Robin Lane and top management has approved the schedule generated at the end of part 3. Save the file containing this schedule as a baseline schedule. Review the file and answer the following questions:
1. How much is the project estimated to cost?
2. What activity is estimated to cost the most to complete?
3. What resource commands the greatest total cost?
4. During which month of the project are the highest and lowest costs expected to occur? What are these costs?
5. What likely costs are not contained in this budget?