WBS Outline

Work Breakdown Structure Outline
Project Initiation
1.1 Develop Project Charter
1.2 Define Scope
1.3 Define Requirements
1.4 Finalize Charter and Gain Approvals
1.5 Hold Review Meeting
1.6 Revise Project charter
1.7 Gain approvals
Planning
2.1 Preliminary project scope development
2.2 Project Team Determination
2.3 Project Team meeting
2.4 Develop project plan, schedule, and budget
2.5 Submit project plan
2.6 Project plan approval.
Execution
3.1 Project Team meeting
3.2 Assignment of Tasks
3.4 Area visits and tests
3.5 Design system
3.6 Procure the hardware and softwere needed
3.7 Testing phase
3.8 Install the live system
3.9 User Training
Control
4.1 Initiate risks management strategies
4.2 Project evaluation
4.3 Project Status updates
4.4 Risk identification
4.5 Constant update of project plan
Close out
5.1 Audit project
5.2 Document all the findings
5.3 Update files and all the relevant records
5.4 Gain formal acceptance
5.5 Archive all the files and documents related to the project

Assignment One

Activity Name WBS ID Name Precedent Task Start Date Finish Date # Days Duration Resource % Completion
Initiation 1.1 Develop project charter 29-Mar 30-Mar 1 100
1.2 Define Scope 1.1 30-Mar 30-Mar 0.5 100
1.3 Define Requirements 1.2 30-Mar 30-Mar 0.5 100
1.4 Gain Approvals 1.3 31-Mar 2-Apr 3 100
1.5 Hold Review Meeting 1.4 3-Apr 3-Apr 1 100
1.6 Revise Project charter 1.5 3-Apr 3-Apr 0.5 100
1.7 Gain approvals 1.6 3-Apr 4-Apr 1 80
Planning
2.1 Preliminary project scope development 1.6 5-Apr 6-Apr 1 0
2.2 Project Team Determination 2.1 6-Apr 12-Apr 7 0
2.3 Project Team meeting 2.2 14-Apr 14-Apr 0.5 0
2.4 Develop project plan, schedule, and budget 2.3 14-Apr 14-Apr 0.5 0
2.5 Submit project plan 2.4 14-Apr 14-Apr 0.5 0
2.6 Project plan approval. 2.5 14-Apr 16-Apr 2 0
Execution
3.1 Project Team meeting 2.6 18-Apr 18-Apr 0.5 Human assets 0
3.2 Assignment of Tasks 3.1 18-Apr 18-Apr 0.5 Team members 0
3.3 Area visits and tests 3.2 19-Apr 22-Apr 4 0
3.4 Design system 3.2 19-Apr 22-Apr 4 0
3.5 Procure the hardware and softwere needed 3.2 19-Apr 22-Apr 4 Finance 0
3.6 Testing phase 3.5 25-Apr 29-Apr 5 0
3.7 Install the live system 3.6 2-May 4-May 2 0
3.8 User Training 3.7 9-May 13-May 5 Relevant workers 0
Control
5.1 Initiate risk management strategies 2.6 18-Apr 20-Apr 2 0
5.2 Project evaluation 3.8 14-May 17-May 3 0
5.3 Project Status updates 2.6 18-Apr 20-May 32 0
5.4 Risk identification 2.6 18-Apr 20-Apr 2 0
5.5 Constant update of project plan
Close out
5.1 Audit project 3.8 14-May 16-May 2 0
5.2 Document all the findings 5.1 16-May 18-May 2 0
5.3 Update files and all the relevant records 5.2 18-May 19-May 1 0
5.4 Gain formal acceptance 5.3 19-May 20-May 1 Management 0
5.5 Archive all the files and documents 5.4 19-May 20-May 1 0