Project management .A

profileschoolanswers
project_management.template.docx

Table of contents

1. Project Charter

2. Team Charter

3. WSB

4. Project Integration

5. Risk

6. Risk Management plan

7. Budget

8. Time

9. Procurement

10. Quality

11. Communication

12. Stakeholder

1.Project Charter: Project Purpose and Vision

To open a new retail location for Lellow’s Toys which will allow the company to expand sales and business into a new area of town. The company will sell educational toys and games to people of all ages and genders, disabilities, and conditions. It will allow children and people to grow and develop better skills.

Size of the retail space: 2,500 square feet

Budget: $200,000 for everything, including merchandise and signage

Business Objectives and Success Criteria

To open a new business location in 323 Applebee Road, Athens, GA 30601.

Date of opening: Saturday May 21st, 2016.

It will open right before summer to start with a summer “pool party!” It is expected to have an extreme turnout and good amount of sales to start. All employees and merchandise will be set up and trained before the grand opening.

· Open on time, measured by actual date VS when the store actually opens

· Have staff trained and ready, measured by customer questionnaires and experience within the store on whether the staff was able to answer their questions and help them with their concerns.

· Ensure a good customer sign up for rewards, measure by how many followers received on social media and how many emails for email list.

· Be sure to advertise and inform new and old customers of the new retail location, so that opening day is a success. This can be measured by the amount of people expected (Approx. 500) VS the amount that show up. If all goes well, it would be an estimated 41 people in the store per hour.

Stakeholders, Project Manager and Sponsor Authority

Stakeholder

Names

Role/Responsibility

Authorization

Project Sponsor

Alli B. Geewillikers

Melissa and Doug Inc.

Hasbro Games

To provide support and funding to allow the retail shop to open up successfully and continue to thrive

Has a say in toy location, physical location and advertising.

Project Manager

Evan Rapp

Ensure that the project is approved, processed and completed in and orderly fashion. Hire the coordinators and contractors to assist with getting everything together.

Has the final say of all of the projects and confirms or denies what the associates will or will not be doing to complete the project in a timely manner.

Retail Customers

Various children, adults, companies, teachers, schools, day cares, etc. looking for educational toys to assist them in their everyday lives.

To be a consumer and provide feedback based on customer service and products provided.

“The customer is always right” will apply when it comes to consumers and product.

Strip Mall Management

Oconee Connector Management Group

Collect Rent and ensure that the ground keeping is kept up to strip mall standards.

Make sure that store pays rent on time & participates in mandatory strip mall events and activities.

High-Level Requirements

High level requirements would be to utilize the SIPOC Theory and identify the following:

Need to be shelved with other alike products

Plush and Dolls

On display, free gift wrapping offered

Children of all ages, girls

Gund, TY, American Girl

Scholastic, Hasbro, American Education

Need to be shelved alphabetically for easier search for both adults & kids

On display. Some games will have demos.

Books and Games

Children and adults of all ages

Creative play toys such as Legos, play sets, wooden toys, puzzles

Toy Smith, Playmobil, Melissa and Doug

Stored in specific bins and shelves designed for product.

Demonstration on display, key facts will be listed next to each product

Children and adults of all ages

Project Budget Summary - $200,000

The total budget for the project will be spread amongst the following categories:

Expense

Price

Lease & Improvements

$48,000

Register Equipment

$16,500

Furniture, Fixtures & Equipment

$17,000

Signage

$4,000

Organizational & Training Costs

$3,500

Inventory to Start

$90,000

Advertising for Grand Opening

$9,000

Insurance Coverage

$2,000

Additional Funds

$10,000

Total

$250,000

Assumptions and Constraints

Assumptions

We can assume that the project will be on time, but will incur some delays during the process. This means that extra funds (other) have been put in place for any unexpected occurrence that are assumed to appear. Additional work may be required to complete the project in a timely manner and assist with getting everything set-up.

We can also assume that all product will be ordered and delivered on time for opening day. And that the space is currently still available in the location we are looking at.

Constraints

If the space is not available, the contractors are unable to complete the job, the advertising does come through as planned, or inventory does not arrive on time, this could cause potential issues for the store opening on time.

