Gantt chart
Given the information provided below and the Gantt chart layout provided, you are to construct a Gantt chart, with overlaps as specified.
Activity Letter |
Activity Description |
Predecessor |
Duration (months) |
Overlap (months) |
|
A |
Train project team |
None |
1 |
None |
|
B |
Project paperwork and systems design |
A |
2 ½ |
¼ |
|
C |
Modify purchased package |
B |
2 |
1 |
|
D |
Manual systems flow |
B |
1 ½ |
1 |
|
E |
Modify in-house procedures |
B |
4 |
1 |
|
F |
Test and implement modifications to purchased package |
C |
1 ½ |
1/8 |
|
G |
Test and implement manual |
D |
¾ |
1/8 |
|
H |
Test and implement modifications to in-house procedures |
E |
1 |
1/8 |
GANTT CHART EXERCISE
Schedule
Date Assigned: 12/7/2015
Project No. 1016-1021 Project Title: Customer Index System
Assigned to: C.I. (Project Team)
|
Description |
|
December |
January |
February |
March |
April |
May |
June |
July |
||||||||||||||||||||||||
|
A. Train Project Team |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
B. Project Management Paperwork |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
C. Modify Purchased Package |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
D. Manual systems Flow |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
E. Modify In-House Procedures |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
F. Test and Implement Modifications to Purchased Package |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
G. Test and Implement Manual Systems Flow |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
H. Test and Implement Modifications to In-House Procedrues |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|