Assignment 2: Project Schedule Changes You have kicked off the District 4 Production Warehouse Move project, your contractors are in place and working on receiving the proper building permits. You originally were told the permits would only take 2 week

profilePROJECT'S GEEK
m3_a2.xls

Sheet1

Task Start Date Duration End Date
Project Kick-off predecessors 1/1/14 4 5-Jan
Book location for meeting 1/1/14 1 2-Jan
Invite stakeholders 1/2/14 1 3-Jan
Prepare presentation 1/3/14 1 4-Jan
Conduct the meeting 1/4/14 1 5-Jan
Develop Charter/Scope 1/5/14 2 7-Jan
Develop WBS 1/7/14 7 14-Jan
Develop Project Plan 1/14/14 2 16-Jan
Develop Communication Plan 1/16/14 2 18-Jan
Develop Status Report 1/18/14 1 19-Jan
Set schedule for team meetings 1/19/14 1 20-Jan
Set schedule for stakeholder meetings 1/20/14 1 21-Jan
Meet with Framing/Drywall 1/21/14 1 22-Jan
Meet with Electrical 1/22/14 1 23-Jan
Meet with Plumbing 1/23/14 1 24-Jan
Meet with Finish Work 1/24/14 1 25-Jan
Meet with Student Workers 1/25/14 1 26-Jan
Obtain Electrical Permits 1/26/14 10 5-Feb
Obtain Plumbing Permits 2/5/14 10 15-Feb
Obtain Building Permits 2/15/14 10 25-Feb
Framing-Order Supplies 2/25/14 3 28-Feb
Framing-Build 2/28/14 15 15-Mar
Framing-Inspect 3/15/14 5 20-Mar
Framing-Project Sign-off 3/20/14 1 21-Mar
Electrical-Order Supplies 3/21/14 3 24-Mar
Electrical-Install 3/24/14 10 3-Apr
Electrical-Inspect 4/3/14 5 8-Apr
Electrical-Project Sign-off 4/8/14 1 9-Apr
Plumbing-Order Supplies 4/9/14 3 12-Apr
Plumbing-Install 4/12/14 10 22-Apr
Plumbing-Inspect 4/22/14 5 27-Apr
Plumbing-Project Sign-off 4/27/14 1 28-Apr
Drywall-Order Supplies 4/28/14 3 1-May
Drywall-Install 5/1/14 15 16-May
Drywall-Inspect 5/16/14 5 21-May
Drywall-Project Sign-off 5/21/14 1 22-May
Finish-Order Supplies 5/22/14 3 25-May
Finish-Install 5/25/14 15 9-Jun
Finish-Inspect 6/9/14 5 14-Jun
Finish-Project Sign-off 6/14/14 1 15-Jun
Workbenches-Order Supplies 6/15/14 2 17-Jun
Workbenches-Build 6/17/14 15 2-Jul
Workbenches-Quality inspection 7/2/14 2 4-Jul
Workbenches-Project Sign-off 7/4/14 1 5-Jul
Pack production equipment 7/5/14 2 7-Jul
Pack non-production equipment 7/7/14 2 9-Jul
Project Sign-off 7/9/14 1 10-Jul
Move production equipment 7/10/14 3 13-Jul
Move non-production equipment 7/13/14 3 16-Jul
Project Sign-off 7/16/14 1 17-Jul
Review contract work 7/17/14 3 20-Jul
Release contractors 7/20/14 1 21-Jul
Pay contractors 7/21/14 1 22-Jul
Final report 7/22/14 3 25-Jul
Archive documentation 7/25/14 3 28-Jul
Lessons Learned 7/28/14 1 29-Jul