TST102
TEST AND EVALUATION MASTER PLAN
FOR SHORT RANGE ANTI TANK WEAPON
(SRAW)
ACAT II
Program Manager Ground Weapons Marine Corps Systems Command Quantico, Virginia
January XXXX
TEST AND EVALUATION MASTER PLAN
FOR
SHORT RANGE ANTI-TANK WEAPON (SRAW)
ACAT II SUBMITTED BY ______________________________________________________ Program Manager Ground Weapons DATE CONCURRENCE ______________________________________________________ Program Executive Officer of Developing Agency DATE ______________________________________________________ Operational Test Agency DATE ______________________________________________________ User's Representative DATE COMPONENT APPROVAL ______________________________________________________ Component Test and Evaluation Director DATE ______________________________________________________ DoD Component Acquisition Executive DATE
OSD APPROVAL ______________________________________________________ Director, Operational Test and Evaluation DATE __________________________________________________________ Director, Developmental Test and Evaluation DATE
TABLE OF CONTENTS
PART 1 – INTRODUCTION ..............................................................................................
1.1 PURPOSE ......................................................................................................
1.2 MISSION DESCRIPTION ............................................................................
1.3 SYSTEM DESCRIPTION .............................................................................
1.3.1 System Threat Assessment ................................................................
1.3.2 Program Background .........................................................................
1.3.2.1 Previous Testing..................................................................
1.3.3 Key Capabilities .................................................................................
1.3.3.1 Key Interfaces .....................................................................
1.3.3.2 Special Test or Certification Requirements ........................
1.3.3.3 Systems Engineering (SE) Requirements ...........................
PART II – TEST PROGRAM MANAGEMENT AND SCHEDULE ............................
2.1 T&E MANAGEMENT ..................................................................................
2.1.1 T&E Organizational Construct ..........................................................
2.2 COMMON T&E DATA BASE REQUIREMENTS .....................................
2.3 DEFICIENCY REPORTING ........................................................................
2.4 TEMP UPDATES ..........................................................................................
2.5 INTEGRATED TEST PROGRAM SCHEDULE .........................................
Figure 1 – Integrated Test Program Schedule ................................................
PART III – TEST AND EVALUATION STRATEGY ....................................................
3.1 T&E STRATEGY ..........................................................................................
3.2 EVALUATION FRAMEWORK...................................................................
3.3 DEVELOPMENTAL EVALUATION APPROACH ...................................
3.3.1 Mission-Oriented Approach...............................................................
3.3.2 Developmental Test Objectives .........................................................
3.3.3 Modeling and Simulation ...................................................................
3.3.4. Test Limitations .................................................................................
3.4 LIVE FIRE EVALUATION APPROACH ...................................................
3.4.1 Live Fire Test Objectives ...................................................................
3.4.2 Modeling and Simulation ...................................................................
3.4.3 Test Limitations .................................................................................
3.5 CERTIFICATION FOR IOT&E ...................................................................
3.5.1 Assessment of Operational Test Readiness .......................................
3.6 OPERATIONAL EVALUATION APPROACH ..........................................
3.6.1 Operational Test Objectives ...............................................................
3.6.2 Modeling and Simulation ...................................................................
3.6.3 Test Limitations .................................................................................
3.7 OTHER CERTIFICATIONS .........................................................................
3.8 RELIABILITY GROWTH ............................................................................
3.9 FUTURE TEST AND EVALUATION .........................................................
PART IV – RESOURCE SUMMARY ...............................................................................
4.1 INTRODUCTION .........................................................................................
4.1.1 Test Articles .......................................................................................
4.1.2 Test Sites and Instrumentation ...........................................................
4.1.3 Test Support Equipment ....................................................................
4.1.4 Threat Representation ........................................................................
4.1.5 Test Targets and Expendables ...........................................................
4.1.6 Operational Force Test Support .........................................................
4.1.7 Models, Simulations, and Test-beds ..................................................
4.1.8 Joint Operational Test Environment ..................................................
4.1.9 Special Requirements.........................................................................
4.2 FEDERAL, STATE, LOCAL REQUIREMENTS ........................................
4.3 MANPOWER/PERSONNEL TRAINING ....................................................
4.4 TEST FUNDING SUMMARY .....................................................................
APPENDICES
Appendix A BIBLIOGRAPHY ..........................................
Appendix B ACRONYMS ..............................................
Appendix C POINTS OF CONTACT .....................................
PART I - INTRODUCTION
1.1. Purpose. This document describes the total T&E planning from component development
through operational T&E into production and acceptance for the SRAW. It focuses on the overall
structure, major elements, and objectives of the SRAW T&E program and is consistent with the
SRAW Technology Development Strategy, Acquisition Strategy, Capability Development Document
(CDD), System Threat Assessment, and Information Support Plan. It is also consistent with, and
complementary to, the SRAW Systems Engineering Plan. The SRAW is an ACAT II program listed
on the OSD T&E Oversight List. It will be operated by the United States Marine Corps.
1.2. Mission Description. The SRAW mission is stated in the Systems Initial Capability
Document dated 20 OCT 2003 and the Capability Development Document of 30 NOV 04. The
ICD states that an operational requirement for a weapon to replace the AT4 and M72 by providing
a system with a higher hit probability, greater lethality, longer effective range, and increased
reliability. Key features of threat military doctrine are the mobility, firepower, and protection
offered by tanks and armored infantry fighting vehicles. Enemy tanks, with their technological
sophistication and numerical superiority, are a formidable threat against which the AT4, M72A2,
and SMAW-HEAA are deficient.