If employees quit, are not fit for the positions, or have restricted availability this may also be considered a huge restraint.

Milestones

Project start date 10.01.2015

Project complete date 05.20.2015 to open on 05.21.15

Event or Deliverable

Target Date

Responsibility

Project charter approved

09.01.2015

Owner of Lellow’s Toys

Project plan completed

09.25.2015

Project Manager

Project plan approved

09.30.2015

Finance Team

Project team assembled

10.01.2015

Project Manager

Project execution initiated/Reconstruction on rental

01.21.2015

Project Assistant Manager

Product ordered and Shipped

03.01.2015

Manger of Store

Project execution completed

05.01.2015

Project Manager and Assistance Manager

Customer acceptance

05.01.2015

Project Manager

Project closed out

05.20.2015

Owner

Business Risks

Opening up in the Oconee Connector Strip Mall near Walmart, TJ Max, Five Below, Target and Toys R Us. The area is an up and up and coming area with lots of newer families who are high class which could actually benefit the store.

High-Level Risks

Impact

How to Prevent

Competition is high for standard toys and products in the area

Medium Impact

Need to advertise more on how unique the services and products being sold at Lellow’s Toys are. They are not standard toys, but provide educational purpose and meaning.

Slightly higher cost than standard toy store

Medium Impact

People going to Lellow’s Toys will pay for quality toys and products. The customer service and free giftwrapping and personalization will help to enable this process and the products in the area.

Smaller Space

Low Impact

Store is more quaint and personal than a larger department store. Providing the best customer service to ensure that no one is missed. Strollers and what not will still be able to get through shelving. Can put a monitored stroller parking in the area if we really wanted to push for more space and comfort.

Approval Process

**Approval Decision to be completed by Owner of Lellow’s Toys**

Approved Project Charter, Project may proceed.

Approved, but project is on hold until future notice.

Revise charter and resubmit for re-approval

Project Charter is rejected

Print Name:

Title: Owner

- Notary Seal or Stamp -

Signature:

Notary Public:

Driver’s License or Other Form of Identification #:

W.B.S.

1. Discuss:

Barriers

(What do you need to control, avoid, improve, or preempt)

Need to communicate constantly and understand that when it comes to projects and assignments, not everyone will agree. Need to make sure everyone is on the same page about the assignment and the project.

Research Sources

(Where to look, how to share findings)

We can share through my courses email or personal email, but research can be found online, in the library, the SPC library, and related articles.

Sanctions

(How does the team react to issues or non-participation)

We discuss the issue with the person not participating. If the issue continues, notify the professor and not include their name on the assignment.

Learning Goals

(Objectives, aims, other)

To learn how to properly manage a project in a professional work environment. Learn team work, how to organize, how to communicate with vendors and contractors, etc.

Team Materials

(Review all the material in this folder)

3.W.S.B

4.Project Integration

The goal for the current project is to open a new retail location for Lellow’s Toys which will allow the company to expand sales and business into a new area of town. The company will sell educational toys and games to people of all ages and genders, disabilities, and conditions. It will allow children and people to grow and develop better skills.

In order to be successful, a full integration process will need to be implemented to help with completing the project successfully.

Integration Process:

Understand Who We Are:

Lellow’s Toys is a local retail educational toy store, with the potential to develop into something bigger than itself. Exactly what we expect our customers to do. The philosophy of Lellow’s Toys is not just to sell product to our customers, but educate them on the products that we sell and how they are unique to them. From creative play to cognitive development, Lellow’s Toys is about integrating education and fun – together.

Establish Location:

Athens, Georgia is the perfect location for Lellow’s Toy Store. The Oconee Connector Retail Locations are new, large in size, cost effective, and near largely developed neighborhoods. This will allow for great marketing and sales from local families.

