Assignment 2: Project Schedule Changes You have kicked off the District 4 Production Warehouse Move project, your contractors are in place and working on receiving the proper building permits. You originally were told the permits would only take 2 week
Home>Business & Finance homework help>Management homework help>Assignment 2: Project Schedule Changes You have kicked off the District 4 Production Warehouse Move project, your contractors are in place and working on receiving the proper building permits. You originally were told the permits would only take 2 week
Sheet1
| Task | Start Date | Duration | End Date |
| Project Kick-off predecessors | 1/1/14 | 4 | 5-Jan |
| Book location for meeting | 1/1/14 | 1 | 2-Jan |
| Invite stakeholders | 1/2/14 | 1 | 3-Jan |
| Prepare presentation | 1/3/14 | 1 | 4-Jan |
| Conduct the meeting | 1/4/14 | 1 | 5-Jan |
| Develop Charter/Scope | 1/5/14 | 2 | 7-Jan |
| Develop WBS | 1/7/14 | 7 | 14-Jan |
| Develop Project Plan | 1/14/14 | 2 | 16-Jan |
| Develop Communication Plan | 1/16/14 | 2 | 18-Jan |
| Develop Status Report | 1/18/14 | 1 | 19-Jan |
| Set schedule for team meetings | 1/19/14 | 1 | 20-Jan |
| Set schedule for stakeholder meetings | 1/20/14 | 1 | 21-Jan |
| Meet with Framing/Drywall | 1/21/14 | 1 | 22-Jan |
| Meet with Electrical | 1/22/14 | 1 | 23-Jan |
| Meet with Plumbing | 1/23/14 | 1 | 24-Jan |
| Meet with Finish Work | 1/24/14 | 1 | 25-Jan |
| Meet with Student Workers | 1/25/14 | 1 | 26-Jan |
| Obtain Electrical Permits | 1/26/14 | 10 | 5-Feb |
| Obtain Plumbing Permits | 2/5/14 | 10 | 15-Feb |
| Obtain Building Permits | 2/15/14 | 10 | 25-Feb |
| Framing-Order Supplies | 2/25/14 | 3 | 28-Feb |
| Framing-Build | 2/28/14 | 15 | 15-Mar |
| Framing-Inspect | 3/15/14 | 5 | 20-Mar |
| Framing-Project Sign-off | 3/20/14 | 1 | 21-Mar |
| Electrical-Order Supplies | 3/21/14 | 3 | 24-Mar |
| Electrical-Install | 3/24/14 | 10 | 3-Apr |
| Electrical-Inspect | 4/3/14 | 5 | 8-Apr |
| Electrical-Project Sign-off | 4/8/14 | 1 | 9-Apr |
| Plumbing-Order Supplies | 4/9/14 | 3 | 12-Apr |
| Plumbing-Install | 4/12/14 | 10 | 22-Apr |
| Plumbing-Inspect | 4/22/14 | 5 | 27-Apr |
| Plumbing-Project Sign-off | 4/27/14 | 1 | 28-Apr |
| Drywall-Order Supplies | 4/28/14 | 3 | 1-May |
| Drywall-Install | 5/1/14 | 15 | 16-May |
| Drywall-Inspect | 5/16/14 | 5 | 21-May |
| Drywall-Project Sign-off | 5/21/14 | 1 | 22-May |
| Finish-Order Supplies | 5/22/14 | 3 | 25-May |
| Finish-Install | 5/25/14 | 15 | 9-Jun |
| Finish-Inspect | 6/9/14 | 5 | 14-Jun |
| Finish-Project Sign-off | 6/14/14 | 1 | 15-Jun |
| Workbenches-Order Supplies | 6/15/14 | 2 | 17-Jun |
| Workbenches-Build | 6/17/14 | 15 | 2-Jul |
| Workbenches-Quality inspection | 7/2/14 | 2 | 4-Jul |
| Workbenches-Project Sign-off | 7/4/14 | 1 | 5-Jul |
| Pack production equipment | 7/5/14 | 2 | 7-Jul |
| Pack non-production equipment | 7/7/14 | 2 | 9-Jul |
| Project Sign-off | 7/9/14 | 1 | 10-Jul |
| Move production equipment | 7/10/14 | 3 | 13-Jul |
| Move non-production equipment | 7/13/14 | 3 | 16-Jul |
| Project Sign-off | 7/16/14 | 1 | 17-Jul |
| Review contract work | 7/17/14 | 3 | 20-Jul |
| Release contractors | 7/20/14 | 1 | 21-Jul |
| Pay contractors | 7/21/14 | 1 | 22-Jul |
| Final report | 7/22/14 | 3 | 25-Jul |
| Archive documentation | 7/25/14 | 3 | 28-Jul |
| Lessons Learned | 7/28/14 | 1 | 29-Jul |
Sheet1
Start Date
Duration