1.3. System Description. The SRAW system is a fire-and-forget weapon which can be carried
into combat by an individual Marine. The SRAW will be used to track, engage, and defeat tanks
and armored vehicles from all aspects. The system weight limit of twenty pounds and the
requirement to defeat advanced heavy armor initiatives mean that a very large
performance-to-weight ratio of the warhead is necessary. The SRAW must also be usable for
Military Operations in Urban Terrain (MOUT). It must be capable of being safely fired from
enclosed positions such as masonry rooms that measure 15' × 12' × 7' (4.57m × 3.66m × 2.1m) and
possess 20ft² (1.86m²) of ventilation, and bunkers with front and rear vent area of 15ft² (1.4m²)
each. Special tests of the sound pressure level and toxicity when the SRAW is fired from specified
enclosures must be conducted during weapon system development. The SRAW is to have a
minimum safe engagement range of 16 meters. Furthermore, the desired low cost of the SRAW
system will require innovative accuracy enhancement techniques at the longer ranges.
Conventional high-accuracy inertial sensors and missile seekers are precluded by the system cost
requirements. Since the SRAW is to be fire-and-forget, the initial aiming performance of the
gunner will have an enormous effect on the system accuracy. Presently, limited data exists as to
gunner aiming performance. This performance will be measured during SRAW development.
1.3.1. System Threat Assessment. Potential enemy threats confronting the United States in the
near to long-range period are fully explained in the Marine Corps Long-Range Plan (MLRP) and
the Marine Air-Ground Task Force Master Plan (MMP) of June 2000. Marine Corps forces could
face a variety of threats throughout the world and must be prepared to fight in all climates and
terrain. The most probable areas are the Middle East/Southwest Asia, Europe, and Latin America.
1.3.1.1. While employed against threat forces in the areas mentioned in the previous paragraph,
the SRAW will be subjected to various countermeasures used against antitank missiles. The
missile itself can be classified as a guided munition by the Army Materiel Command
- Smart Weapons Management Office's (AMC-SWMO) definition in its "Guide to How
Countermeasures Affect Smart Weapons" published in January 1992. Since it is not a "smart
weapon", it is not susceptible to most countermeasures (CM), such as chaff or flares, used against
missiles found in the "smart weapon" category. However, the AMCSWMO has determined that
the sensor/fuze section of a guided munition may be vulnerable to CM.
1.3.1.2. Since the target acquisition function for the SRAW is performed optically by the Marine
firing the weapon, and not by the missile or launcher, the system itself is not considered vulnerable
to acquisition CM such as obscurants. However, CM may affect the Marine's ability to acquire a
target and select an aim point. Any electrical component of the missile could be susceptible to
electronic CM. The Target Detection Device (TDD) of the SRAW may be vulnerable to signature
alteration of the target. Active jammers would have significantly less effect on the missile's
guidance as those functions are performed internally by the inertial guidance system. Directed
Energy Weapons (DEW) and projectiles could be used to destroy the missile prior to impact on the
target, but at present they are classified as only potential threats by the AMC-SWMO. The SRAW
may also be vulnerable to high-powered microwave energy (HPM), which may be capable of a
"hard kill", causing meltdown of electronic circuitry in the SRAW missile, or a "soft kill" in the
form of redirected current in the missile's circuits, or failure of the circuitry in the guidance or
TDD. This is known as "electronic upset". Further details of the threat to the SRAW are discussed
in the System Threat Analysis Report (STAR) for the SRAW, which is classified. The contractor
has also performed a classified System Countermeasures Analysis.
1.3.2. Program Background. Successful development of an improved LAW as specified in the
ICD would materially increase the combat effectiveness of Marine Corps units by supplementing
the fires of medium and heavy anti-tank weapons. This would provide the flexibility dictated by
the continued and increasing emphasis on mechanized combat in future warfare. Furthermore, the
ICD and CDD outline the increasing importance of built-up areas in both developed and
developing nations. The ICD specifies that the SRAW needs to achieve its tactical goals not only
on the conventional battlefield, but also in the urban environment. No weapon system capable of
performing the SRAW mission (defeating main battle tanks fitted with explosive reactive armor
and/or supplemental armor at short ranges in a low-cost, man-portable system) currently exists in
the US military. Thus the SRAW system will augment the presently weak infantry short-range
firepower.
1.3.2.1. Previous Testing. Omitted for training purposes.
1.3.3. Key Capabilities: The Key Performance Parameters, Key System Attributes, and
Additional Attributes are listed in Tables 1, 2, and 3, respectively.
1.3.3.1. Key Interfaces. The SRAW system will be capable of interfacing with the current night
vision sight or similar devices at the time of fielding in order to provide a night capability.
1.3.3.2. Special Test/Certification Requirements. Omitted for training purposes.
1.3.3.3. Systems Engineering (SE) Requirements. Omitted for training purposes.
Key Performance Parameters
Development Threshold Development Objective
Minimum range 17 meters 17 meters Maximum range > 600 meters > 800 meters Probability of hit (stationary target)
.5 (400 meters) .7 (400 meters)
Probability of hit (crossing target)
.5 (200 meters) .45 (250 meters)
.6 (200 meters) .55 (250 meters)
Operational Availability .95 .95 Warhead Defeat capability T-80 MBT w/ explosive
reactive armor T-80 MBT w/ explosive reactive armor
Table 1 Key Performance Parameters
Key System Attributes Development Threshold Development Objective Reliability .95 .95
Table 2 Key System Attributes Additional Attributes Development Threshold Development Objective Transition Time: Carry to Fire
20 seconds 15 seconds
Table 3 Additional Attributes
2. PART II - TEST PROGRAM MANAGEMENT AND SCHEDULE
2.1. T&E Management.
2.1.1. T&E Organizational Construct
2.1.1.1. Marine Corps Systems Command (MARCORSYSCOM) has overall responsibility for
the SRAW program. Essential responsibilities of the PM CBG/SRAW Project Officer,
MARCORSYSCOM, include:
Prepare the Test and Evaluation Master Plan (TEMP)
Staff for comments and approval through the Commanding General, Marine Corps
Combat Development Center (MCCDC), the Director, Marine Corps Operational Test
and Evaluation Activity (MCOTEA), and submit to the Commander, Marine Corps
Systems Command for approval.
