86 ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
4 - P R O J E C T I N T E G R AT I O N M A N A G E M E N T
Human resource management plan,
Communications management plan,
Risk management plan,
Procurement management plan,
Stakeholder management plan, and
Project baselines.
4.3.3.5 Project Documents Updates
Project documents that may be updated include, but are not limited to:
Requirements documentation,
Project logs (issues, assumptions, etc.),
Risk register, and
Stakeholder register.
4.4 Monitor and Control Project Work
Monitor and Control Project Work is the process of tracking, reviewing, and reporting the progress to meet the
performance objectives defined in the project management plan. The key benefit of this process is that it allows
stakeholders to understand the current state of the project, the steps taken, and budget, schedule, and scope
forecasts. The inputs, tools and techniques, and outputs for this process are depicted in Figure 4-8. Figure 4-9
depicts the data flow diagram of the process.
Inputs Tools & Techniques Outputs
.1 Project management plan
.2 Schedule forecasts
.3 Cost forecasts
.4 Validated changes
.5 Work performance information .6 Enterprise environmental factors .7 Organizational process assets
.1 Expert judgment
.2 Analytical techniques
.3 Project management information system .4 Meetings
.1 Change requests
.2 Work performance reports .3 Project management plan updates .4 Project documents updates
Figure 4-8. Monitor and Control Project Work: Inputs, Tools & Techniques, and Outputs
87©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
4 - P R O J E C T I N T E G R AT I O N M A N A G E M E N T
4
e
W
W
Cost forecasts
P
P
W
4.4 Monitor and
Control Project Work
4.5 Perform
Integrated Change Control
Project Integration Management
O
9.4 Manage
Project Team
10.2 Manage
Communications
11.6 Control Risks
12.3 Control
Procurements
Project Documents
10.3 Control
Communications
5.6 Control Scope
5.5 Validate Scope
6.7 Control Schedule
7.4 Control Costs
12.3 Control
Procurements
11.6 Control Risks
8.3 Control Quality
13.4 Control
Stakeholder Engagement
Enterprise/ Organization
4.2 Develop Project Management
Plan
Figure 4-9. Monitor and Control Project Work Data Flow Diagram
88 ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
4 - P R O J E C T I N T E G R AT I O N M A N A G E M E N T
Monitoring is an aspect of project management performed throughout the project. Monitoring includes collecting,
measuring, and distributing performance information, and assessing measurements and trends to effect process
improvements. Continuous monitoring gives the project management team insight into the health of the project and
identifies any areas that may require special attention. Control includes determining corrective or preventive actions
or replanning and following up on action plans to determine whether the actions taken resolved the performance
issue. The Monitor and Control Project Work process is concerned with:
Comparing actual project performance against the project management plan;
Assessing performance to determine whether any corrective or preventive actions are indicated, and
then recommending those actions as necessary;
Identifying new risks and analyzing, tracking, and monitoring existing project risks to make sure the risks
are identified, their status is reported, and that appropriate risk response plans are being executed;
Maintaining an accurate, timely information base concerning the project’s product(s) and their associated
documentation through project completion;
Providing information to support status reporting, progress measurement, and forecasting;
Providing forecasts to update current cost and current schedule information;
Monitoring implementation of approved changes as they occur; and
Providing appropriate reporting on project progress and status to program management when the project
is part of an overall program.
4.4.1 Monitor and Control Project Work: Inputs
4.4.1.1 Project Management Plan
Described in Section 4.2.3.1. Monitoring and controlling project work involves looking at all aspects of the
project. Subsidiary plans within the project management plan form the basis for controlling the project. Subsidiary
plans and baselines include, but are not limited to:
89©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
4 - P R O J E C T I N T E G R AT I O N M A N A G E M E N T
4
Scope management plan (Section 5.1.3.1),
Requirements management plan (Section 5.1.3.2),
Schedule management plan (Section 6.1.3.1),
Cost management plan (Section 7.1.3.1),
Quality management plan (Section 8.1.3.1),
Process improvement plan (Section 8.1.3.2),
Human resource management plan (Section 9.1.3.1),
Communications management plan (Section 10.1.3.1),
Risk management plan (Section 11.1.3.1),
Procurement management plan (Section 12.1.3.1),
Stakeholder management plan (Section 13.2.3.1),
Scope baseline (Section 5.4.3.1),
Schedule baseline (Section 6.6.3.1), and
Cost baseline (Section 7.3.3.1).
