Company Name: Trillo Apparel Company

Company type: Apparel design and production

District 4 Production Warehouse Move Project Details

The VP of Operations estimates the production and shipping warehouse move for District 4 will provide room required to generate the additional $1 million/year product revenues to meet the current demand due to the expanded production capacity. Daily production generates $50,000 revenue so a week of downtime will cost $250,000 in lost revenues.

The move must be completed in 4 months.

Mileage between the old and new facilities is 10 miles.

Bids have been received from contractors to build out the new office space and production floor and have signed contracts for work as follows:

Pack, move and unpack production equipment

City Equipment Movers

$150,000

n/a

5 Days

Move non-production equipment and materials

Express Moving Company

$125,000

n/a

5 Days

Framing

East Side Framing & Drywall

$121,000

$125,000

15 Days

Electrical

Sparks Electrical

$18,000

$12,000

10 Days

Plumbing

Waterworks Plumbing

$15,000

$13,000

10 Days

Drywall

East Side Framing & Drywall

$121,000

$18,000

15 Days

Finish Work

Woodcraft Carpentry

$115,000

$15,000

15 Days

Build work benches for production floor

Student Workers Carpentry

$112,000

$110,000

15 Days