Coordinate the Developmental Test (DT) Reports prepared by the hardware
contractors, development activity, and any relevant test agencies.
Publish a final Developmental Test and Evaluation (DT&E) report.
Provide guidance and direction to the development activity, Naval Surface Warfare
Center, Dahlgren Division (NSWC-DD), Dahlgren, VA.
Certify, to the Director, MCOTEA, that the system is ready and safe for OT&E. This
certification is based on a certification letter from the development activity.
2.1.1.2. Naval Surface Warfare Center-Dahlgren Division (NSWC-DD), Dahlgren, VA.
NSWC-DD will serve as the development activity and will provide the necessary technical,
administrative, and contractual support for the successful completion of the program. NSWC-DD
is responsible for coordinating, monitoring, and reviewing all contractual schedules/milestones,
test plans, designs, documentation, testing, test results, training, reports, and costs. Specific
responsibilities include:
Provide engineering and technical support for test execution.
Prepare the Detailed Test Plan (DTP) for developmental testing and submit to
COMMARCORSYSCOM, (PM CBG) for staffing and promulgation.
Incorporate failure definitions and scoring criteria prepared by MCOTEA for the test
program, with input from MCCDC and MARCORSYSCOM.
Prepare a final Government DT&E report for inclusion in the Marine Corps Program
Decision Memorandum (MCPDM) package.
Prepare a safety certification letter and submit it to the COMMARCORSYSCOM (PM
CBG) stating whether the weapon system met/did not meet design criteria, is safe/not
safe to proceed into OT&E, and is recommended/not recommended to enter
production.
Manage the provision of requisite test hardware and contractor engineering and
technical services required to support Developmental Test (DT) and Operational Test
(OT).
Administer the SRAW program, per COMMARCORSYSCOM (PM CBG) guidance.
2.1.1.3. Marine Corps Operational Test and Evaluation Activity (MCOTEA). The Director,
MCOTEA, is responsible for the field execution and coordination of operational testing and
evaluation (OT&E). His representative shall arrange for MCOTEA's participation in
developmental testing, as appropriate, to support OT&E objectives. MCOTEA responsibilities
shall include the following:
Ensure that operational testing is effectively planned, conducted, evaluated, and
reported with emphasis on adequacy, quality, credibility, and validity.
MCOTEA, with input from MCCDC and MARCORSYSCOM, will prepare failure
definitions and scoring criteria for testing. Prepare the Test Planning Document (TPD),
Detailed Test Plan (DTP) for IOT&E and the Operational Test & Evaluation Outline
(Part IV) of the TEMP.
Monitor developmental tests and review the DTP to ascertain which portions of DT&E
will contribute to the accomplishment of OT&E objectives. Assess the readiness of the
SRAW for operational tests.
Present an independent evaluation of test results directly to the Commandant of the
Marine Corps (CMC).
2.1.1.4. CG, FMF Lant/CG, FMF Pac. Responsibilities include providing resources to support
operational testing per the approved TPD. Appoint a test coordinator who will serve as the on-site
test director.
2.1.1.5. Others. During all developmental testing, data will be recorded by Reliability,
Availability and Maintainability (RAM) personnel. Data will be gathered from all tests and used in
logistic and life-cycle cost analyses. For each test conducted, the contractor will provide test
reports to the appropriate government official. All field incidents will be reviewed by a test team.
If needed, a failure analysis report will be required from the contractor.
2.2. Common T&E Database Requirements. Omitted for training purposes.
2.3. Deficiency Reporting. Omitted for training purposes.
2.4. TEMP Updates. Omitted for training purposes.
2.5 Integrated Test Program Schedule. See Figure 1 for the time sequencing of the Test and
Evaluation process. Included are the program milestones and the contractor testing plans. The
decision to proceed beyond limited production will be made at the Full Rate Production decision
meeting. Several steps critical to the overall success of the SRAW development effort have already
been completed. The warhead development process was completed during the Technology
Development Phase.
The ICD has addressed a need for a multipurpose SRAW with the capability to defeat main battle
tanks, assault fortified positions/obstacles, and mark or burn enemy positions while conducting
close combat operations. This TEMP addresses only the antitank variant of the SRAW for this
increment. Future variants will be addressed subsequent to this milestone, and will be included in
an updated TEMP.
Fiscal Year
03 04 05 06 07 08 09 10 11 12 13
Milestone MS B
MS C
Phases Technology Dev. Eng. & Man. Dev. Production Sustainment
Dev. Contract
X X X
PDR X
CDR X
Contractor Testing (DT-1)
X X X X X
Gov’t. DT (DT-2)
X X X
Prod Readiness Review
X
OTRR X
LRIP X
IOT&E X
FRPDR X
FOT&E X X X
Figure 1 Integrated Test Program Schedule
3. PART III – TEST AND EVALUATION STRATEGY
3.1. T&E Strategy. In contrast to previous USMC TEMPs, which addressed developmental and
operational testing separately, Part III of the SRAW TEMP describes the full continuum of testing
at both the subsystem and system levels. In doing so, this document outlines an integrated SRAW
strategy that promotes integrated developmental and operational testing (IDT/OT) while
preserving organizational-unique policy and regulatory requirements. Specifically, Part III
documents developmental testing (contractor and government), integrated system testing and
dedicated operational testing that supports fielding decisions that when integrated at the system
level, provide capabilities described in the SRAW CDD.