Develop Store Needs and Finances

The toy store will need at least $200,000 in funding to completely accomplish its current goals for success. The budget is shown below for better understanding of the costs:

Expense

Price

Lease & Improvements (this includes contractors, interior design supplies, and other materials needed to make the building functional)

$48,000

Register Equipment (this includes POS computer systems and check registers)

$16,500

Furniture, Fixtures & Equipment (This includes shelving, racks, displays, front counter/register location, gift wrapping and personalization station)

$17,000

Signage (This includes the front sign on building, front door and windows)

$4,000

Organizational & Training Costs (This includes training employees on inventory, processing, register, sales, customers and products)

$3,500

Inventory to Start (This includes plush, dolls, wooden toys, cars, trains, books, games etc., as well as wooden table sets, play kitchens, etc. and demonstration toys)

$90,000

Advertising for Grand Opening (This includes marketing materials such as flyers, ads, business cards, stamp/frequent buyer cards,

$9,000

Insurance Coverage (this includes building and employee)

$2,000

Additional Funds (This includes office supplies, toiletries, OSHA compliance certificate, cleaning supplies, paint pens, wrapping paper, ribbon, etc.)

$10,000

Total

$250,000

Decide Contractors and Design

Contractors are a vital part of the Lellow’s Toys integration. They will be what glues the product together so the retail location can be successful. Research on local contracting companies is the first step to this part of the process. Finally, selecting an organization to complete to required work. It was decided that the best contractor for this specific job would be ETL Construction. Their ratings, experience and quality of work seem to be excellent, and they specialize in retail specific construction.

Following this decision would be a meeting to discuss fine details such as color, shelving, floor layout, register area, etc. to make the store a unique design, yet permeable for people and strollers of various sizes.

Select Product and Vendors

The product that Lellow’s Toys wishes to sell are the following: Dolls, Plush, Toy Cars, Wooden Trains, Books, Workbooks, Wooden Toys, Ride on Toys, Interactive Toys, etc. Toys to build the brain, work with dexterity, cognitive skills, and help those to learn and develop themselves. The vendors are listed below that were carefully selected based upon their product, their Corporate Social Responsibility, and their Customer Service.

· Gund

· TY

· American Girl

· Scholastic

· Hasbro

· American Education

· Toysmith

· Playmobil

· Melissa and Dug

Market Materials

How will Lellow’s Toys Market their opening day and their product? Selecting a company that can assist with Marketing Materials will be beneficial to the organizations growth. Creating online social media outlets through Facebook, Instagram, Pinterest, and Twitter are helpful. Post card advertisements will be mailed to local neighborhoods, daycare facilities, schools and disability homes. Large banner “Coming Soon” will be placed near major roadway near building to show construction in progress, with website information for people to research.

Additionally, when Lellow’s Toys opens, to ensure employees come back they will have opportunities to join the mailing list for discounts and coupons, and also be able to use stamp reward cards for purchases. Birthday buckets with incentivized discount will also be an option for those looking to ‘register’ for their child’s birthday party.

Want to make sure we are measuring the status of consumers in and out, and identify those customers that will be continually consistent.

Interview and Train Staff

Staffing is another important factor when it comes to opening a new retail location. Applications will be searched through and then interviews will begin. The owner/project manager will complete the interview process of the new employees. There will be a total of 7 employees hired, 6 staff and 1 assistant manager to help the owner of the store.

Each employee will be given training materials and guidebooks, employee handbooks, and required to sign paperwork. The guidebooks for the employee will review the various types of toys and suggestions, and allow the employee to learn the location of the product, what the product does, how it benefits a person, and how to recommend the product. The toys are educational for all ages and types of people, some toys more suited for an individual than others. They should be able to answer the question “What should I get for a 5 year old autistic boy, who has trouble grabbing and holding onto things?”

Customers are what keep the store going, so customer service will be the next thing each employee would be trained on. How to keep customers happy, how to upsell, and how to continually manage themselves in a child friendly environment.

Giftwrapping and personalization will be another thing that we will personalize.

The POS (Point of Sale) system will be the final training experience each employee will encounter. Learning how to properly manage inventory as it comes in and out of the facility, how to properly ring up a customer, process discounts, sales, checks, cash and credit cards.

Open the Store

After everything has been completed, it will be time to finally open the store. Preparing an opening sale, preparing the staff and having activities ready for people to play would make it a special time for everyone to enjoy themselves, while also working.

