Time Phased Budget
Table 1: Task and Resources Schedule
|
Task Name |
Duration |
Start |
Finish |
Predecessors |
Resource Names |
Responsibility |
Actual Cost |
|
Commencement |
2 days |
Fri 2/12/16 |
Mon 2/15/16 |
|
Labor |
Architect, supervisor, and volunteers |
$200,000.00 |
|
Requirements review |
6 days |
Tue 2/16/16 |
Tue 2/23/16 |
1 |
Labor |
The team |
$0.00 |
|
Project Design Review |
45 days |
Tue 2/23/16 |
Mon 4/25/16 |
|
Labor and Material |
Supervisor |
$0.00 |
|
Project Testing |
31 days |
Tue 4/26/16 |
Tue 6/7/16 |
9 |
Labor and Material |
Supervisor and Volunteers |
$0.00 |
|
Project End |
22 days |
Wed 6/8/16 |
Thu 7/7/16 |
22 |
Labor and Material |
Team |
$0.00 |
Figure 1: Time Phased Budget
Actual Cost Architect, supervisor, and volunteers The team Supervisor Spervisor and Volunteers Team Labor Labor Labor and Material Labor and Material Labor and Material 1 9 22 Mon 2/15/16 Tue 2/23/16 Mon 4/25/16 Tue 6/7/16 Thu 7/7/16 Fri 2/12/16 Tue 2/16/16 Tue 2/23/16 Tue 4/26/16 Wed 6/8/16 2 days 6 days 45 days 31 days 22 days Commencement Requirements review Project Design Review Project Testing Project End 200000.0 0.0 0.0 0.0 0.0
Time in Months
Total Cost