The objective of IDT/OT is to: 1.) maximize opportunities to collect operationally relevant data;
2.) optimize use of limited T&E time and resources; and 3.) identify problems of an operational
nature at the earliest opportunity. Whenever possible, attempts will be made to maximize DT&E
test cases to provide OT&E-relevant data. Every effort will be made to avoid collection of
duplicate data by combining test events and consolidating data requirements to reduce redundant
testing during follow-on IDT/OT and/or OT events.
IDT/OT involves collecting OT&E-relevant data from appropriate DT events with a focus on
achieving both DT and OT objectives. The responsible test organization will perform the tests
while MCOTEA collects data points to supplement OT&E data. If MCOTEA determines the data
are operationally relevant and remains unaltered by the developing contractor as the program
matures, MCOTEA has the option to carry these data forward to dedicated OT&E.
The T&E WIPT members will have the option to review contractor test plans and procedures and
provide comments to the program office. If possible, IDT/OT modifications that do not
significantly impact schedule or cost will be negotiated by the program office with the contractor,
and the appropriate changes for the DT&E test scenarios will be incorporated to partially satisfy or
collect data against an operational requirement.
MCOTEA will request acknowledgement from the PEO of the IDT/OT activities and events
documented in the OT&E plan and coordinate OT&E plans for acknowledgement from the DT
community to use DT data.
3.2. Evaluation Framework. Table 4 lists the Critical Technical Parameters. All test objectives
for the Technology Development phase have been met.
Table 4 Critical Technical Parameters
3.3.0. Developmental Evaluation Approach. New initiatives in chemical energy warhead
development sponsored by the Defense Advanced Research Projects Agency (DARPA), the US
Army, and the USMC have the potential to significantly increase the lethality of small Chemical
Energy (CE) anti-tank projectiles and missiles. These initiatives include the Javelin Weapon
Critical Technical Total Events Technical Test Scheduled Decision Parameter Objectives Site/Facilities Test Time Supported Accuracy/Range Stationary TGT
DT-1 >.5Ph at 400 meters
NAWC China Lake, CA
Q2 20XX CDR
DT-2 >.5Ph at Q3 20XX MS C 600 m (T)
>.5Ph at NAWC China Lake
800 m (O) Accuracy/Range Moving TGT
DT-1 .5 Ph at 200 meters
NAWC China Lake, CA
Q2 20XX Q3 20XX
CDR MSC
DT-2 .45 Ph at NAWC 250 m China Lake, (crossing
target) CA
Lethality DT-1 Classified Aerojet Test site, Soccoro AZ
Q3 20XX PDR
DT-2 Classified NAWC Q4 20XX MSC China Lake Minimum DT-2 16 meters NAWC Q3 20XX MS C Arming Distance China Lake CA Weight of system DT-1 23 lbs NAWC China
Lake, CA Q4 20XX CDR
DT-2 <20 lbs MS C NSWC Q4 20XX Dahlgren, VA Length of DT-1 40 inches Factory Q4 20XX CDR System DT-2 <40 inches Factory Q420XX MS C
System Warhead Program, Javelin Alternate Warhead Program, DARPA Advanced CE Warhead
Program, and warhead upgrades to the Tube-launched, Optically tracked, Wire-guided (TOW)
Missile program. Progress has been made in both tandem shaped-charge warheads (primarily
direct attack) and in explosively formed penetrators (top attack). Fusing, guidance and control,
sensor, and propulsion developments in programs such as Javelin, NLOS, AAWS-M, and TOW
can be used by the SRAW program. These developments enable the required SRAW performance
to be achieved in a relatively compact and inexpensive weapon system. Limited referencing and
guidance and control technologies developed by the Strategic Defense Initiative (SDI), and other
fluidics research developed by DARPA, the US Army, US Navy, and USAF may be useful to the
SRAW program.
3.3.0.1 DT&E Events, Scope of Testing, and Basic Scenarios. During the EMD Phase, the
contractor will conduct sufficient testing to demonstrate the objectives of the previous section. The
DT test program will be performed in two phases. The first phase consists of developing,
fabricating, and testing nine engineering model missiles. When this phase is completed, the design
will be frozen, and 125 more missiles will be fabricated, tested for quality assurance, and used for
qualification testing. This period of testing will take approximately 24 months to complete. The
following list represents major testing events:
3.3.0.2 Hardware/Software Integration testing, Hardware-In-The-Loop (HWIL) testing with
Government oversight, Environmental testing, HERO testing, Software stress testing Contractor,
development testing Hardware verification testing, Fuze development testing, Contractor missile
technical evaluation Qualification testing (e.g. countermeasures, transportability, etc.)
3.3.0.3 For certain key tests such as lethality or flight tests, the government shall send
representatives to monitor the contractor tests. Human Factors Engineering will be of great
importance during the SRAW development. The man-machine interface plays an important role in
overall system performance and is thus an important part of the weapon system design. The
requirements placed on the gunner must be realistic and must be interactively tested with real
gunners and real system mockups during the SRAW development. Detailed procedures will be
provided in the Detailed Test Plan (DTP). Input to the DTP shall be provided by the contractor and
any relevant government test agency.
3.3.0.4 The government shall approve contractor test plans prior to execution. Table 5 lists the
type and quantity of components to be tested. Tables 6, 7, and 8 list the developmental testing
scheduled during the program.
