Re: Project Management Resource Assignment
ID Task
Mode
Task Name Duration Start Finish Predecessors Resource Names
0 Riordan HR Integration Software Development
122 days Mon 7/4/16
Tue 12/20/16
1 Scope 4 days Mon 7/4/16 Thu 7/7/16
2 Determine project scope 8 hrs Mon 7/4/16 Mon 7/4/16 Project Manager
3 Secure project sponsorship 1 day Tue 7/5/16 Tue 7/5/16 2 Project Manager,Project Sponsor
4 Define preliminary resources 1 day Wed 7/6/16 Wed 7/6/16 3 Project Manager,Project Sponsor
5 Secure core resources 1 day Thu 7/7/16 Thu 7/7/16 4 Project Manager,Project Sponsor
6 Scope complete 0 days Thu 7/7/16 Thu 7/7/16 5
7 Analysis/Software Requirements
14 days Fri 7/8/16 Wed 7/27/16
8 Conduct needs analysis 5 days Fri 7/8/16 Thu 7/14/16 6 HR Manager,Project Manager
9 Draft preliminary software specifications
3 days Fri 7/15/16 Tue 7/19/16 8 HR Manager,IT Admin,Project Manager
10 Develop preliminary budget 2 days Wed 7/20/16
Thu 7/21/16 9 Project Manager
11 Review software specifications/budget with team
4 hrs Fri 7/22/16 Fri 7/22/16 10 Project Manager,Analyst
12 Incorporate feedback on software specifications
1 day Fri 7/22/16 Mon 7/25/16
11 Analyst
13 Develop delivery timeline 1 day Mon 7/25/16
Tue 7/26/16 12 Project Manager
14 Obtain approvals to proceed (concept, timeline, budget)
4 hrs Tue 7/26/16 Tue 7/26/16 13 Project Sponsor,Project Manager
15 Secure required resources 1 day Wed 7/27/16
Wed 7/27/16
14 Project Manager
Page 1
ID Task
Mode
Task Name Duration Start Finish Predecessors Resource Names
16 Analysis complete 0 days Wed 7/27/16
Wed 7/27/16
15
17 Design 14.5 days Thu 7/28/16 Wed 8/17/16
18 Review preliminary software specifications
2 days Thu 7/28/16 Fri 7/29/16 16 HR Manager
19 Develop functional specifications
5 days Mon 8/1/16 Fri 8/5/16 18 Developer
20 Develop prototype based on functional specifications
4 days Mon 8/8/16 Thu 8/11/16 19 Developer
21 Review functional specifications
2 days Fri 8/12/16 Mon 8/15/16
20 Project Manager,HR Manager,IT Manager
22 Incorporate feedback into functional specifications
1 day Tue 8/16/16 Tue 8/16/16 21 Project Manager
23 Obtain approval to proceed 4 hrs Wed 8/17/16
Wed 8/17/16
22 Project Manager,Project Sponsor
24 Design complete 0 days Wed 8/17/16
Wed 8/17/16
23
25 Development 48 days Wed 8/17/16
Mon 10/24/16
26 Review functional specifications
1 day Wed 8/17/16
Thu 8/18/16 24 Developer
27 Identify modular/tiered design parameters
1.5 days Thu 8/18/16 Wed 8/31/16
26 Developer,Analyst
28 Assign development staff 1 day Wed 8/31/16
Thu 9/1/16 27 Developer
29 Develop code 15 days Thu 9/1/16 Thu 9/22/16 28 Developer
30 Developer testing (primary debugging)
15 days Thu 9/22/16 Mon 10/24/16
29FS-75% Developer
31 Development complete 0 days Mon 10/24/16Mon 10/24/1630
32 Testing 73.5 days Fri 8/19/16 Wed 11/30/16
Page 2
ID Task
Mode
Task Name Duration Start Finish Predecessors Resource Names
33 Develop unit test plans using product specifications
4 days Fri 8/19/16 Wed 8/24/16
24 Testers,Developer
34 Develop integration test plans using product specifications
4 days Thu 8/25/16 Tue 8/30/16 24 Testers,Developer
35 Unit Testing 15 days Mon 10/24/16Mon 11/14/16
36 Review modular code 5 days Mon 10/24/16Mon 10/31/1633,31 Project Team
37 Test component modules to product specifications
2 days Mon 10/31/16
Wed 11/2/16
31,36 Testers
38 Identify anomalies to product specifications
3 days Wed 11/2/16
Mon 11/7/16
37 Project Team
39 Modify code 3 days Mon 11/7/16
Thu 11/10/16
38 Project Team
40 Re-test modified code 2 days Thu 11/10/16
Mon 11/14/16
39 Project Team
41 Unit testing complete 0 days Mon 11/14/16Mon 11/14/1640
42 Integration Testing 12 days Mon 11/14/16