5.Risk

This part of the Project Management Plan provides a general description for the approach taken for identifying, analyzing, and prioritizing the risks associated with the project. It describes the procedures for contingency planning and the methods used in tracking risks, evaluating changes in individual risk exposures, and responding to those changes. Includes a plan for ongoing risk identification throughout the project's life cycle. In the context of this section, project risk means risk to one of the project baselines (technical, cost, or schedule). Lellow’s Toys takes a proactive approach to risk in that everyone shares in the ownership of risk management. We believe open and constant communication and information flow is vital in identifying and mitigating risk. We facilitate this through mandatory meetings, daily email, weekly reports, concise documentation, face to face interaction, and timely maintenance and updates of a risk assessment and response database.

Risk Assessment Tools

The following primary tools will be used to conduct risk assessments:

Risk Assessment Matrix. The Risk Assessment Matrix consists of two elements: risk factors and risk ranking guidelines. The risk factors represent the topics considered to have the most influence on project risk. The risk ranking guidelines are qualitative statements assigned to a low-, medium-, and high-risk category. The risk ranking guidelines are used to determine the risk impact of each of the risk factors to the project baseline.

Risk Register/Assessment Data Sheet. The Risk/Register/Assessment Data Sheet is the tool used to document the results of any risk assessment, and is designed to be used in conjunction with the Risk Assessment Matrix to obtain a structured, consistent, and rigorous assessment and response to risks. These will be turned in and addressed at the twice weekly risk assessment/response meetings to be chaired by the project manager and documented by the assistant project manager. Any known or believed unknown risks of significance are to be brought to the attention of the project manager immediately.

Twice Weekly Risk Assessment/Response Meetings. Mandatory meeting twice weekly every Monday and Friday. Those in attendance shall be the owner, all contractors, project manager, assistant project manager, store manager, finance team.

Risk Probability of Occurrence

Probability Range Probability Numeric Score

91-99% Very Likely 5

61-90% Probable 4

41-60% May Occur 3

11-40% Unlikely 2

1-10% Very Unlikely 1

Risk Impact

Impact Description Numeric score

Would cause project failure 5

Would cause major cost/schedule increases 4

Would cause moderate cost/schedule increases 3

Would cause slight cost/schedule increases 2

Would cause very negligible cost/schedule increases 1

Risk Register/Assessment Data Sheet

The project’s risk register is located in the project manager’s office and identifies the following points.

1. Date Identified – The date the risk was identified.

2. Status – Identifies whether the risk is potential, active, or closed.

3. Risk Description – A description of the risk.

4. Risk Probability

5. Risk Impact – The effect of the project phase and overall project if the risk event occurs.

6. Risk Score – Reflects the severity of the risks effect on objectives. The risk score is determined by multiplying the risk probability and risk impact values.

7. Risk Assignment – Person(s) responsible for the risk if it should occur.

8. Agreed Response – The strategy that is most likely to be effective.

· Avoidance – Risk avoidance entails changing the project plan to eliminate the risk or condition or to protect the project objectives from its impact.

· Transference – Risk transference is seeking to shift the consequence of a risk to a third party together with ownership of the response.

· Mitigation – Risk mitigation seeks to reduce the probability and/or consequences of a risk event to an acceptable threshold.

· Acceptance – This technique indicates that the project team has decided not to change the project plan to deal with a risk or is unable to identify any other suitable response strategy.

9. Risk Response Plan – Specific actions to enhance opportunities and reduce threats to the project’s objectives.

Roles and Responsibilities

Owner

The owner has the ultimate responsibility for identifying, analyzing, mitigating, and controlling project risks, including acceptance of the project risks, or modification, or termination of the project—all of which are project risk management activities. Owner, along with finance director and project manager are responsible for all contingency planning and approval.

Project Manager

· Overall responsibility for the risk management plan.

· Responsible for formulating risk responses and facilitating changes with owner and stakeholder’s approval.

· Input and approval from owners regarding which course to take: Avoidance, Transference, Mitigation or Acceptance regarding risks.

· Maintains the Risk Management Data Base and distribution of updates

· Briefs the team on the status of risks and response times.

· Tracks efforts to reduce moderate and high risk to acceptable levels.

· Provides risk management training (ensuring everyone is familiar with probability scale, Impact scale, and how to properly fill out risk data sheet.

