, Chief Programmer

4 Client, Chief Programmer

5 Senior Programmer, Programming Analyst

7 Programming Analyst

8 Programming Analyst 9 Senior Programmer, Chief Programmer 10 Senior Programmer, Chief Programmer 11 Senior Programmer, Programming Analyst 12 Senior Programmer 15 Senior Programmer, Programming Analyst 16 Programming Analyst, Chief Programmer

18 Programmer, Senior Programmer

19 Student, Programmer 20 Student 21 Programmer

23 Programming Analyst, Senior Programmer

24 Programmer, Senior Programmer 26 Programmer, Programming Analyst

27 Programmer, Programming Analyst 28 Programming Analyst 29 Student, Senior Programmer 31 Senior Programmer, Programmer

32 Programmer, Client 33 Senior Programmer, Programming Analyst

The following figure shows Programming Analyst and Chief Programmer being assigned to Task 3. If you

assign your first resource (Programming Analyst) to the task and later assign second resource (Chief

Programmer) then, the information box for the corresponding task will show a warning information

suggesting you to ‘Click to set how the task is rescheduled as a result of the assignment’. This would change

the duration to half as you have doubled your resources. To confirm select the first of the 3 options.

But if you assign both resources simultaneously then the duration wouldn’t get changed. To change the

duration to half, you need to first look at the work against each resource. From the View Tab, in the Split

View category, click the checkbox next to Details, and select Task Form from the dropdown menu to see

all the details about the resources allocated to a task. You would notice that work against each resource may

still be the total work for that task. Example for the task 3, each resource should work for 12 hours each (half

of 8(hours)*3(days)=12 hours) and not 24 hours each (that would make the total work to be 48 hours). If this

is 24 hours, then you need to change this to 12 and then duration would get halved.

It is necessary to note that the duration of tasks should have changed when the allocation of two people were

added to a task above. Let’s CHECK and see.

You will need:

1. a printout of Deliverable #1 with original durations.

2. a printout of the Gantt chart just performed with resource allocations just added.

Notes about resource allocations

By comparing the printouts of Deliverable #1 and the Gantt chart of resources just allocated, check the tasks

with 1 resource (person) allocated. You will find that the durations are the same.

However, for the tasks with 2 (or more) resources (people) allocated, the durations should have halved or

changed. In fact, it is better to see how what the s/w has done when you allocated the resources. You may

also like to insert a pre-defined column called ‘Work’ in your Gantt Chart (see the figure below). Also, from

the main menu select Split under Window to see all the details about the resources allocated to a task. For

example, for Task 3, we can see the resources (personnel) allocated and the amount of person-hours they are

working. Each resource is shown to be working for 12 hours (half of the total work is allocated to each

resource) as total work is 3 days (8*3 = 24 hours).

CHECK the tasks that have 2 resources allocated have halved under the duration column (such as 3, 4, 5, 9,

10, 11, 15, 16, 18, 23, 24, 26, 27, 29, 31, 32 and 33). If any need to be changed, use the instructions above

using the Split window with the Task Form in the lower half. Change the Work for each resource to half of

what it is if the duration didn’t get cut in half when assigning 2 resources, then click the OK button

For task 32 in the image above, the work was 24h each before changing it to 12h each to halve it, then click

the OK button.

Note: All your tasks should now be blue and the total duration of the project should change to 94 days.

As you have made quite a lot of changes now would be a good time to SAVE.

The Budget

Before finishing let’s have a look at the budget of the project thus far. The budget should show a total cost

of $38,280.00, check.

View the ‘Cost Overview Report’.

From the Report Tab, then Costs, choose More Reports. The dialog box

that appears has several categories on the left. Click on the

Dashboards category and then select the Cost Overview report. Verify that the

total costs are $38,280.00.

Deliverable #2: Resource Management

Microsoft Project file: Palmers_Deliverable_2

Deliverable #2 in this assignment includes your Microsoft Project file from Deliverable 1 above with

Resources added and assigned to the appropriate tasks.

Deliverable #2……………………………………………………………………………………. 30 points

The criteria listed for Deliverable #1 Gantt chart also apply here. Specified changes in the project must be

shown and each task must show the staff and student resources allocated to the task.