4.4.1.2 Schedule Forecasts
Described in Section 6.7.3.2. The schedule forecasts are derived from progress against the schedule baseline
and computed time estimate to complete (ETC). This is typically expressed in terms of schedule variance (SV) and
schedule performance index (SPI). For projects not using earned value management, variances against the planned
finish dates and forecasted finish dates are provided.
The forecast may be used to determine if the project is still within defined tolerance ranges and identify any
necessary change requests.
4.4.1.3 Cost Forecasts
Described in Section 7.4.3.2. The cost forecasts are derived from progress against the cost baseline and computed
estimates to complete (ETC). This is typically expressed in terms of cost variance (CV) and cost performance index
(CPI). An estimate at completion (EAC) can be compared to the budget at completion (BAC) to see if the project is
still within tolerance ranges or if a change request is required. For projects not using earned value management,
variances against the planned versus actual expenditures and forecasted final costs are provided.
90 ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
4 - P R O J E C T I N T E G R AT I O N M A N A G E M E N T
4.4.1.4 Validated Changes
Described in Section 8.3.3.2. Approved changes that result from the Perform Integrated Change Control process
require validation to ensure that the change was appropriately implemented. A validated change provides the
necessary data to confirm that the change was appropriately executed.
4.4.1.5 Work Performance Information
Work performance information is the performance data collected from various controlling processes, analyzed
in context, and integrated based on relationships across areas. Thus work performance data has been transformed
into work performance information. Data in itself cannot be used in the decision-making process as it has only
out-of-context meaning. Work performance information, however, is correlated and contextualized, and provides a
sound foundation for project decisions.
Work performance information is circulated through communication processes. Examples of performance
information are status of deliverables, implementation status for change requests, and forecasted estimates to
complete.
4.4.1.6 Enterprise Environmental Factors
Described in Section 2.1.5. The enterprise environmental factors that can influence the Monitor and Control
Project Work process include, but are not limited to:
Governmental or industry standards (e.g., regulatory agency regulations, codes of conduct, product
standards, quality standards, and workmanship standards),
Organization work authorization systems,
Stakeholder risk tolerances, and
Project management information system (e.g., an automated tool suite, such as a scheduling software
tool, a configuration management system, an information collection and distribution system, or web
interfaces to other online automated systems).
91©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
4 - P R O J E C T I N T E G R AT I O N M A N A G E M E N T
4
4.4.1.7 Organizational Process Assets
Described in Section 2.1.4. The organizational process assets that can influence the Monitor and Control Project
Work process include, but are not limited to:
Organizational communication requirements;
Financial controls procedures (e.g., time reporting, required expenditure and disbursement reviews,
accounting codes, and standard contract provisions);
Issue and defect management procedures defining issue and defect controls, issue and defect
identification, and resolution and action item tracking;
Change control procedures, including those for scope, schedule, cost, and quality variances;
Risk control procedures including risk categories, probability definition and impact, and probability and
impact matrix;
Process measurement database used to make available measurement data on processes and products;
and
Lessons learned database.
4.4.2 Monitor and Control Project Work: Tools and Techniques
4.4.2.1 Expert Judgment
Expert judgment is used by the project management team to interpret the information provided by the monitor
and control processes. The project manager, in collaboration with the team, determines the actions required to
ensure that project performance matches expectations.
