Fix the error

profileemey.b
mgt_604_assignment_000_0-1-1.docx

MGT 604

Assignment #2

(To be uploaded to Blackboard by midnight 7/23/2016)

Consider a construction project with the following (8) activities:

1) Determine Activities Schedule for this project using a Gantt chart on Microsoft Project.

2) Identify the Critical Path of activities for this project.

Solution

Paths and durations are:

A, C, E, G, H

tA + tC + tE + tG + tH = 2+2+4+5+2 = 15

A, C, F, H

tA + tC + tF + tH = 2+2+3+2 = 9

A, D, G, H

tA + tD + tG + tH = 2+4+5+2 = 13

B, D, G, H

tB + tD + tG + tH = 3+4+5+2 = 14

A, C, E, G, H gives the longest duration thereby being the Critical Path

3) Determine those activities that have Slack / Float, and their amount of Slack/ Float.

Activity

ES

EF

LS

LF

Slack (LS-ES)

Critical

A

0

2

0

2

0

Yes

B

0

3

1

4

1

No

C

2

4

2

4

0

Yes

D

3

7

4

8

1

No

E

4

8

4

8

0

Yes

F

4

7

10

13

6

No

G

8

13

8

13

0

Yes

H

13

15

13

15

0

Yes

4) Given the Optimistic and Pessimistic time estimate for each activity in the table below, a) What is the probability of project completion in 16 weeks or less? b) With 99% confidence, when would this project be completed?

Part (a)

Expected time: t = (a + 4m + b)/6 where a = optimistic, b = pessimistic, m = most likely time

Variance: v = [(b-a)/6]2

Activity

a

m

b

t

v

A

1

2

3

(1 + 4*2 +3)/6 = 2

[(3 - 1)/6]2 = 0.11

B

2

3

4

(2 + 4*3 + 4)/6 = 3

[(4 - 2)/6]2 = 0.11

C

1

2

3

(1 + 4*2 +3)/6 = 2

[(3 - 1)/6]2 = 0.11

D

2

4

6

(2 + 4*4 + 6)/6 = 4

[(6 - 2)/6]2 = 0.44

E

1

4

7

(1 + 4*4 + 7)/6 = 4

[(7 - 1)/6]2 = 1.00

F

1

2

9

(1 + 4*2 + 9)/6 = 3

[(9 - 1)/6]2 = 1.78

G

3

4

11

(3 + 4*4 + 11)/6 = 5

[(11 - 3)/6]2 = 1.78

H

1

2

3

(1 + 4*2 +3)/6 = 2

[(3 - 1)/6]2 = 0.11

Total variances of activities on critical path

Total variance = 0.11 + 0.11 + 1.00 + 1.78 + 0.11 = 3.11

Completion on or before 16 weeks

Z = 0.5681818181818182 ≈ 0.57

Using normal distribution tables;

i.e. P (T ≤ 16 weeks) = 0.7157 = 71.57%

Part (b)

Therefore:

5) Given activity Crash Costs in the table below:

a) What is the Total Cost for completion of this construction project in normal time?

Solution

Total Cost in normal time = Cost of Critical tasks

Total Cost = CA, CC, CE, CG, CH

Total Cost = $22000 + $26000 + $56000 + $80000 + $16000

Total Cost = $200000

b) What is the additional cost for completing the project two (2) weeks earlier than expected?

Solution

Crash cost per period = Crash cost – Normal cost/Normal time – Crash time

Activity

N. time

C. time

N. cost

C. cost

CCpW

Critical

A

2

1

22000

22750

750

Yes

B

3

1

30000

34000

2000

No

C

2

1

26000

27000

1000

Yes

D

4

2

48000

49000

1000

No

E

4

2

56000

58000

1000

Yes

F

3

2

30000

30000

500

No

G

5

2

80000

84000

1500

Yes

H

2

1

16000

19000

3000

Yes

Activities on critical path are A, C, E, G, H

Crash A by 1 week with Crash Cost per Week of $750

Crash E by 1 week, at $1000

That creates a new critical path, B, D, G, H with completion period of 14 weeks

Crash D with Crash Cost per Week, $1000

Therefore, total additional cost = $750 + $1000 + $1000 = $2750

[The Normal Distribution Cumulative Probability Table is attached]

MGT-604_Week- 2_ Assignment _RS

And3.111.76

Variance

s

===

1615

Z

1.76

X

m

s

--

==

(X16)P(Z0.57)0.7157

P

£=£=

99%Z2.33 (-)/15/1.76

cmsc

³===-

2.33*1.761519.1008weeks

c

=+=