CE 3361 PROJECT MANAGEMENT -1-

PROJECT IV SPRING 2016: DUE 3 MAY 2016

SHOW ALL WORK AND BE NEAT

1. ILLUSTRATE THE PROJECT MANAGER CONTRACT MODEL TYPICALLY USED IN MAJOR CONSTRUCTION ACTIVITIES SUCH AS POWER PLANTS.

(20)

2. WHAT ARE THREE PRINCIPAL DUTIES OF AN INSPECTOR ON A BUILDING

PROJECT?

(12) __ _________________________________________________________________

_________________________________________________________________ __

_______________________________________________________________ ___

_ ________________________________________________________________

________________________________________________________________

3. WHO HAS RESPONSIBILITY WHEN ALL THE TREES AT THE SITE DIE WHEN THERE A NO PROVISIONS IN THE CONTRACT FOR WATERING THE TREES DURING A DRY PERIOD? CHECK ALL CORRECT ANSWERS.

(8) OWNER ENGINEER

CONTRACTOR NATURE

WATER DEPARTMENT EX-PRESIDENT GEORGE BUSH

CE 3361 PROJECT MANAGEMENT -2-

PROJECT IV SPRING 2016: DUE 3 MAY 2016

4. LIST AT LEAST THREE BASIC ELEMENTS NEEDED ON ALL CONTRACT

DRAWINGS?

(12) ___________________________________________________________

___________________________________________________________

___________________________________________________________

___________________________________________________________

5. IS IT ETHICAL TO TAKE COMPANY PENCILS AND PAPER HOME FOR YOUR

CHILDREN TO USE AT SCHOOL BECAUSE YOUR EMPLOYER DID NOT

PAY YOU OVERTIME FOR YOUR WORK ON THE WEEKENDS?

(4) YES

NO

6. IN THE BIDDING STAGE, WHAT PROCEDURES DO YOU FOLLOW WHEN A

PROSPECTIVE CONTRACTOR CALLS YOUR OFFICE ASKING TO

SUBSTITUTE A DIFFERENT TYPE PIPE THAN SPECIFIED IN THE

CONTRACT? CHECK ALL ACCEPTABLE ANSWERS.

(12) INFORM THE CONTRACTOR THAT IT IS ACCEPTABLE

TO MAKE THE PIPE SUBSTITUTION AND YOU WILL WORK OUT

THE DETAILS LATER

INFORM THE CONTRACTOR THAT IT IS ACCEPTABLE

TO MAKE THE PIPE SUBSTITUTION AS LONG AS THEY

MAKE A FINANCIAL CONTIBUTION TO YOUR

RETIREMENT FUND

TELL THE BIDDER THAT YOUR DO NOT GIVE ANSWERS

ON THE PHONE AND TO SUBMIT THE QUESTION IN

WRITING FOR A RESPONSE THAT WILL BE GIVEN TO ALL

PROSPECTIVE BIDDERS

REFUSE TO ANSWER THE QUESTION AND HANG UP THE PHONE

CE 3361 PROJECT MANAGEMENT -3-

PROJECT IV SPRING 2016: DUE 3 MAY 2016

7. AT WHAT STAGE IN THE PROJECT SHOULD THE COST AND SCHEDULE ESTIMATE BE PERFORMED?

(9) FEASIBILITY

PREPARATION OF DRAWINGS

ANYTIME PRIOR TO PREPARATION OF THE FINAL

CONTRACT DOCUMENTS

8. WHAT ARE THE RESPONSIBILITIES OF THE OWNER AS A PARTY TO A CONSTRUCTION CONTRACT?

(10) _ ______________________________________________________________

________________________________________________________________

___________________________________ ____________________________

_________________________ ______________________________________

9. WHO HAS DESIGN RESPONSIBILITY FOR MAKING CHANGES IN THE CONTRACT?

(6) OWNERS ENGINEER

CONTRACTOR CONTRACTOR’S ENGINEER

CE 3361 PROJECT MANAGEMENT -4-

PROJECT IV SPRING 2016: DUE 3 MAY 2016

ANNOTATED MEANS ESTIMATING SHEETS ON MOODLE

10. YOUR ENGINEERING FIRM HAS BEEN CONTRACTED TO SOLVE A SEWER

LEAK IN A CLAY TILE PIPE NEXT TO THE LUCKY LADY HORSE

BARN. YOUR RECOMMENDATION IS TO REMOVE THE EXISTING

SEWER AND REPLACE THE ENTIRE 300-FT LONG SECTION WITH A NEW

6-IN. DIAMETER PVC PIPE. YOUR DESIGN REQUIRES A 5-FT WIDE

BY 6.7 FT DEEP EXCAVATION WITH VERTICAL SIDE WALLS (SEE FIG. 1 IN

MOODLE).