· Facilitates risk assessments and preparing risk briefings, reports, and documents required for project review meetings.

· Chairs mandatory twice weekly risk assessment/response meetings to be attended by, assistant project manager, contractors, store manager, and finance team.

· Communicate results of meetings to owner and all stakeholders’ weekly e-mail.

· Meet separately with owner and stakeholders with risk management update and status of possible future risks.

· Along with owner and stakeholders, review and revise risk management plan as needed.

Assistant Project Manager

· Assists project manager with overall administration of risk management plan.

· Primary liaison between team members and project manager.

· Ensure all project team members are prepared with input to weekly risk meetings.

· Assign risk responsibility/ownership to the appropriate team member.

· Ensure all risk data sheets are properly recorded to risk register database.

· Responsible for tracking and closing out of all risk data sheets with project manager sign off.

· Record minutes of twice weekly risk assessment meetings.

· Advising project manager of potential risks not identified by project team.

Project Team

· Frontline responsibility for identifying risks.

· Monitoring and tracking of risks assigned to them at last risk assessment meeting.

· Assist in assessing and assigning score to any real or perceived risks.

· Recommend any changes to the current risk assessments.

· Input regarding course of action to take regarding specific risks.

Contractors

· Attend twice weekly risk assessment meetings.

· Twice weekly status updates/progress reports, specifically in regards to:

· Design

· Site conditions

· Construction procedures

· Construction occupational safety

Store Manager

· Supports project manager regarding store layout and opening inventory issues/changes.

Finance Team

· Responsible for weekly updates of financial condition and payment status of all pertinent vendors and contractors.

· Approval and sign off of any risk assessments that may cause potential cost overruns.

· Input and approval of any agreed response strategy along with owner, project manager, and stakeholders.

6.Risk Management Plan

Description

Lellow’s Toys, a popular specialty toystore, is opening there second location in Athens, GA. Opening this new retail location will allow the company to expand sales and business into a new area of town. The company will sell educational toys and games to people of all ages and genders, disabilities, and conditions. It will allow children and people to grow and develop better skills.

Roles and responsibilities for mitigating risk

Owner: Hires management team, payroll and costs, creates contingency plan for management reserves, transfers risk to contractors, decides who is best suited for controlling activities, providing liability insurance, and approving project charter.

Project Manager: Plans and executes project, oversees the project, reconstruction on rental, holds meetings for the project, budget reserves such as allocating resources to project activities, ensures that the project is approved, processes and completes project in an orderly fashion, developing methods to assess and resolve technical uncertainties, and hiring the coordinators and contractors to assist with store grand opening.

Project Assistant Manager: Assists project manager with responsibilities, delegating tasks and responsibilities to contractors and coordinators, and acts as project manager when project manager is unavailable.

Contractors: Taking ownership by absorbing risks, identifying and documenting responsibility, does the actual work, coordinates their contributions with the project team, providing support to project scope, and completing segments by deadline.

Store Manager: Supports project manager, orders inventory and expenses, trains employees, delegating tasks to employees, following through with employees to ensure tasks are completed, communicates with store owner, ensuring customer satisfaction, and loss prevention.

Employees: Stocking shelves, merchandizes displays to planogram, hanging signage, cashiering, verifying correct prices, gift wrapping and personalizing toys, providing excellent customer service and experience.

Sales Marketer: Provides marketing tools, advertising, providing signage, creates planograms for merchandising, and ensures store managers are merchandising displays to planogram.

Finance Team: Processes, underwrites, and approves project plan, and finances project.

7.Budget

Total budget break down is listed below, followed by its risk analysis on page 7.

Total Budget $250,000

Lellow’s Toys: Risk Management Plan Group 4-1

Lellow’s Toys: Final Project Group 4 – 1

Revision 20150927

Risk/Association: Timing and Delivery

Risk Owner:

Description of Risk: Supply chain failure for on-time delivery of product inventory for Grand Opening Day

Score: 4

Likelihood: 1

Impact: 4

Rank:

Current Internal Controls and Their Effectiveness:

· Ordering product in advance |

· Communicate and outline necessities to vendors |

Proposed Actions to Reduce Likelihood of the Risk

Target Completion Date

Status and Impact of Actions

1

Order product in advance, to ensure delivery

03/31/2016

Ordering in advance allows for the option of receiving product earlier,

rather than later.

