| | Task | Duration (days) | Start Date | End Date |
| | Surveying |
| | Parking Area | 3 | 8/15/16 | 8/18/16 |
| | Signage | 3 | 8/19/16 | 8/22/16 |
| | Striping | 5 | 8/23/16 | 8/28/16 |
| | Parking Use Survey/Study | 7 | 8/29/16 | 9/5/16 |
| | Design | 0 |
| | Existing Conditions | 14 | 9/5/16 | 9/19/16 |
| | Parking | 14 | 9/19/16 | 10/3/16 |
| | Signage | 7 | 10/3/16 | 10/10/16 |
| | Striping | 7 | 10/3/16 | 10/10/16 |
| | Markings | 7 | 10/3/16 | 10/10/16 |
| | 50 % Submittal | 39 | 9/5/16 | 10/14/16 |
| | Revisions | 0 |
| | Design | 32 | 10/17/16 | 11/18/16 |
| | Proposal | 21 | 11/18/16 | 12/9/16 |
| | Presentation | 21 | 11/18/16 | 12/9/16 |
| | Website | 4 | 12/5/16 | 12/9/16 |
| | 100% Submittal |
| | All final deliverables | 56 | 10/14/16 | 12/9/16 |