Sheet1

Task Duration (days) Start Date End Date
Surveying
Parking Area 3 8/15/16 8/18/16
Signage 3 8/19/16 8/22/16
Striping 5 8/23/16 8/28/16
Parking Use Survey/Study 7 8/29/16 9/5/16
Design 0
Existing Conditions 14 9/5/16 9/19/16
Parking 14 9/19/16 10/3/16
Signage 7 10/3/16 10/10/16
Striping 7 10/3/16 10/10/16
Markings 7 10/3/16 10/10/16
50 % Submittal 39 9/5/16 10/14/16
Revisions 0
Design 32 10/17/16 11/18/16
Proposal 21 11/18/16 12/9/16
Presentation 21 11/18/16 12/9/16
Website 4 12/5/16 12/9/16
100% Submittal
All final deliverables 56 10/14/16 12/9/16