need it in 3 hours
Exam 2 Sample Problems 1. Using an inverted buret for pump calibration, the industrial hygienist timed the movement of a
soap bubble from 200 to 0 mL. The following are the obtained results:
Time 1: 7.45 sec Time 2: 7.39 sec Time 3: 7.49 sec Time 4: 7.41 sec Time 5: 7.44 sec Calculate the flow rate (in LPM) of the sampling train.
2. A diffuser opening measures 24 x 12 inches and has an anemometer reading of 25 fpm. Calculate the volumetric rate of airflow, Q (in cfm).
3. The indoor CO2 concentrations in a work space during the workday were measured as follows.
The outdoor CO2 concentration is 500 ppm. Nine (9) employees occupy the space.
Time of Day Indoor CO2 Concentration (ppm) 8 AM 330 1 PM 970 8 PM 540
a) Calculate the volume of outside air per person (cfm/person) flowing into the work space.
b) Is the resulting volume of outside air acceptable based on the minimum flow of 20
cfm/person as recommended in the ASHRAE Standard? 4. Pitot traverse measurements in a duct resulted to an average velocity pressure of 0.05 inches of
water. a) Calculate the duct velocity.
b) The LEV system should be operating at a minimum velocity of 800 fpm. Is the measured
duct velocity acceptable? 5. Calculate the required dilution flow rate if 20 pounds of toluene are evaporated from a process
during an 4-hour work shift. The acceptable airborne concentration of toluene is set at 10 ppm. Assume that Kmix=1.5, d = 1 and MW = 92.1. (4 points)