4.4.2.2 Analytical Techniques
Analytical techniques are applied in project management to forecast potential outcomes based on possible
variations of project or environmental variables and their relationships with other variables. Examples of analytical
techniques used in projects are:
Regression analysis,
Grouping methods,
Causal analysis,
92 ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
4 - P R O J E C T I N T E G R AT I O N M A N A G E M E N T
Root cause analysis,
Forecasting methods (e.g., time series, scenario building, simulation, etc.),
Failure mode and effect analysis (FMEA),
Fault tree analysis (FTA),
Reserve analysis,
Trend analysis,
Earned value management, and
Variance analysis.
4.4.2.3 Project Management Information System
The project management information system, which is part of enterprise environmental factors, provides access
to automated tools, such as scheduling, cost, and resourcing tools, performance indicators, databases, project
records, and financials used during the Monitor and Control Project Work process.
4.4.2.4 Meetings
Described in Section 4.3.2.3. Meetings may be face-to-face, virtual, formal, or informal. They may include
project team members, stakeholders, and others involved in or affected by the project. Types of meetings include,
but are not limited to, user groups and review meetings.
4.4.3 Monitor and Control Project Work: Outputs
4.4.3.1 Change Requests
As a result of comparing planned results to actual results, change requests may be issued to expand, adjust, or
reduce project scope, product scope, or quality requirements and schedule or cost baselines. Change requests may
necessitate the collection and documentation of new requirements. Changes can impact the project management
plan, project documents, or product deliverables. Changes that meet the project’s change control criteria should go
through the integrated change control process established for the project. Changes may include, but are not limited
to, the following:
93©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
4 - P R O J E C T I N T E G R AT I O N M A N A G E M E N T
4
Corrective action—An intentional activity that realigns the performance of the project work with the
project management plan;
Preventive action—An intentional activity that ensures the future performance of the project work is
aligned with the project management plan; and
Defect repair—An intentional activity to modify a nonconforming product or product component.
4.4.3.2 Work Performance Reports
Work performance reports are the physical or electronic representation of work performance information
compiled in project documents, intended to generate decisions, actions, or awareness. Project information may be
communicated verbally from person to person. However, in order to record, store, and sometimes distribute work
performance information, a physical or electronic representation in the form of project documents is required. Work
performance reports are a subset of project documents, which are intended to create awareness and generate
decisions or actions. Specific work performance metrics may be defined at the start of the project and included in
the normal work performance reports provided to key stakeholders.
Examples of work performance reports include status reports, memos, justifications, information notes,
recommendations, and updates.
4.4.3.3 Project Management Plan Updates
Changes identified during the Monitor and Control Project Work process may affect the overall project
management plan. These changes, after being processed through the appropriate change control process can lead
to project management plan updates. Project management plan elements that may be updated include, but are
not limited to:
Scope management plan (Section 5.1.3.1),
Requirements management plan (Section 5.1.3.2),
Schedule management plan (Section 6.1.3.1),
Cost management plan (Section 7.1.3.1),
Quality management plan (Section 8.1.3.1),
Scope baseline (Section 5.4.3.1),
Schedule baseline (Section 6.6.3.1), and
Cost baseline (Section 7.3.3.1).
94 ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
4 - P R O J E C T I N T E G R AT I O N M A N A G E M E N T
4.4.3.4 Project Documents Updates
Project documents that may be updated include, but are not limited to:
Schedule and cost forecasts,
Work performance reports, and
Issue log.
4.5 Perform Integrated Change Control
Perform Integrated Change Control is the process of reviewing all change requests; approving changes and
managing changes to deliverables, organizational process assets, project documents, and the project management
plan; and communicating their disposition. It reviews all requests for changes or modifications to project documents,
deliverables, baselines, or the project management plan and approves or rejects the changes. The key benefit of
this process is that it allows for documented changes within the project to be considered in an integrated fashion
while reducing project risk, which often arises from changes made without consideration to the overall project
objectives or plans. The inputs, tools and techniques, and outputs of this process are depicted in Figure 4-10. Figure
4-11 depicts the data flow diagram of the process.