2

Develop relationships with other vendor/

suppliers

01/01/2016

Developing relationships with other vendors and suppliers allows for

other opportunities when selling product, and ensures that there will be product in the store if number 1 vendors cannot supply.

3

Offer Incentives to ensure on-time delivery

01/01/2016

This may cost a bit more financially, but will ensure that no matter what

the product is delivered when asked.

Proposed Actions to Reduce Impact of the Risk

Target Completion Date

Status and Impact of Actions

1

Having other back up options in place for

Product, in case it is B.O. or not delivered.

03/01/2016

Having other options in place of product that may not be delivered,

allows for better options and the option to continue to sell product.

2

Offer Incentives to ensure on time delivery

01/01/2016

This will help to reduce the effect of no inventory

Risk/Association: General Risk Associations

Risk Owner:

Description of Risk: The store and all items inside (shelving, plastic toys, plush toys, employees, restroom, power outlets, displays, etc.) must be safe for children of all ages. This is a high risk category, any safety issues could lead to down fall of the store. All shelves and displays need to be secured as to not fall and injure children or parents also employees must be screened well to avoid any compromising situations where the store could be liable.

Score: 15

Likelihood: 3

Impact: 5

Rank:

Current Internal Controls and Their Effectiveness:

· All racks are ordered from the companies that sell the product |

· Protocol for the store, restrooms and backrooms are up to OSHA standard |

· Application for employees has strategic questions |

Proposed Actions to Reduce Likelihood of the Risk

Target Completion Date

Status and Impact of Actions

1

Secure racks to floor and walls to prevent falling

03/31/2015

Prevents racks from falling on top of children

2

Hang certificates of OSHA compliance

Immediately

Certificate should be received and showing as soon as the store can

have contractors, workers, or anyone. This will cover legal liability.

3

Perform background check on employees

N/A After interview process

Allows for safe environment, and help to assist with liability concerns

Proposed Actions to Reduce Impact of the Risk

Target Completion Date

Status and Impact of Actions

1

Similar to likelihood risks

If completed, the impact of liability can be reduced significantly.

Risk/Association: General Risks

Risk Owner:

Score: 16

Likelihood: 4

Impact: 4

Rank:

Description of Risk: Product shrinkage can happen either through theft or from accident destruction by children, this must be monitored as any shrinkage results in an immediate loss to the store. Also shrinkage is something that can be controlled with the proper measures which can be determined after opening but measures before opening can be implemented like security cameras and security tags on higher priced items to avoid theft.

Current Internal Controls and Their Effectiveness:

· Have an employee by front door at all times, one at the register, and one watching around the store to ensure visual security of product coming in and out. |

Proposed Actions to Reduce Likelihood of the Risk

Target Completion Date

Status and Impact of Actions

1

Security Cameras

02/01/2015

Security Cameras will allow review and understanding of where lost

product has gone, and also how employees react.

2

Security Tags

After inventory received

Will alert store employees when expensive product has walked out of

store.

Proposed Actions to Reduce Impact of the Risk

Target Completion Date

Status and Impact of Actions

1

Make sure small product is by register

04/30/2016

Tiny product pieces near register are less likely to walk than those that are

not. This can assist with loss prevention.

2

Ensure that employees are trained on theft

Awareness

04/30/2016

This will assist employees with understanding what to be aware of, how to

be safe, but also prevent theft from happening frequently in the store.

Risk/Association: Finances

Risk Owner:

Score: 6

Likelihood: 3

Impact: 2

Rank:

Description of Risk: Original cost of budget was $200,000 for even number purposes. After looking up cost commercial costs of improvements, equipment, and inventory cost was increased by $43,000 over the original number. These numbers include the cost of labor as well as Georgia averages for the salary ranges. However, there is always room to cut cost depending on the location that is chosen for the store and how much restoration and improvements that to be done. The budget was then raised to $250,000. The idea of this continuing to happen, and handling increase in inventory cost or construction costs are risky.

