Factors affecting the schedule

The permits were to take 2 weeks but now they are taking 3 weeks

Drywall and framing contractors are running late on other projects and they can only release half of their crew, which doubles their schedule

What is needed:

Building the extra time into the schedule by doubling the installation work timelines for both the framing and drywall

Updating project plan with the new 3 week timeline for obtaining permits

The permits were to take 2 weeks but now they are taking 3 weeks

Drywall and framing contractors are running late on other projects and they can only release half of their crew, which doubles their schedule

What is needed

Building the extra time into the schedule by doubling the installation work timelines for both the framing and drywall

Update project plan with the new 3-week timeline for obtaining permits

2

Course of Actions to be considered

Adding a new contractor at an extra cost of $200,000 and negotiating an extra one week for the permits to be obtained from project sponsor

Building the extra time into the schedule by doubling the installation work timelines for both the framing and drywall, which will cater for the one week needed for the permits

The two course of action to be considered include: Adding a new contractor at an extra cost of $200, 000 and negotiating an extra one week for the permits to be obtained from the project sponsor

Building the extra time into the schedule by doubling the installation work timelines for both the framing and drywall, which will cater for the one week needed for the permits

3

Option 1: Hiring a new contractor & negotiating a one week extension

In considering hiring a new contractor, its important to consider the tradeoffs between time and cost

The total cost for hiring a new contractor and negotiating a one week extention for the permits will be…….

$200,000+250,000 ( (for the lost revenue for the one week) = $450,000

In considering hiring a new contractor, its important to consider the tradeoffs between time and cost

The total cost for hiring a new contractor and negotiating a one week extension for the permits will be:

$200,000+250,000 (for the lost revenue for the one week)= 450,000 extra the budget

4

Option 2: Increasing time schedule for the contractors

If the time schedule is increased for framing and drywall, there would be no extra cost in the budget

However, the company will have revenue lost which will be…..

$250,000*3=$750,000

If the time schedule is increased for framing and drywall, there would be no extra cost in the budget

However, the company will have revenue lost which will be:

$250,000*3=$750,000

5

Recommendation

Adding a new contractor at an extra cost of $200,000 and negotiating an extra one week for the permits to be obtained from the project sponsor will lead to an extra cost of $450,000

On the other hand, creating the extra time into the schedule by doubling the installation work timelines for both the framing and drywall, which will suffice for the one week needed for the permits will make the company lose revenue in the amount of $750,000

It is therefore recommended to add a new contractor and negotiate with the project sponsor about a one week extension for the project

Adding a new contractor at an extra cost of $200, 000 and negotiating an extra one week for the permits to be obtained from the project sponsor will lead to an extra cost of $450, 000

On the other hand, creating the extra time into the schedule by doubling the installation work timelines for both the framing and drywall, which will cater for the one week needed for the permits will make the company lose revenue worth $750,000.

It is therefore recommended to add a new contractor and negotiate with the project sponsor about a one week extension for the project.

6

References

Berkun, S. (2008). Making things happen: Mastering project management. Sebastopol, Calif: O’Reilly Media

Larson, Erik, Gray, C. (10/2013). Project Management, 6th Edition. [VitalSource Bookshelf Online]. Retrieved from https://digitalbookshelf.argosy.edu/#/books/1259341534/

Schmidt, T. (2009). Strategic project management made simple: practical tools for leaders & teams. Hoboken, N.J. John Wiley & Sons.