3.3.0.5 Subassembly Developmental Testing:
a. Airframe. The prime contractor will design, document, and fabricate missiles for eject
tests, warhead and rocket motor subcontractor safety qualification tests; conduct mechanical
and thermal analyses of airframe components; perform loads tests on structural components
and joints.
b. Launcher. The prime contractor will design, document, and fabricate the launcher;
conduct a mechanical analysis of the launcher; conduct drop tests with the launcher and
composite airframe.
c. Target Detection Device. The prime contractor will design, develop, and conduct
subsystem tests on the Target Detection Device (TDD) and components. Because the TDD
could be susceptible to potential CM and is important to mission success, it will be
thoroughly tested in both natural and manmade environments (i.e. heat, cold, weather,
obscurants, etc.)
d. Batteries/Power Supply. The prime contractor will develop, qualify, and conduct
verification of the thermal battery and power distribution system.
e. Electronics Development. The prime contractor will design, fabricate, breadboard, and
test the guidance and control circuitry; design and develop the warhead electronic packaging;
conduct electromagnetic interference testing; design, modify, integrate and test HWIL
hardware and software.
f. Telemetry. The prime contractor will design, develop, and fabricate telemetry circuitry to
support developmental testing. The contractor will also evaluate and select the telemetry
transmitter and receiver.
g. Inertial Sensor Assembly (ISA). The prime contractor will monitor the design,
fabrication, and testing of the prototype/breadboard ISA, produced by a subcontractor. The
prime contractor will perform system integration and acceptance testing of Engineering
Model ISAs.
h. Warhead. Warhead development and testing will be conducted by the warhead
subcontractor. The design has been defined at the end of the Demonstration and Validation
phase; structural and electrical interfaces between warhead, safe & arm device and missile
structure will be defined by the end of the risk reduction program. The lethality of the
warhead has been successfully demonstrated both during static tests and during a full-up
missile flight test. The prime contractor will monitor pre-production qualification testing
(PPQT) testing by the subcontractor.
i. Rocket Motor Development. The rocket motor subcontractor has developed and tested a
heavy-wall design; flight-weight motors and casings have been fabricated and tested, and gas
generator interface requirements established. The prime contractor will monitor
subcontractor PPQT tests.
j. Jet Reaction Control Assembly (JRCA). The JRCA design will have been validated and
tested by the end of the technology development phase. Selection of materials and methods
of fabrication will be complete; gas generator design configuration and interface has been
established. Valve Body and Structural Base designs will be reviewed and updated; the aft
closure release mechanism will be integrated. The prime contractor will conduct shock,
vibration, temperature, and cold gas actuation testing. Any problems will be evaluated and
corrected and designs finalized by the Critical Design Review. Tactical JRCA components
will be tested to include proof, acceptance, cold gas actuation, environmental (i.e. vibration,
shock, temperature), and gas generator tests (3 low temperature, 2 high, 1 nominal).
k. Gas Generator. The gas generator subcontractor will verify performance of the gas
generator prior to delivery. The prime contractor will monitor these tests.
l. System Development/Integration. The prime contractor will assemble and conduct
acceptance and environmental tests on 9 Engineering Model missiles and conduct integration
tests of the missiles with launchers.
m. The prime contractor will conduct environmental qualifications, electromagnetic
interference and HERO testing on the 125 missiles selected for Technical Evaluation (DT
II); conduct safety certifications (man-rating); conduct technical flight tests, to include
eject-only, accuracy, and full-up warhead flight testing.
3.3.1. Mission-Oriented Approach. Omitted for training purposes.
3.3.2. Developmental Test Objectives. After a successful Technology Development and
Milestone B decision, the SRAW program will transition into Engineering Manufacturing
Development (EMD). Any deficiencies in the weapon system will be corrected. The system will
become man-rated. Critical technical parameters not specifically demonstrated during the previous
phase will be addressed during EMD. Failures will be reported in accordance with the Failure
Reporting Analysis and Corrective Action System (FRACAS), and used for assessment of
reliability. Detailed procedures will be provided in the detailed test plans. The objectives of EMD
DT&E are to successfully develop and demonstrate a weapon that will meet the physical
parameters set forth in the development specification, possess sufficient lethality to satisfy the
Marine Corps' requirement, and can be manufactured at a low cost. Specific objectives include:
Validating performance parameters, freezing the system design.
Building qualification hardware, and evaluating the design through qualification testing.
Verifying the lethality of the weapon system under realistic stand-off, velocity, angular
velocity, and component packaging conditions.
Verifying the accuracy and aerodynamic properties of the missile.
Demonstrating compatibility of all interfacing components/systems/subsystems,
especially the warhead, fuze and safe-and-arm device.
Analyzing SRAW susceptibility to countermeasures, to include target signature alteration,
active jammers, directed energy weapons and projectiles, high-powered microwaves, and
target camouflage and deception measures; enemy-induced electromagnetic interference
(EMI); hazards of electromagnetic radiation to ordnance (HERO). These tests should be
conducted to realistically simulate the actual threat.
Demonstrating MOUT capabilities.
Verifying compliance with the development specifications.
Providing data for more realistic cost estimates.
Obtaining data on the gunner aiming performance and gunner compatibility with the
launcher.
Obtaining a safety certification and man-rating.
Successfully demonstrating production-level components both individually and integrated
into a full-up system (missile and launcher).
Obtaining preliminary data for RAM, Human Factors and ILS assessments.
3.3.3. Modeling & Simulation (M&S). Omitted for training purposes
3.3.4. Test Limitations. The size, weight, and materials of the components and systems tested
during SRAW Technology Development phase will differ somewhat from the eventual production
model. Initially, breadboard components will be tested in laboratory and field tests. Subsystems
and modules will be tested before being assembled into actual flight-test missiles. Preliminary
flight tests shall be conducted with accuracy-configured missiles equipped with a dummy warhead
and ballistically matched to the tactical system. Once components have been successfully
demonstrated both at the breadboard level and integrated into the flight test missiles,
improvements in size, weight, design layout, and materials can be performed to produce a
production-level component.