Current Internal Controls and Their Effectiveness:

· Have a strict budget with researched set costs |

Proposed Actions to Reduce Likelihood of the Risk

Target Completion Date

Status and Impact of Actions

1

Ask for proposals from various contractors, don’t

settle with the first team that is met with.

11/01/2015

Want to find a team that is cost effective, but will also ensure

that our project is completed in a timely and efficient manner.

2

Make sure inventory is good quality inventory,

but check with all vendors to ensure that we are

getting the best bang for our buck. Maybe talk

about free racks with purchases as well.

01/31/2016

Want to make sure we speak with all vendors about their pricing and

deals, this will allow us to save money by purchasing a variety of

products, and getting a discount on what we purchase.

3

Proposed Actions to Reduce Impact of the Risk

Target Completion Date

Status and Impact of Actions

1

Ensure that credit is in a good place for additional

loans if needed

11/01/2015

Want to ensure that all credit and financials are at a stable point to

pull out more loans, and cover any other financials so the financial

hardship is not difficult if this does in deed happen.

2

Make sure that the budget has a cushion of at

least $10,000

11/01/2015

Want to make sure additional funds are in the budget to cover for the

Costs of unplanned emergencies and issues that will happen.

Current Internal Controls and Their Effectiveness:

· Currently looking to sell educational toys, books and games |

· Location within short distance of Toys R Us, Walmart, and Target |

· Wooden and American Made toys are our specialty |

Description of Risk: Specialty Toy Store may not obtain as much business because of higher priced and more unique options to select from.

Rank:

Impact: 5

Likelihood: 2

Score: 10

Risk Owner:

Risk/Association: Methodology

Proposed Actions to Reduce Likelihood of the Risk

Target Completion Date

Status and Impact of Actions

1

Offer free gift wrapping and personalization with

any purchase

03/31/2016

Free gift wrapping and personalization will make customers more prone to

purchasing product, knowing that their getting more ‘bang for their buck.’

2

Educate employees on the specialty of the

Product and how beneficial each piece is

03/31/2016

Training employees on each product piece and explaining how they can

benefit various types of children and people allows the consumer to have

a better understanding of the products and want to purchase more product

from our store.

Proposed Actions to Reduce Impact of the Risk

Target Completion Date

Status and Impact of Actions

1

If this happens, go to cheaper yet efficient product

06/01/2016

We will already have other vendor options, but if we are not receiving customers because of pricing and other concerns, we will need to lower the cost effectiveness of our product.

8.Time

The project of opening up Lellow’s toys store is estimated to take eight months to complete. The initial approval of the project charter is expected to take 30 days, this is in order to get approval from the stakeholders as well as getting approval from the finance team. Once the charter has been approved then the project manager will assign a team to manage the different aspects of the team and the stages of the project. This will include a retail manager to buy the inventory, remodeling the inside of the store to accommodate the incoming inventory, as well as a finance team to make sure the project stays on budget.

Once the team has been assembled then the next step is to order the inventory. This will be managed by the retail manager, who will then answer to the finance team and then the project manager. It is the retail manager’s jobs to research the best supplier for the inventory of the toys that will be coming into the store. The best option is to place a bid out to multiple suppliers and have them bid for the business. The qualifications will be requiring that the supplier will have to have the ability and space to fulfil the big order of initial inventory as well as being able to keep a steady flow in inventory coming in as it comes off the shelf.

The final step in the timing of the project is to make sure that the customer is satisfied with the end result, also known as delivering the product to the customer. Once the customer has been satisfied with the end result of the project then the project will be complete.

9.Procurement

Plan procurement management

To open a secondary retail business location, Lellow’s Toys, a popular specialty toystore, in Athens, GA. Opening this new retail location will allow the company to expand sales and business into a new area of town. The company will sell educational toys and games to people of all ages and genders, disabilities, and conditions. It will allow children and people to grow and develop better skill. The deliverables in opening a secondary retail location include improvements, equipment, and inventory. Using fixed-priced contracts will ensure quality products being delivered into our inventory.