A. YOU CALL DR. MAHAR FOR HIS ADVISE AND HE GIVES YOU THE FOLLOWING LIST OF ACTIVITIES AND THE ACTIVITY SEQUENCE:

· REPLACE ASPHALT - PLACE/COMPACT GRANULAR

BASE COURSE

· LAYOUT SEWER LINE - EXCAVATE ASPHALT AND

SOIL AND REMOVE

DAMAGE PIPE

· COMPACT SOIL BENEATH - PLACE NEW 6 IN. PVC PIPE

NEW PVC PIPE

· BACKFILL AND COMPACT - PAVEMENT MARKINGS

TRENCH

B. THE ACTIVITY SEQUENCE FOR REPLACING THE DAMAGED SEWER

LINE IS GIVEN AS FOLLOWS:

____LAYOUT SEWER LINE _____________________________

____EXCAVATE ASPHALT AND REMOVE DAMAGED PIPE______

____COMPACT SOIL BENEATH NEW PVC PIPE _________ ______

(16) ____PLACE NEW PVC PIPE _________________________ _________

____BACKFILL AND COMPACT TRENCH _____________________

PLACE/COMPACT BASE COARSE BENEATH ASPHALT_____

____REPLACE ASPHALT_____________________________________

____PAVEMENT MARKINGS__________________________________

CE 3361 PROJECT MANAGEMENT -5-

PROJECT IV SPRING 2016: DUE 3 MAY 2016

ANNOTATED MEANS ESTIMATING SHEETS ON MOODLE

11 PREPARE A QUANTITY TAKE OFF FOR EACH ACTIVITY - FILL IN

FOLLOWING TABLE.

ITEM ACTIVITY UNIT ESTIMATED QUANTITY

1 LAYOUT

2

3

4 PLACE PIPE

5

6 BASE COURSE CY

7

8 LF 100

AC - ACRES: 1 FT2 = 0.00002296 ACRES

CY - CUBIC YARDS: 27 FT3/CY

LF - LINEAR FEET

SY – SQUARE YARDS: 9 FT2/SY

FIG. 1 EXCAVATION CROSS-SECTION (SEPARATE PAGE IN MOODLE)

CE 3361 PROJECT MANAGEMENT -6-

PROJECT IV SPRING 2016: DUE 3 MAY 2016

ANNOTATED MEANS ESTIMATING SHEETS ON MOODLE

12. PREPARE AN ENGINEER COST ESTIMATE FOR PERFORMING THE SEWER

REPLACEMENT WORK (MEANS ESTIMATING SHEETS ON MOODLE).

ITEM ACTIVITY UNIT ESTIMATED UNIT PRICE TOTAL

QUANTITY COST

1

2 EXCAVATE CY

3

4

5

6 CY

7

8 MARKINGS LF 100

CE 3361 PROJECT MANAGEMENT -7-

PROJECT IV SPRING 2016: DUE 3 MAY 2016

ANNOTATED MEANS ESTIMATING SHEETS ON MOODLE

13. PREPARE AN ENGINEER SCHEDULE ESTIMATE FOR PERFORMING THE

SEWER REPLACEMENT WORK (MEANS ESTIMATING SHEETS ON MOODLE).

ITEM ACTIVITY UNIT QUANTITY DAILY DURATION

PRODUCTION

1

2 EXCAVATE CY

3

4

5

6 CY

7

8 MARKINGS LF

14. PREPARE A BAR CHART SCHEDULE FOR MANAGING THE SEWER

REPLACEMENT WORK. (USE A SEPARATE SHEET OF PAPER)

15. IDENTIFY 3 SAFETY/ENVIRONMENTAL CONCERNS. DO NOT FORGET THE

SNAKE FENCE.

___ ___________________________________________________________

_________________________________________________________________

(9) ________________________________ _________________________________

______________________________________________ ___________________

BY SIGNING THIS PAGE, I HAVE NOT GIVEN OR RECEIVED HELP FROM THE

OTHER STUDENTS.

NAME:__________________ SIGNED:__________________________