3.4. Live Fire Test and Evaluation Approach. A formal Live Fire Test and Evaluation under Title
10 U.S. Code, Section 2366 "Major systems and munitions programs: survivability testing and
lethality testing required before full-scale production," with its associated independent report to
Congress, is not required for SRAW. However, certain developmental tests are planned. Tables 6,
7, and 8 list the full-up warhead test flights and lethality tests planned for both the nine
Engineering Model test flights and the technical evaluations (Techeval/DT II).
3.4.1. Live Fire Test Objectives. Omitted for training purposes.
3.4.2. Modeling & Simulation (M&S). Omitted for training purposes.
3.4.3. Test Limitations. Omitted for training purposes.
3.5 Certification for Initial Operational Test and Evaluation. The purpose of the Initial
Operational Test and Evaluation (IOT&E) of the Short Range Antitank Weapon (SRAW) is to
ensure that the system meets the mission needs and minimum operational performance
requirements identified in the CPD. This testing will evaluate the SRAW when it is employed by
the typical Marine user in a realistic environment. MCOTEA will plan, conduct, and report the
results of all operational testing.
3.6. Operational Evaluation Approach. An IOT&E of the SRAW will be conducted by
MCOTEA prior to the Full Rate Production Decision. The following paragraphs describe the
operational effectiveness and operational suitability Critical Operational Issues that are essential to
the evaluation of the SRAW's ability to perform its mission. The IOT&E will be conducted with
preproduction prototypes of the SRAW system. These prototypes must be representative of the
production system.
3.6.0.1 Operational testing of the SRAW will be conducted in four phases. During each of these
phases, data will be collected on the system which will be used to evaluate the operational
effectiveness and operational suitability of the SRAW. Throughout Phases I – IV, the SRAW will
be employed by properly trained Marines, in an operational environment.
3.6.0.2 Phase I will be approximately two weeks long and will include training of the Marines,
utilizing the contractor provided training program, and evaluation of that program. A pilot test to
evaluate the test program and the data collection and evaluation system will also be conducted
during this phase. An operational test readiness review (OTRR) will be held prior to advancing to
Phase II.
3.6.0.3 Phase II will consist of a series of tactical scenarios using a rifle platoon-sized unit against
representative threat targets. These scenarios will include day and night, and offensive and
defensive scenarios. MOUT operations will also be conducted during this phase of the test. This
phase of the test will be conducted at MCB Camp Pendleton, CA.
3.6.0.4 Phase III will integrate a platoon equipped with SRAW into a unit conducting a
Combined Arms Exercise (CAX) at MCAGCC, 29 Palms, CA. This phase will provide data on the
performance of the SRAW in a combined arms environment and will include comments from the
unit leadership and the Tactical Exercise Evaluation Control Group (TEECG).
3.6.0.5 Phase IV will evaluate the portability and transportability of the SRAW on amphibious
ships. This evaluation will be conducted by a squad-sized unit at the San Diego Naval Base and
Landing Force Training Command, Pacific. Marines will embark, debark, and travel through
various amphibious ships, as well as conduct dry net operations.
3.6.0.6 Susceptibility to enemy countermeasures will be operationally tested to the degree that
safety will allow. OT&E results will be adjusted to account for the effects of unverifiable
countermeasures based on an assessment of the capabilities of current threat countermeasures. It is
anticipated that DT data will be adequate to support the evaluation of the lethality of the SRAW.
3.6.0.7 Separate environmental testing will be conducted to cover environmental conditions not
encountered during the four phases listed above. It is anticipated that the extreme cold weather
requirements will have to be tested at a site other those for phases I – IV.
3.6.0.8 Operational Effectiveness Issues
(a) Will a Marine wearing full combat equipment, cold weather clothing, and/or MOPP
clothing, be able to carry the SRAW, and engage and destroy both stationary and moving
enemy armored vehicles with the SRAW?
(b) Will the SRAW enhance the chances of survivability of Marines firing it in comparison
to the current LAW system?
(c) Will the SRAW be safe to Marines to fire, including employment during Military
Operations in Urban Terrain (MOUT)?
(d) Will a Marine be able to satisfy the conditions set forth in (a) above with a SRAW at
night, if equipped with the current night vision sight or goggles?
3.6.0.9 Operational Suitability Issues
(a) Is the reliability, availability, and maintainability (RAM) of the SRAW suitable for
operational employment?
(b) Is the SRAW logistically supportable?
(c) Are SRAW training and documentation adequate to allow the average Marine to
employ this system in an operational environment?
(d) Does the SRAW function within current doctrine, tactics, and organization?
(e) Are the transportability and deployability of the SRAW suitable for operational
employment?
(f) Does the design of the SRAW incorporate sound human engineering principles?
(g) Is the SRAW safe for Marines to employ?
(h) Does the embedded software function properly in an operational environment?
3.6.1 Operational Test Objectives. All Critical Operational Issues listed in paragraphs 3.6.0.1
and 3.6.0.2 will be addressed during the IOT&E. Operational effectiveness and operational
suitability objectives for the SRAW will be examined by means of a thorough test and evaluation
which addresses each of the system requirements, as stated in the SRAW ROC/CDD. Operational
effectiveness objectives include: mission performance, survivability and vulnerability, and
cooperative systems. Operational suitability objectives include: RAM, deployability and
transportability, personnel selection and training, organizational impact, concept of employment,
logistics support, human factors and safety, and software.
3.6.2 Modeling and Simulation. Omitted for training purposes.
3.6.3 Test Limitations
(a) The effects of weather and terrain will be limited to those at MCB Camp Pendleton, CA;
MCAGCC 29 Palms, CA; and Naval Base, San Diego, CA.
(b) Availability of amphibious ships will limit the extent of amphibious compatibility testing.
(c) Due to the high cost and limited availability of EMD tactical missiles for OT, missile RAM
data collected during DT firings will be combined with OT data for the system evaluation. Only
those missile firings conducted without contractor involvement and in a representative combat
environment will be combined with OT firing data.
