Identify Project Stakeholders and Major Risks.
Project Charter
Project Charter
V 2.0
Project Charter
|
Project Name |
Jumping Bean Coffee Shop |
Project Number |
1 |
|
Project Team |
C |
Prioritization |
High |
|
Owner(s) |
Amy Fast, John Ferrugiaro, Allison Fox, Heather French, Kristen Gale
|
Start Date: |
3/7/2016 |
|
Scheduled Completion Date: |
4/23/2016 |
Mission/ Purpose |
At the Jumping Bean we strive to bring you top quality coffee to
inspire you with every sip. When our doors open every morning we
want you to feel invited and at home in a way you can only find with a
locally owned and operated coffee house. With a variety of brewed
coffee, espresso beverages, and tea you are sure to find comfort in
knowing we are right around the corner. |
|||||
|
|
||||||
|
Project Description and Project Product |
The Jumping Bean Coffee Shoppe will offer delicious blends of light, medium and full bodied coffees and teas to the surrounding community. Nestled in a busy shopping mall, customers will be able to enjoy coffee, espresso, lattes and teas while they enjoy their shopping experience. This is much needed in this populated area because there are limited shops that offer a great cup of coffee. Sure you have your typical convenience store coffee but the Jumping Bean Coffee Shoppe will offer much more than that. Customers will be able to come and enjoy the ambiance while sipping on coffee made from finest coffee beans. In order to complete the work for this project we will need to obtain a building available for lease, equipment, such as cash register, coffee and espresso machines, hire contractors to design the building to suit our needs, purchase tables and chairs, cups, mugs, and paper goods. High level deliverables that will be generated from this project would be the building lease, equipment, coffee and espresso machines, contractor costs, and tables and chairs.
|
|||||
|
|
||||||
Objectives |
The objective of this project is to successfully launch the opening of Jumping Bean Coffee Shop in Tinton Falls, NJ on April 23, 2016. The project team has identified the following goals needed to achieve its objective.
1. Successful completion of the business plan including the mission statement, budget, marketing plan, etc. prior to sourcing financial needs. 1. Acquisition of minimal equipment required for startup prior to the start of employee training. 1. Contractual agreements for wholesale supply of coffee and other supplies prior to the start of employee training. 1. Securement of competitive financing needed for capital expenditures beyond owner contributions and prior to milestones requiring said capital. 1. Completion of staffing and training 2 weeks prior to launch.
|
|||||
|
|
||||||
|
Business Need |
The Jumping Bean will be located within Tinton Falls Centre Plaza in
Tinton Falls, NJ and will be the only specialty coffee shop in the area.
It will provide tired shoppers with a place to relax and enjoy gourmet
coffee and snacks. The Jumping Bean will provide an environment
that feels like home and offer a variety of brewed coffee, expresso
beverages and tea. There is a target market at this location due to
the high volume of shoppers, neighboring condominium complexes
and a lack of competitors who provide quality coffee. Tinton Falls is
at the heart of Monmouth County, one of New Jersey’s most affluent
neighborhoods and as such the Jumping Bean will be able to
capitalize on the need for higher priced gourmet coffee. |
|||||
|
|
||||||
|
Milestones |
1. Find a commercial realtor by 3/11/2016
1. Search available locations and make decision by 3/28/2016
1. Lease space by 3/25/2016
1. Get estimates from contractors by 3/26/2016
1. Make decision on contractor by 3/27/2016
1. Search for company that rents restaurant equipment by 3/28/2016
1. Order tables and chairs by 3/30/2016
1. Renovations need to be done by 4/8/2016
1. Have equipment delivered by 4/11/2016
1. Open for business by 4/23/2016
|
|||||
|
Budget |
|
|||||
|
|
Estimated Labor |
20,000 |
||||
|
|
Estimated Materials |
15,000 |
||||
|
|
Estimated Contractors |
15,000 |
||||
|
|
Estimated Equipment and Facilities |
17,000 |
||||
|
|
Estimated Travel |
5,000 |
||||
|
|
Total Estimated Cost |
72,000 |
||||
|
|
||||||
|
User Acceptance Criteria |
1. City and State licenses’ obtained prior to open. 2. Leased building must complete an inspection to ensure that the building is safe for customers 3. All equipment should be tested in the space to ensure proper functionality 4. A health inspection should be performed prior to open to ensure a safe, clean and safe place for customers to enjoy our coffee.
|
|||||
|
|
||||||
|
Major Risks |
1. The ideal location is beyond the project’s budget resulting in cost over-runs. 2. The actual space we leased needs to be remodeled to suit our needs. 4. Furniture and fixtures needed for the grand opening become backordered or unavailable resulting in increased costs necessary to secure replacements prior to opening day. 5. There is only one company that leases restaurant equipment and all of their espresso machines are currently being rented forcing the business to purchase equipment, resulting in cost overruns. 6. Excessively exceeding the budget half way through the project. 7. Licenses and permits required by the state or the municipality are not obtained as planned resulting in missed deadlines.
|
|||||
|
|
||||||
|
KEY STAKEHOLDERS
Internal Stakeholders: All team members are also owners of Jumping Bean and as such are the primary internal stakeholders. Barista employees of Jumping Bean are also internal stake holders. The company has not sourced talent for any management positions as they positions are filled by the 5 owners.
External Stakeholders: The team has identified the following external stakeholders:
1. Customers 2. The Tinton Falls Community 3. Competitors (a) Wawa on Shafto Road (b) Dunkin Donuts on Asbury Ave (c) The Local Deli on Asbury Ave 4. All suppliers, contractors, and other vendors. 5. The State of New Jersey
|
||||||
|
Project Manager Authority Level |
Amy Fast will serve as project manager for Jumping Bean. Amy will have full authority to determine, manage and change scheduling, contractors, vendors, staffing and product resources as long as those changes do not exceed 10% of previously budgeted costs. Changes exceeding 10% will require majority owner approval.
|
|||||
|
Project Core Team |
Amy Fast, Allison Fox, Heather French, Kristen Gale, John Ferrugiaro
|
|||||
|
Subject Matter Experts (SMEs) |
The company will need to source employees, contractors, and/or vendors with the following special expertise.
1. Experienced contractor specializing in retail space renovation. 2. Contactor or employee with marketing expertise 3. Accountant 4. Commercial Real Estate Agent 5. Registered Agent Service 6. At least one experienced Barista 7. Business Lawyer 8. IT Professional specializing in retail networks
|
|||||
|
APPROVALS |
||||||
Type Name |
Signature |
Date |
||||
|
Project Manager Approval
|
Amy Fast
|
March 11, 2016
|
||||
|
Customer/Sponsor Approval
|
Team C
|
March 11, 2016
|