notebook for a project
Name: Ahmed Alqahtani
Date :15-Feb-2016
Construction Houses for Poor People
Name of Project: Construction Houses for Poor People in Denver
Sponsor: Donor funding from well-wishers
Executive Summary
Project Scope Statement
This project is to build quality, custom houses for the poor beginning the month of February 2016. Its completion will see the provision of at least 30 decent houses for the poor in Denver. The houses will be constructed at a cost not exceeding $200,000. They will be constructed and completed over a period of 5 months with the help of an architect, beneficiary families and the community at large.
Product Description
This project will be fruitful if constructed within budget. Also, its completion will ensure the provision of 30 decent homes for the poor in Denver.
Milestones
|
Milestone Number |
Milestone |
Status (Mandatory/Optional) |
End Date |
Confirmation |
|
1 |
Commencement |
Mandatory |
13/02/16 |
Sponsor Approval |
|
2 |
Requirements review |
Mandatory |
22/02/16 |
Sponsor Approval |
|
3 |
Project design review |
Mandatory |
25/04/16 |
Sponsor Approval |
|
4 |
Project testing |
Mandatory |
07/06/16 |
Sponsor Approval |
|
5 |
Project end |
Mandatory |
06/07/16 |
Sponsor Approval |
Budget
|
Expense |
Cost |
|
Labour |
$20,000 |
|
Materials |
$180,000 |
|
Total |
$200,00 |
Required Personnel
The following personnel will be required to complete this building project:
1. An architect to provide a design of the house.
1. A supervisor to help guide construction activities.
1. Volunteers from the families and the community who will benefit from the project.