| Johnson House Tasks and Predecessors | ||
| Task Name | Duration | Predecessors |
| NTP | 1 day | |
| Mobilize/Layout | 2 days | 1 |
| Footings | 3 days | 2 |
| UG MEP | 1 day | 3SS |
| FND | 5 days | 3 |
| Backfill | 1 day | 7 |
| FND drain | 1 day | 9 |
| Gravel & VP crawl space | 2 days | 5 |
| FND Waterproof | 1 day | 5FS+3 days |
| Frame | 14 days | |
| Girder & Sills | 1 day | 8 |
| Floor | 2 days | 11 |
| Walls | 5 days | 12 |
| Roof trusses | 1 day | 13 |
| Roof sheathing/trim | 2 days | 14 |
| Pick-up framing | 3 days | 15 |
| Garage to subgrade | 1 day | 5 |
| Dry-in | 1 day | 15 |
| Roofing | 2 days | 18,16 |
| Rough Plumbing | 4 days | 15 |
| Rough Electrical | 5 days | 18 |
| Rough Mechanical | 3 days | 18 |
| Insulation | 2 days | 20,21,22,16 |
| Inspections | 1 day | 23 |
| Drywall | 7 days | 24 |
| Windows | 1 day | 13SS |
| Siding | 2 days | 16,6 |
| Exterior doors | 1 day | 13 |
| Brick | 3 days | 16 |
| Stucco | 7 days | 29,52 |
| Gutters | 1 day | 19 |
| Paint Int. | 3 days | 25 |
| Carpet | 2 days | 32 |
| Cabinetry | 3 days | 36 |
| Tile | 3 days | 32 |
| Laminate/VCT | 1 day | 32 |
| Finish Electrical | 5 days | 32 |
| Finish Plumbing | 4 days | 35,34 |
| Finish Mechanical | 3 days | 32 |
| Interior doors | 1 day | 33,35 |
| Millwork | 2 days | 33,35,34 |
| Garage slab | 4 days | 8 |
| Garage door | 1 day | 42,25 |
| Landscape | 5 days | 29,45 |
| Pour driveway/walks | 5 days | 46 |
| Site utilities | 4 days | 20,21 |
| Attic insulation | 1 day | 25 |
| Accessories/trim | 2 days | 34 |
| Final inspection | 1 day | 48,47,37,38,39,40 |
| Final clean | 2 days | 49SS |
| Paint exteiror | 2 days | 27,43 |
| Pour porch | 3 days | 9 |