Johnson House Tasks and Predecessors
Task Name Duration Predecessors
NTP 1 day
Mobilize/Layout 2 days 1
Footings 3 days 2
UG MEP 1 day 3SS
FND 5 days 3
Backfill 1 day 7
FND drain 1 day 9
Gravel & VP crawl space 2 days 5
FND Waterproof 1 day 5FS+3 days
Frame 14 days
Girder & Sills 1 day 8
Floor 2 days 11
Walls 5 days 12
Roof trusses 1 day 13
Roof sheathing/trim 2 days 14
Pick-up framing 3 days 15
Garage to subgrade 1 day 5
Dry-in 1 day 15
Roofing 2 days 18,16
Rough Plumbing 4 days 15
Rough Electrical 5 days 18
Rough Mechanical 3 days 18
Insulation 2 days 20,21,22,16
Inspections 1 day 23
Drywall 7 days 24
Windows 1 day 13SS
Siding 2 days 16,6
Exterior doors 1 day 13
Brick 3 days 16
Stucco 7 days 29,52
Gutters 1 day 19
Paint Int. 3 days 25
Carpet 2 days 32
Cabinetry 3 days 36
Tile 3 days 32
Laminate/VCT 1 day 32
Finish Electrical 5 days 32
Finish Plumbing 4 days 35,34
Finish Mechanical 3 days 32
Interior doors 1 day 33,35
Millwork 2 days 33,35,34
Garage slab 4 days 8
Garage door 1 day 42,25
Landscape 5 days 29,45
Pour driveway/walks 5 days 46
Site utilities 4 days 20,21
Attic insulation 1 day 25
Accessories/trim 2 days 34
Final inspection 1 day 48,47,37,38,39,40
Final clean 2 days 49SS
Paint exteiror 2 days 27,43
Pour porch 3 days 9