Project Management Problems
Problem 11.
Figure #2 is incorrect due to node B Figure #3 is incorrect due to node E
Problem 12.
Critical Path Problem with Slack Calculations: used copy/paste
Problem 13.
Another example of Critical Path, Slack and Total Project Time/cell C23 – used copy/paste
Problem 14.
Example utilizing Early Start/Early Finish, and Late Start/Late Finish – used copy/paste
Problem 15.
Project Management Example with triple time estimate, also identifies Critical Path/0 slack
Project Management Example with triple time estimate, also identifies Critical Path/0 slack and “red” – used POMQ
Problem 16.
Project Management Example with triple time estimate, also identifies Critical Path/0 slack
Project Management Example with triple time estimate, also identifies Critical Path/0 slack and “red” – used POMQ
Problem 17.
Problem 18.
Project Crashing – used POMQ
Answer – go across Project time = 7 and you will see the project crashing time
A=0, B=1, C=3, E=0, F=0 Total Crashing Cost = B1 ($110) + C3 ($200) = $110+$600 = $710
Problem 19.
Total cost of crashing by two days = $600 + $850 = $1,450