Wed 11/30/16
43 Test module integration 5 days Mon 11/14/16
Mon 11/21/16
41 Testers
44 Identify anomalies to specifications
2 days Mon 11/21/16
Wed 11/23/16
43 Testers
45 Modify code 3 days Wed 11/23/16
Mon 11/28/16
44 Testers
46 Re-test modified code 2 days Mon 11/28/16
Wed 11/30/16
45 Testers
47 Integration testing complete
0 days Wed 11/30/16
Wed 11/30/16
46
48 Training 62.5 days Wed 8/31/16
Fri 11/25/16
Page 3
ID Task
Mode
Task Name Duration Start Finish Predecessors Resource Names
49 Develop training specifications for end users
3 days Wed 8/31/16
Fri 9/2/16 24 Trainers,HR Manager
50 Develop training specifications for helpdesk support staff
3 days Mon 9/5/16 Wed 9/7/16 24 Trainers
51 Identify training delivery methodology (computer based training, classroom, etc.)
2 days Thu 9/8/16 Fri 9/9/16 24 Trainers
52 Develop training materials 3 wks Mon 10/24/16
Mon 11/14/16
49,31,50,51 Trainers
53 Conduct training usability study
4 days Mon 11/14/16
Fri 11/18/16 52 Trainers
54 Finalize training materials 3 days Fri 11/18/16 Wed 11/23/16
53 Trainers
55 Develop training delivery mechanism
2 days Wed 11/23/16
Fri 11/25/16 54 Trainers
56 Training materials complete 0 days Fri 11/25/16 Fri 11/25/16 55
57 Documentation 50.5 days Mon 9/12/16
Mon 11/21/16
58 Develop Help specification 2 days Mon 9/12/16
Wed 10/5/16
24 IT Admin,IT Manager
59 Develop Help system 3 wks Mon 10/24/16
Mon 11/14/16
58,29FS-50% Developer
60 Review Help documentation 3 days Mon 11/14/16
Thu 11/17/16
59 IT Manager
61 Incorporate Help documentation feedback
2 days Thu 11/17/16
Mon 11/21/16
60 IT Admin,Project Team
62 Develop user manuals specifications
2 days Mon 9/12/16
Tue 9/13/16 24 Analyst,IT Admin
63 Develop user manuals 3 wks Wed 9/14/16
Tue 10/4/16 62,29FS-50% Analyst,IT Admin
Page 4
ID Task
Mode
Task Name Duration Start Finish Predecessors Resource Names
64 Review all user documentation
2 days Wed 10/5/16
Thu 10/6/16 63 IT Manager
65 Incorporate user documentation feedback
2 days Fri 10/7/16 Mon 10/10/16
64
66 Documentation complete 0 days Mon 11/21/16
Mon 11/21/16
65,61
67 Pilot 96.5 days Thu 7/28/16 Fri 12/9/16
68 Identify test group 1 day Thu 7/28/16 Thu 7/28/16 16 Project Manager
69 Develop software delivery mechanism
1 day Fri 7/29/16 Fri 7/29/16 68 Deployment Team
70 Install/deploy software 1 day Wed 11/30/16
Thu 12/1/16 47,69,66,56 Deployment Team
71 Obtain user feedback 1 wk Thu 12/1/16 Thu 12/8/16 70 Deployment Team
72 Evaluate testing information 1 day Thu 12/8/16 Fri 12/9/16 71 Deployment Team
73 Pilot complete 0 days Fri 12/9/16 Fri 12/9/16 72
74 Deployment 4.5 days Fri 12/9/16 Thu 12/15/16
75 Determine final deployment strategy
1 day Fri 12/9/16 Mon 12/12/16
73 Project Team
76 Develop deployment methodology
0.5 days Mon 12/12/16
Mon 12/12/16
75 Project Team
77 Secure deployment resources
1 day Tue 12/13/16
Tue 12/13/16
76 Project Team
78 Train support staff 1 day Wed 12/14/16
Wed 12/14/16
77 Project Team
79 Deploy software 1 day Thu 12/15/16
Thu 12/15/16
78 Project Team
80 Deployment complete 0 days Thu 12/15/16
Thu 12/15/16
79
Page 5
ID Task
Mode
Task Name Duration Start Finish Predecessors Resource Names
81 Post Implementation Review 3 days Fri 12/16/16 Tue 12/20/16
82 Document lessons learned 1 day Fri 12/16/16 Fri 12/16/16 80 Project Manager,Project Team
83 Distribute to team members 1 day Mon 12/19/16
Mon 12/19/16
82 Project Manager
84 Create software maintenance team
1 day Tue 12/20/16
Tue 12/20/16
83 Project Manager
85 Post implementation review complete
0 days Tue 12/20/16
Tue 12/20/16
84
86 Software development complete
0 days Tue 12/20/16
Tue 12/20/16
85
Page 6