impregillo project- engneering economics and mangment

profileswf7
ce_3361_project_iii_impregillo.doc

-1-

CE 3361 NAME:____________________

PROJECT III DATE:_____________________

SHOW ALL WORK AND CALCULATIONS

DUE: 19 APRIL 2016

GROUP B: IMPREGILLO COMPANY

IN ORDER TO COMPARE THE BIDS BY CATERPILLER AND IMPREGILLO, KIEWIT HAS ASKED ITS STAFF TO CARRYOUT AN ECONOMIC STUDY BASED IN PRESENT WORTH, ANNUAL WORTH AND PAYBACK PERIOD ANALYSES. IT IS YOUR RESPONSIBILITY TO PERFORM THE ECONOMIC ANALYSIS ONLY ON YOUR ASSIGNED ALTERNATIVE: IN THIS CASE IMPREGILLO. USE THE TABLES PROVIDED IN THIS ASSIGNMENT. NO OTHER SUBMISSIONS WILL BE ACCEPTED. THE FOLLOWING COST/REVENUE SCHEDULE HAS BEEN DEVELOPED FOR THE IMPREGILLO OPTION BY OUR ACCOUNTANT:

IMPERGILLO

INITIAL $600,000

COST

DELIVERY $15,000

COST

OPERATION/ $3000/YR

MAINTANENCE

UPGRADE/ $1000 EVERY 2TH

PARTS YEAR

INSURANCE $600/YR

FIRST YEAR INCOME $120000/YR

INCOME INCREASE $20,000/YR

SALVAGE $120000

LIFE 4 YR

INTEREST

COST 2%/QUARTER CP MONTHLY

REVENUE 3%/YR

-2-

CE 3361 NAME:____________________

PROJECT III DATE:_____________________

SHOW ALL WORK AND CALCULATIONS

1. PERFORM A PRESENT WORTH ECONOMIC ANALYSIS ON IMPREGILLO OPTION: FILL IN TABLES NEATLY

IMPREGILLO OPTION

PRESENT WORTH: PW i = 8.300%/YR

COST n = 0 TO 12 YEARS

ELEMENT

TIME

P/F

P/A

AMOUNT

SOURCE

-$600,000

1.0000

-$600.000

Eq.

-$ 15,000

0

-$600,000

-$ 15,000

0.72692

-$ 10,904

Eq.

-$600,000

-$ 15,000

-$ 1,000

-$ 1,000

-

-$ 727

-$ 1,000

6

-$ 1,000

0.52841

-$ 1,000

-$ 1,000

-

-$ 3,000

-

-$ 600

12

-

TOTAL

TIME

(1 + i)n

1/(1 + i)n

(1 + i)n - 1

i ∙ (1 + i)n

P/F

P/A

2

4

6

8

10

12

-3-

CE 3361 NAME:____________________

PROJECT III DATE:_____________________

SHOW ALL WORK AND CALCULATIONS

IMPREGILLO OPTION

PRESENT WORTH: PW i = 3%/YR

n = 4 TO 12 YEARS

REVENUE

ELEMENT

TIME

P/A

P/G

P/F

AMOUNT

SOURCE

$120,000

12

-

$1,194,480

TABLE 8

$ 20,000

51.2482

$120,000

-

0.8885

$120,000

8

$120,000

TOTAL

DETERMINE NET PRESENT WORTH:

REVENUE:______________

COST: _______________

NET PW:_________________

-4-

CE 3361 NAME:____________________

PROJECT III DATE:_____________________

SHOW ALL WORK AND CALCULATIONS

2. PERFORM AN ANNUALWORTH ECONOMIC ANALYSIS ON THE IMPREGILLO OPTION: FILL IN TABLES NEATLY

IMPREGILLO OPTION

ANNUAL WORTH: AW i = 8.300%/YR

COST n = 12 YEARS

ELEMENT

N

PW

A/P

AMOUNT

SOURCE

-$600,000

12

-$600,000

-$102,870

Eq.

-$ 15,000

-$600,000

0.17145

-$ 15,000

12

-$ 10,904

Eq.