3.7 Other Certifications. Omitted for training purposes.
3.8 Reliability Growth. Omitted for training purposes.
3.9 Future Test and Evaluation. Omitted for training purposes.
4. PART IV - RESOURCE SUMMARY
4.1. Introduction. Omitted for training purposes.
4.1.1. Test Articles. The Engineering and Manufacturing Development Statement of Work
requires that the contractor deliver the following items: 125 Technical Evaluation (DT II) systems
12 inert mock-ups six cut-away mock-ups one flight model guidance & control unit. These items
will be used for testing of the weapon system's lethality, accuracy, and performance. See Table 5
for a list of test articles required for DT and OT.
4.1.2. Test Sites and Instrumentation. Tables 6, 7 and 8 list the facilities, equipment, and test
support services required to successfully complete developmental testing.
4.1.3. Test Support Equipment. Tables 9 and 10 list the government test services and facilities.
4.1.4. Threat Representation. Omitted for training purposes.
4.1.5. Test Targets and Expendables. The SRAW targets are to be Government-Furnished
Equipment (GFE).
4.1.6. Operational Force Test Support. See Table 5 for a list of test articles required for OT.
The following long-lead time, high-cost items will be needed for the IOT&E:
a. 103 Operational Evaluation (IOT&E) systems;
b. Training device(s) to be used as a low-cost alternative to actual IOT&E weapon systems
to train Marines participating in IOT&E;
c. Five T-72 target tanks (two must be operational);
d. Three BMP-2 target vehicles (two must be operational);
e. Four armored vehicle remote control kits;
The above items are based on testing of the anti-armor warhead. Additional mission warhead types
(i.e. bunker buster and flame variants) will increase/change the above requirements
4.1.7. Models, Simulations, and Testbeds. Omitted for training purposes.
4.1.8 Joint Mission Environment. Omitted for training purposes.
4.1.9. Special Requirements. Special requirements are to be determined by the contractor as
necessary to meet the SRAW requirements.
4.2. Federal, State, and Local Requirements. Omitted for training purposes.
4.3. Manpower/Personnel and Training. Omitted for training purposes.
4.4. Test Funding Summary. Omitted for training purposes.
Table 5 Test Articles
Subsystem test Duration of test Scope Location Full Qualification Tests: Vendors S&A Device ISA Propulsion Gas Generator Warhead
12 Weeks 12 Weeks 12 Weeks 12 Weeks 12 Weeks
Specified Env’t
NAWC China Lake, Ca
Ordnance Induced Failure Tests: Propulsion Gas Generator
4 weeks 4 weeks
NAWC China Lake, CA
Countermeasures testing 4 weeks Specified Env’t
Aberdeen, MD
Engineering Model Tests: Hardware in the loop tests Subsystem Integration and testing: 2 Missiles for prequel at Newport 7 flight test missiles for eject tests 5 flight test missiles w/telemetry 2 flight test missiles w/warhead
13 weeks 4 weeks 4 weeks 8 weeks 4 weeks
Loral
Limited Missile Qual Test 8 weeks Loral Preliminary EMI & ESD Tests 4 weeks W/o
Ordnance Loral
Preliminary HERO Tests 4 weeks NSWC Dahlgren, VA
Launcher tests: Round retention w/slug Closure release test 4 weeks
8 weeks
Immersion Drop tests closures
NAWC China Lake, CA
EM missile acceptance, vibration and temp tests
4 weeks Pre-flight Testing
NAWC China Lake, CA
EM Missile eject tests 7 each Remote launch
NAWC China Lake, CA
EM Missile flight test w/telemetry 5 each Remote Launch
NAWC China Lake, CA
EM Missile flight test w/ warhead 2 each Remote Launch
NAWC China Lake, CA
Table 6 Subsystem Tests
Test Number/Duration
of tests Scope Location
Airframe load test 4 weeks Launch force loads Loral Newport Beach
JRC Bench Checkout
20 weeks breadboard Loral
Guidance and control bench checkout
20 weeks breadboard Loral
TDD Bench checkout
20 weeks breadboard Loral
Launcher checkout 20 weeks functionality Loral Ordnance Dev’t tests: Propulsion E&V Warhead E&V Gas Generator
16 weeks 16 weeks 16 weeks
Subcontractor Verification w/ Loral oversight
Loral
Subsystem Acceptance Tests: JRC Guidance & Cont’l Tgt detect device S&A device Inertial Sensor Telemetry
4 weeks 4 weeks 4 weeks 4 weeks 4 weeks 4 weeks
Loral verification of final product
Loral
Subsystem Env’t Tests: JRC G&C TDD Airframe S&A device ISA Telemetry
4 weeks 4 weeks 4 weeks 4 weeks 4 weeks 4 weeks 4 weeks
Loral verification of final product
Loral
Table 7 Electro-Magnetic Missile Tests
DT-2 Tests Number/Duration Scope Location Weapons prequel flight test 8 each NAWC Weapon Env’t qual tests Block 1 Block 2 Block 3
11 each 11 each 11 each
NAWC
Fire through Brush test 2 each NAWC Weapon safety qual test 17 each NAWC Safety cert tests (man rating) Firing from enclosures
43 each 3 each
NAWC
Weapon performance Flight tests 32 weeks NAWC Final EMI & ESD tests NAWC Final HERO tests NAWC
Table 8 DT-2 Tests
Gov’t Service or Facility Time Frame Test Period Comments NAWC China Lake
Env’t test facility Solar Radiation Temperature Altitude Water Immersion Vibration Acceleration Sensing, photo, tape recording, timing Missile Assembly and Integration area
