Schedule the following activities using CPM:
Activity Immediate Predecessor Time (Weeks) A - 1 B A 4 C A 3 D B 2 E C, D 5 F D 2 G F 2 H E, G 3
a) Draw the network (5 points) b) What is the critical path? (15 points) c) How many weeks will it take to complete the project? (15 points) d) Which activities have slack, and how much? (15 points)
2. (50 points)—Forecasting
What strategies do supermarkets, airlines, hospitals, banks, and cereal manufacturers use to influence demand? Please provide 1 strategy for each and explain that strategy.