-$600,000

-$ 15,000

-$ 1,000

-$ 1,000

-$ 125

-$ 1,000

0.17145

-$ 1,000

-$ 1,000

-$ 1,000

-$ 3,000

-$ 3000

-$ 600

12

TOTAL

TIME

(1 + i)n

(1 + i)n – 1

i ∙ (1 + i)n

A/P

12

-5-

CE 3361 NAME:____________________

PROJECT III DATE:_____________________

SHOW ALL WORK AND CALCULATIONS

IMPREGILLO OPTION

ANNUAL WORTH: AW i = 3%/YR

n = 12 YEARS

REVENUE

ELEMENT

n

PW

A/P

AMOUNT

SOURCE

$120,000

12

$120,000

$ 20,000

TABLE 8

$120,000

0.10046

$120,000

12

$120,000

TOTAL

DETERMINE NET ANNUAL WORTH:

REVENUE:___________

COST:_______________

NET:_________________

-6-

CE 3361 NAME:____________________

PROJECT III DATE:_____________________

SHOW ALL WORK AND CALCULATIONS

3. GIVEN THE FOLLOWING ANNUAL WORTH FOR ONE LIFE CYCLE. DETERMINE THE PAYBACK PERIOD OF THE IMPREGILLO OPTION FOR A 0% RATE OF RETURN:

IMPREGILLO OPTION

ANNUAL WORTH: AW i = 8.300%/YR

COST n = 4 YEARS

ELEMENT

n

AMOUNT

SOURCE

-$600,000

4

-$182,364

Eq.

-$ 15,000

4

-$ 4,559

Eq.

-$ 1,000

4

-$ 259

Eq.

-$ 1,000

4

-$ 221

Eq.

-$ 3,000

4

-$ 3,000

Eq.

-$ 600

4

-$ 600

Eq.

REVENUE i = 3%/YR

n = 4 YEARS

ELEMENT

n

AMOUNT

SOURCE

$120,000

4

$120,000

TABLE 8

$ 20,000

4

$ 29,261

TABLE 8

$120,000

4

$ 28,684

TABLE 8

-7-

CE 3361 NAME:____________________

PROJECT III

SHOW ALL WORK AND CALCULATIONS

PAYBACK PERIOD CALCULATION: nP

SHOW CALCULATIONS

COST REVENUE

AW NCF

AWREVENUE = ___________

AWCOST = ___________

AW NET CASH FLOW = ___________

nP = ________________

DOES THE IMPREGILLO OPTION PAYBACK PERIOD EXCEED WITHIN

THE USEFUL LIFE OF DRILL: CHOOSE ALL CORRECT ANSWERS

YES NO

ONLY AFTER NOT IMPORTANT

SALVAGE

NAME _____________________________________

SIGNATURE:_______________________________

BY SIGNING THIS PAGE, I CERTIFY THAT I HAVE NOT GIVEN

OR RECEIVED HELP FROM ANY OTHER STUDENT

-8-

CE 3361 NAME:____________________

PROJECT III

THE FOLLOWING STUDENTS ARE ASSIGNED THE IMPREGILLO ALTERNATIVE

IMPREGILLO ALTERNATIVE

Alajmi, Faraj

Alajmi, Nasher

Alanazi, Bassam

Aldossary, Husina

Alenezi, Abdulwahab

Alfakeeh, Ahmed

Alhajeri, Badar

Alharbi, Suod

Aljabal, Khaled

Almakrami, Ali

Almelihi, Abdulhadi

Almershad, Abdalla

Almutairi, Abdullah

Almutiri, Ahmad

Alotaibi, Abdulrahman

Alotaibi, Mohammad

Alrashed, Abdullah

Alsuhaibani, Eyas

Alzaid, Abdulaziz

Alzakeri, Ibrahim

Broadway, Jason

Erb, Conner

Haider, Fajer

Prasai, Arjun

Shrestha, Kshitiz

Suhluli, Abdulrahman

White, Chris

Walrath, Clinton