Inputs Tools & Techniques Outputs
.1 Project management plan
.2 Work performance reports .3 Change requests .4 Enterprise environmental factors .5 Organizational process assets
.1 Expert judgment
.2 Meetings
.3 Change control tools
.1 Approved change requests .2 Change log .3 Project management plan updates .4 Project documents updates
Figure 4-10. Perform Integrated Change Control: Inputs, Tools & Techniques, and Outputs
95©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
4 - P R O J E C T I N T E G R AT I O N M A N A G E M E N T
4
P
P
P C
C
A
C
C
Wo
Project Integration Management
O
8.3 Control Quality
12.3 Control
Procurements
13.3 Manage
Stakeholder Engagement
Project Documents
8.3 Control Quality
8.2 Perform Quality
Assurance
7.4 Control Costs
6.7 Control Schedule
5.6 Control Scope
5.5 Validate Scope
11.6 Control Risks
12.2 Conduct
Procurements
10.3 Control
Communications
9.4 Manage
Project Team
12.3 Control
Procurements
13.3 Manage
Stakeholder Engagement
13.4 Control
Stakeholder Engagement
12.1 Plan
Procurement Management
Enterprise/ Organization
4.5 Perform
Integrated Change Control
4.4 Monitor and
Control Project Work
4.3 Direct and
Manage Project Work
4.2 Develop Project Management
Plan
Figure 4-11. Perform Integrated Change Control Data Flow Diagram
96 ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
4 - P R O J E C T I N T E G R AT I O N M A N A G E M E N T
The Perform Integrated Change Control process is conducted from project inception through completion and is
the ultimate responsibility of the project manager. The project management plan, the project scope statement, and
other deliverables are maintained by carefully and continuously managing changes, either by rejecting changes
or by approving changes, thereby assuring that only approved changes are incorporated into a revised baseline.
Changes may be requested by any stakeholder involved with the project. Although changes may be initiated
verbally, they should be recorded in written form and entered into the change management and/or configuration
management system. Change requests are subject to the process specified in the change control and configuration
control systems. Those change request processes may require information on estimated time impacts and estimated
cost impacts.
Every documented change request needs to be either approved or rejected by a responsible individual, usually
the project sponsor or project manager. The responsible individual will be identified in the project management plan
or by organizational procedures. When required, the Perform Integrated Change Control process includes a change
control board (CCB), which is a formally chartered group responsible for reviewing, evaluating, approving, delaying,
or rejecting changes to the project, and for recording and communicating such decisions. Approved change
requests can require new or revised cost estimates, activity sequences, schedule dates, resource requirements,
and analysis of risk response alternatives. These changes can require adjustments to the project management
plan and other project documents. The applied level of change control is dependent upon the application area,
complexity of the specific project, contract requirements, and the context and environment in which the project is
performed. Customer or sponsor approval may be required for certain change requests after CCB approval, unless
they are part of the CCB.
Configuration control is focused on the specification of both the deliverables and the processes; while change
control is focused on identifying, documenting, and approving or rejecting changes to the project documents,
deliverables, or baselines.
Some of the configuration management activities included in the Perform Integrated Change Control process
are as follows:
Configuration identification. Identification and selection of a configuration item to provide the basis for
which the product configuration is defined and verified, products and documents are labeled, changes
are managed, and accountability is maintained.
97©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
4 - P R O J E C T I N T E G R AT I O N M A N A G E M E N T
4
Configuration status accounting. Information is recorded and reported as to when appropriate
data about the configuration item should be provided. This information includes a listing of approved
configuration identification, status of proposed changes to the configuration, and the implementation
status of approved changes.
Configuration verification and audit. Configuration verification and configuration audits ensure the
composition of a project’s configuration items is correct and that corresponding changes are registered,
assessed, approved, tracked, and correctly implemented. This ensures the functional requirements
defined in the configuration documentation have been met.
