Week 5 Individual Assignment: Risk Information Sheet

Learn from this week’s reading assignments to complete this assignment.

 

· Review Ch. 4, "Scope of Risk," of Business Continuity Management: Building an Effective Incident Management Plan

· Review Ch. 8, "IT Governance Issues: Risk Management, COSO ERM and OCEG Guidance," of Executive's Guide to IT Governance.

· Review the Week Five search strings.

Scenario: The Stevens Company is converting from the SQL Server database to the Oracle database.

Create: A Risk Information Sheet for at least five risks that might be encountered during the conversion. Follow the example below:

Risk Information Sheet (Example)

Risk ID: PO2-4-32

Date: March 4, 2014

Probability: 80%

Impact: High

Description:

Over 70% of the software components scheduled for reuse will be integrated into the application. The remaining functionality must be custom developed.

Refinement / Context:

· Certain reusable components were developed by a third party with no knowledge of internal design standards.

· Certain reusable components are implemented in a language unsupported on the target environment.

Mitigation / Monitoring:

· Contact the third party to determine conformance to design standards.

· Check to see if language support can be acquired.

Management / Contingency Plan / Trigger:

Develop a revised schedule assuming that 18 additional components must be built.

Current Status:

In Progress

Originator: Jane Manager

Assigned: John Analyst

Use the Template Below:

Risk Information Sheet

Risk ID:

Date:

Probability:

Impact:

Description:

Refinement / Context:

Mitigation / Monitoring:

Management / Contingency Plan / Trigger:

Current Status:

Originator:

Assigned: