The 4 basic phases of a project life cycle as taught in this course include
Question 1 options:
|
|
|
||
|
|
|
||
|
|
|
||
|
|
|
Save
A project is defined as a specific job with a defined beginning, but NO specific end.
Question 2 options:
|
|
a) True |
|
|
b) False |
Save
A project sponsor provides
Question 3 options:
|
|
|
||
|
|
|
||
|
|
|
||
|
|
|
Save
Project scope defines what a project will and will not accomplish.
Question 4 options:
|
|
a) True |
|
|
b) False |
Save
Risk is greatest during the early phases of a project life, but the amount at stake is greatest during the later phases of a project.
Question 5 options:
|
|
a) True |
|
|
b) False |
Save
Identify the example in the list below that would not usually be considered a project.
Question 6 options:
|
|
|
||
|
|
|
||
|
|
|
||
|
|
|
Save
An effective project leader typically spends a minimal amount of their time communicating.
Question 7 options:
|
|
a) True |
|
|
b) False |
Save
The contemporary/interactionist view of conflict is that
Question 8 options:
|
|
|
||
|
|
|
||
|
|
|
||
|
|
|
Save
The output from a project is referred to as
Question 9 options:
|
|
a) Focus |
|
|
b) Deliverables |
|
|
c) Phases |
|
|
d) Tasks |
Save
A behavior that serves to equalize participation by increasing quiet member participation and decreasing overly active member participation is
Question 10 options:
|
|
|
||
|
|
|
||
|
|
|
||
|
|
|
Save
Consensus requires 100% team member agreement.
Question 11 options:
|
|
a) True |
|
|
b) False |
Save
Each team must define the rules of decision-making and consensus for themselves.
Question 12 options:
|
|
a) True |
|
|
b) False |
Save
Two truths and a lie is an example of a
Question 13 options:
|
|
|
||
|
|
|
||
|
|
|
||
|
|
|
Save
Facilitators protect people, ideas, and the process.
Question 14 options:
|
|
a) True |
|
|
b) False |
Save
It is important that scribes do not take the power of the pen and rephrase statements based on their own views.
Question 15 options:
|
|
a) True |
|
|
b) False |
Save
The rules of brainstorming indicate there can be no positive comments as well as no negative comments to individual ideas.
Question 16 options:
|
|
a) True |
|
|
b) False |
Save
Agreed upon standards of team behavior are called
Question 17 options:
|
|
|
||
|
|
|
||
|
|
|
||
|
|
|
Save
When completing a Project Charter, a decision must be made as to whether the project is a problem or an opportunity.
Question 18 options:
|
|
a) True |
|
|
b) False |
Save
Tracking progress is difficult because the project leader must maximize the status information gathered while minimizing the effort by the team to provide status.
Question 19 options:
|
|
a) True |
|
|
b) False |
Save
Team member feedback should be
Question 20 options:
|
|
|
||
|
|
|
||
|
|
|
||
|
|
|
Save
An event that represents a significant accomplishment at a specific point in time is called a
Question 21 options:
|
|
a) Finish Date |
|
|
b) Milestone |
|
|
c) Task |
|
|
d) Celebration |
Save
Each of the following is an element of project close-out management EXCEPT
Question 22 options:
|
|
a) Finishing the work |
|
|
b) Handing over the project |
|
|
c) Extending the project 2 more months |
|
|
d) Reviewing how it all went |
Save
Task is another term for work activity in a structured project plan.
Question 23 options:
|
|
a) True |
|
|
b) False |
Save
WBS is an acronym for
Question 24 options:
|
|
a) Work Breakdown Structure |
|
|
b) Work Breakdown System |
|
|
c) Work Based Standard |
|
|
d) World Based Standard |
Save
You are managing a large project that requires part of your project team to live in other countries with vast differences in time zones. A large number of project team members are also scattered around a large geographical region of your country. Which of the following is the LEAST practical method of communication?
Question 25 options:
|
|
|
||
|
|
|
||
|
|
|
||
|
|
|
Save
High level project estimates include all but which of the following:
Question 26 options:
|
|
|
||
|
|
|
||
|
|
|
||
|
|
|
Save
The construction foreman posted a large sign requiring all work site visitors to wear a hard hat and safety glasses. He also purchased large quantities of both items and made them readily available at the entrance. The foreman is engaged in
Question 27 options:
|
|
|
||
|
|
|
||
|
|
|
||
|
|
|
Save
Concurrent or parallel activities are:
Question 28 options:
|
|
a) Activities that can be performed at the same time |
|
|
b) Activities that use resources from the same resource pool |
|
|
c) Activities that use labor from the same group of workers |
|
|
d) Activities that must be done one after the other |
Save
Keith Monroe nails hundreds of pieces of culled lumber in the blazing July sun to finish his barn roof. He and his assistant are clearly in:
Question 29 options:
|
|
|
||
|
|
|
||
|
|
|
||
|
|
|
Save
A project that must be finished by December 31st is:
Question 30 options:
|
|
|
||
|
|
|
||
|
|
|
||
|
|
|
Save
If a project is behind schedule and team members have been absent, earned value calculations will indicate:
Question 31 options:
|
|
|
||
|
|
|
||
|
|
|
||
|
|
|
Save
If a project is behind schedule and team members have been working overtime but not making good progress due to technical difficulties, earned value calculations will indicate:
Question 32 options:
|
|
|
||
|
|
|
||
|
|
|
||
|
|
|
Save
Slack that affects successor tasks in a project plan is called
Question 33 options:
|
|
|
||
|
|
|
||
|
|
|
||
|
|
|
Save
Slack that affects the entire project duration is called
Question 34 options:
|
|
|
||
|
|
|
||
|
|
|
||
|
|
|
Save
The path in a project plan schedule that does not have any slack (zero slack) is called the critical path.
Question 35 options:
|
|
a) True |
|
|
b) False |
Save
Suppose your PV for a project is $100,000 and your EV is $60,000. What is the SPI for the project?
Question 36 options:
|
|
|
||
|
|
|
||
|
|
|
||
|
|
|
Save
Software installed on a computer is an example of a project deliverable.
Question 37 options:
|
|
a) True |
|
|
b) False |
Save
Effective change management accommodates customer or technical changes. As long as a change gets implemented, however, there is no need for the project team and sponsor/customer to agree on changes to the project scope before starting any work.
Question 38 options:
|
|
a) True |
|
|
b) False |
Save
Baselining a project is NOT important for monitoring and updating progress.
Question 39 options:
|
|
a) True |
|
|
b) False |
Save
Question 40 (1 point)
When evaluating project status it is important to compare expected versus actual.
Question 40 options:
|
|
a) True |
|
|
b) False |
Save
Question 41 (1 point)
The correct definition of resource leveling is:
Question 41 options:
|
|
|
||
|
|
|
||
|
|
|
||
|
|
|
Save
Question 42 (1 point)
Project resource constraints can involve which of the following examples:
Question 42 options:
|
|
|
||
|
|
|
||
|
|
|
||
|
|
|
Save
Question 43 (1 point)
When does a project close?
Question 43 options:
|
|
|
||
|
|
|
||
|
|
|
||
|
|
|
Save
Question 44 (1 point)
You have just completed your project and have to complete the final activities your company requires. Which of the following activities is NOT expected to be part of the project close-out?
Question 44 options:
|
|
|
||
|
|
|
||
|
|
|
||
|
|
|
Save
Question 45 (1 point)
The team has just completed work on the project. By all accounts, this was a difficult project from the beginning and the results bear this out. You were over budget by 20% and significantly behind your schedule. Morale became progressively worse in the face of the numerous challenges. At the close of the project, you decide to hold an informal meeting with the team to discuss the problems and identify their sources, all with the goal of trying to prevent something like this from happening again. This process is known as what?
Question 45 options:
|
|
|
||
|
|
|
||
|
|
|
||
|
|
|
Save
Question 46 (1 point)
The IT (Information Technology) implementation project is bogging down and falling behind schedule. The department heads are complaining that the project cannot help them if it is not implemented in a reasonable timeframe. Your project manager is considering putting extra resources to work on activities along the critical path to accelerate the schedule. This is an example of what?
Question 46 options:
|
|
|
||
|
|
|
||
|
|
|
||
|
|
|
Save
Question 47 (1 point)
A building contractor is working on a vacation home and is looking over his schedule. He notices that the schedule calls for the foundation footers to be poured and then the rough floor decking to be installed. In this plan, the decking would be an example of what type of activity?
Question 47 options:
|
|
|
||
|
|
|
||
|
|
|
||
|
|
|
Save
Question 48 (1 point)
The project administrator is preparing a preliminary budget for a project and adds in the cost of a new computer for the project team to use. What type of cost would this computer purchase represent?
Question 48 options:
|
|
|
||
|
|
|
||
|
|
|
||
|
|
|
Save
Question 49 (1 point)
Standard project reports include
Question 49 options:
|
|
|
||
|
|
|
||
|
|
|
||
|
|
|
Save
Question 50 (1 point)
If PV=$1,600, EV=$1,075, and AC=$1,290, CPI for the project is