4.5.1 Perform Integrated Change Control: Inputs
4.5.1.1 Project Management Plan
Described in Section 4.2.3.1. Elements of the project management plan that may be used include, but are not
limited to:
Scope management plan, which contains the procedures for scope changes;
Scope baseline, which provides product definition; and
Change management plan, which provides the direction for managing the change control process and
documents the formal change control board (CCB).
Changes are documented and updated within the project management plan as part of the change and
configuration management processes.
4.5.1.2 Work Performance Reports
Described in Section 4.4.3.2. Work performance reports of particular interest to the Perform Integrated Change
Control process include resource availability, schedule and cost data, and earned value management (EVM) reports,
burnup or burndown charts.
4.5.1.3 Change Requests
All of the Monitoring and Controlling processes and many of the Executing processes produce change requests
as an output. Change requests may include corrective action, preventive action, and defect repairs. However,
corrective and preventive actions do not normally affect the project baselines—only the performance against the
baselines.
98 ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
4 - P R O J E C T I N T E G R AT I O N M A N A G E M E N T
4.5.1.4 Enterprise Environmental Factors
Described in Section 2.1.5. The following enterprise environmental factor can influence the Perform Integrated
Change Control process: project management information system. The project management information system
may include the scheduling software tool, a configuration management system, an information collection and
distribution system, or web interfaces to other online automated systems.
4.5.1.5 Organizational Process Assets
Described in Section 2.1.4. The organizational process assets that can influence the Perform Integrated Change
Control process include, but are not limited to:
Change control procedures, including the steps by which official organization standards, policies, plans,
and other project documents will be modified, and how any changes will be approved, validated, and
implemented;
Procedures for approving and issuing change authorizations;
Process measurement database used to collect and make available measurement data on processes
and products;
Project documents (e.g., scope, cost, and schedule baselines, project calendars, project schedule network
diagrams, risk registers, planned response actions, and defined risk impact); and
Configuration management knowledge base containing the versions and baselines of all official
organization standards, policies, procedures, and any project documents.
4.5.2 Perform Integrated Change Control: Tools and Techniques
4.5.2.1 Expert Judgment
In addition to the project management team’s expert judgment, stakeholders may be asked to provide their
expertise and may be asked to sit on the change control board (CCB). Such judgment and expertise are applied to
any technical and management details during this process and may be provided by various sources, for example:
99©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
4 - P R O J E C T I N T E G R AT I O N M A N A G E M E N T
4
Consultants,
Stakeholders, including customers or sponsors,
Professional and technical associations,
Industry groups,
Subject matter experts (SMEs), and
Project management office (PMO).
4.5.2.2 Meetings
In this case, these meetings are usually referred to as change control meetings. When needed for the project, a
change control board (CCB) is responsible for meeting and reviewing the change requests and approving, rejecting,
or other disposition of those changes. The CCB may also review configuration management activities. The roles and
responsibilities of these boards are clearly defined and agreed upon by appropriate stakeholders and documented
in the change management plan. CCB decisions are documented and communicated to the stakeholders for
information and follow-up actions.
4.5.2.3 Change Control Tools
In order to facilitate configuration and change management, manual or automated tools may be used. Tool
selection should be based on the needs of the project stakeholders including organizational and environmental
considerations and/or constraints.
Tools are used to manage the change requests and the resulting decisions. Additional considerations should
be made for communication to assist the CCB members in their duties as well as distribute the decisions to the
appropriate stakeholders.
4.5.3 Perform Integrated Change Control: Outputs
4.5.3.1 Approved Change Requests
Change requests are processed according to the change control system by the project manager, CCB, or by an
assigned team member. Approved change requests will be implemented through the Direct and Manage Project
Work process. The disposition of all change requests, approved or not, will be updated in the change log as part of
updates to the project documents.