Gantt chart

profileswf7
gantt_chart-assignemt-1_2.doc

Given the information provided below and the Gantt chart layout provided, you are to construct a Gantt chart, with overlaps as specified.

Activity Letter

Activity Description

Predecessor

Duration (months)

Overlap (months)

A

Train project team

None

1

None

B

Project paperwork and systems design

A

2 ½

¼

C

Modify purchased package

B

2

1

D

Manual systems flow

B

1 ½

1

E

Modify in-house procedures

B

4

1

F

Test and implement modifications to purchased package

C

1 ½

1/8

G

Test and implement manual

D

¾

1/8

H

Test and implement modifications to in-house procedures

E

1

1/8

GANTT CHART EXERCISE

Schedule

Date Assigned: 12/7/2015

Project No. 1016-1021 Project Title: Customer Index System

Assigned to: C.I. (Project Team)

Description

December

January

February

March

April

May

June

July

A. Train Project Team

B. Project Management Paperwork

C. Modify Purchased Package

D. Manual systems Flow

E. Modify In-House Procedures

F. Test and Implement Modifications to Purchased Package

G. Test and Implement Manual Systems Flow

H. Test and Implement Modifications to In-House Procedrues