3 Explosive safe rooms 25 lbs of class 1.1 exp 115VAC, 1 phase 20A 2 explosive storage bunkers
June 06-March 07
May 05-Nov 06
Continuous
NSWC Dahlgren, VA HERO Tests Facilities and services
Aug 05-Sep 05 Aug 06-Sep 06
1 week 1 week
Aberdeen Proving Ground, MD
Countermeasure tests Test range and support CM devices, materials Targets Equipment storage facilities
Office area 115 vac Van power 20kVA Storage for secret mat’l Facilities and support personnel
June 06-July 06 2 weeks
Edgewood, MD CM tests Aerosols tests Facilities and support personnel
Yuma Proving Ground Parachute test facility Aircraft Crew Rigging Pallet material Tower drop facilities
Mar 07-Apr 07 2 weeks
Lapes Test Facility Aircraft Crew Rigging Pallet Material Loadmaster services
March 07-Apr 07
2 weeks
Table 9 Government Test Services and Facilities
Item Time frame Test period Comments Facilities
NSWC Dahlgren, VA
HERO Test facility NAWC
Aug 05-Sep 05
1 week
Missile assy area May 05-Nov 05 1 week Equipment
Aircraft for LAPES and parachute test LAPES parachute test rigging and pallets Stationary and moving armor targets Reactive Armor Stationary Armor target Enclosure test building Instrumentation for enclosure test:
Sound pressure level Toxic gas sensor
AN/PVS-4 night sight AN/PVS-7B night vision goggles NBC Gear Paratrooper Jump pack
Mar 07-Nov 07
Mar 07-Nov 07
July 05-Aug 05
June 05-May 07
July 05-Aug 05
Jan 07
Jan 07
TBD
TBD
TBD
TBD
1 week
1 week
Continuous
Continuous
Continuous
Continuous
Continuous
TBD
TBD
TBD
TBD
Services Aircraft flight crew for LAPES Enclosure Test instrumentation support personnel
March 07-Apr 07
Jan 07
2 weeks
1 week
Table 10 Government Furnished Facilities, Equipment, and Services
APPENDIX A. BIBLIOGRAPHY
A. Marine Corps Required Operational Capability (ROC) for Improved Light Anti-Tank Weapon
(ILAW), 6 August 1999. ROC INS 1.04a.
B. Marine Corps Required Operational Capability (ROC) for a Short Range Anti-tank Weapon
(SRAW), 3 September 1999. ROC INS 1.11
C. JROC Initial Capabilities Document (ICD) for a Short Range Anti-tank Weapon (SRAW), 20
October, 2003.
D. JROC Capabilities Development Document for Short Range Anti-Tank Weapon (SRAW), 20
November 2004.
E. SRAW Broad Agency Announcement, DARPA/NSWC #81-1 SRAW, N6092188-Q-B051.
F. SRAW Phase I Evaluation and Down Selection Procedures Plan (including Annex containing
the Measures of Effectiveness Criteria for Phase I Results and Phase II Plans).
G. Acquisition Plan for the Balanced Technology Initiative Short-Range, Anti-Tank Weapon
Program, NSWC Acquisition Plan Number DL-88-03.
H. Statement of Work for the SRAW Phase II Concept Development.
I. Statement of Work for the SRAW Technology Development Phase.
J. SRAW EMD Program Plan (Preliminary), 25 February 2003.
K. MIL-STD-882, System Safety Program Requirements.
L. NAVORD OR-44942 Weapons System Safety Guidelines Handbook.
APPENDIX B. ACRONYMS
6-DOF 6-Degrees of Freedom AMC-SWMO Army Materiel Command — Smart Weapons Management Office AAWS-M Advanced Antiarmor Weapon System — Medium CE Chemical Energy CG Commanding General CMC Commandant of the Marine Corps DARPA Defense Advanced Research Projects Agency DEW Directed Energy Weapon DT Developmental Test DTP Detailed Test Plan DT&E Developmental Test and Evaluation EM Engineering Model EMD Engineering Manufacturing Development EMI Electromagnetic Interference EOA Early Operational Assessment ESD Electrostatic Discharge FRACAS Failure Reporting Analysis and Corrective Action System FY Fiscal Year G&C Guidance & Control GFE Government Furnished Equipment HERO Hazards of Electromagnetic Radiation to Ordnance HPM High-Powered Microwave IER Independent Evaluation Report ILAW Improved Light Anti-Tank Weapon ILS Integrated Logistics Support ILSMT Integrated Logistics Support Management Team IOT&E Initial Operational Test & Evaluation IPR In Progress Review ISA Inertial Sensor Assembly JRCA Jet Reaction Control System LAPES Low Altitude Parachute Extraction System MCAGCC Marine Corps Air-Ground Combat Center MCCDC Marine Corps Combat Development Command MCO Marine Corps Order MCOTEA Marine Corps Operational Test and Evaluation Activity MCPDM Marine Corps Program Decision Memorandum MARCORSYSCO M
Marine Corps Systems Command
MOS Military Occupational Specialty MOUT Military Operations in Urban Terrain NAWC Naval Air Warfare Center
NLOS Non-Line-Of-Sight NSWC Naval Surface Warfare Center OPEVAL Operational Evaluation OT Operational Test PDA Principal Development Activity PEO Procurement Executive Officer PPQT Pre-Production Quality Testing RAM Reliability, Availability and Maintainability RHA Rolled Homogeneous Armor ROC Required Operational Capability S&A Safe & Arm SDI Strategic Defense Initiative SRAW Short Range Antitank Weapon TDD Target Detection Device TECHEVAL Technical Evaluation TEECG Tactical Exercise Evaluation Control Group TEMP Test and Evaluation Master Plan TOW Tube-launched, Optically tracked, Wire-guided Missile TPD Test Planning Document
APPENDIX C. POINTS OF CONTACT
TITLE NAME ORG COMM/AV PHONE
Omitted for training purposes.