Conduct procurements

Developing relationships with other vendors and suppliers allows for other opportunities when selling product, and ensures that there will be product in the store if popular vendors cannot supply. Having other suppliers in the event a vendor cannot provide a product in time or items that are not offered through their supplier. In addition to efficient deliveries, having multiple suppliers will provide Lellow’s Toys opportunities to increase profits. Using fixed-price contracts, Lellow’s Toys will be able to negotiate pricing between different vendors.

Control procurements

In controlling such procurements, Lellow’s Toys system inventory management (SIMs), will generate suggested inventory amounts to be ordered based off how fast items move off the shelf in accordance to the current inventory count and anticipated sales. Once the order is generated, the store managers will review and approved the order. Once the order is delivered, the store employees will scan the order and add it into the store’s inventory. The store managers will add the invoices into the store buy card of when it was received and its cost. The store managers will set the invoices aside for the owner of Lellow’s Toys accountant for review.

Close procurements

Once the accountant reviews the invoices have been inputted correctly into the system and all records match, the accountant will place the invoices in an envelope to be mailed out and paid to the vendors. Many vendors offer discounts on invoices if invoices are paid within thirty days so it is crucial that the management team records accurately.

10.Quality Management

Quality policies will be implemented during several phases of project from reviewing the work on the contractors, screening employees before hiring, cost control during construction, and loss prevention. Some of these measures will be controlled by the store manager while others will be handled by the project manager overseeing construction. The construction quality will be managed by the contractors own foreman and the project manager working in concert to ensure that the renovations are in congruency with what was ordered and is going to be built to last the store at least 20 years, while being on time and under budget.

Potential employees will also undergo an extensive background check and screening process to ensure that children will be safe and not exposed to anyone who may possible want to harm them or the company. All toys will be inspected by store staff for supreme quality and safety before being made available to the public for sale. Also the supply chain quality will be managed with detailed oversight to ensure the products do not contain any materials which are toxic or could harm the children in any way. Most of the toy manufacturers we are working with also with six sigma practices which gives us confidence that their products will be of a supreme quality.

11.Communication Management

Stakeholders require weekly status meetings to enhance communication with the status of each task and phase completion to ensure the project stays on budget and with time. Resources have been allotted for these meetings with normal expenses. Email and phone will be the main form of communication other than the status meetings. Secondary forms of communication will including walkie-talkies radios and an in store intercom which will be used in the after renovations are completed and the store is in full operation. Also the floor staff will have to communicate with the inventory buyer through a weekly report to determine which items are not selling and which items need to be reordered.

The project manager and various project champions will be responsible for communicating the information during the meetings but only the project manager may release confidential information. Common terms will be distributed via handout at meetings along with workflow charts. During the meetings the current tasks will be reviewed to make sure things are on track, and any changes to the baseline of the project may be presented for review. Information will be shared via secured and approved methods like company email or other devices issued by the company.

12.Stakeholder Management

Project stakeholder management is the processes used to identify people, groups or organizations that could impact or be impacted by the project, to analyze stakeholder expectations and their impact on the project--and to develop appropriate management strategies for effectively engaging stakeholders in project decisions. Lellow’s Stakeholder management plan approach consists of the following areas:

1. Stakeholder Identification-Stakeholder identification and analysis information will be performed prior to project inception using a combination of the project charter, meetings (Owner, Project Manager, Finance Manager), brainstorming, and expert judgment.

· Project charter

· Stakeholder analysis

· Expert judgment

· Meetings

Stakeholder

Key interests

Power

Influence

Supporter

Communication level

Owner

Financial

High

High

Yes

High

Project Manager

Successful Completion/Promotion related

High

High

Yes

High

Assistant Project manager

Success full completion/job related

Low

Medium

YES

High

Contractor

Future Contracts

medium

Medium

Yes

High

Store Manager

store is appealing to new customers

High

Medium

Yes

Medium

Store Employees

Low interest

Low

Low

Yes

Low

Marketing

Opening day Success

Low

Low

Yes

Medium

Finance Manager

Cost Overruns

High

High

Yes

High

Vendors

Continued orders

Medium

Medium

Yes

High

2. Plan Stakeholder Management-Planning for how to manage stakeholders will be the responsibility of the Project manager with input from the owner. This will be based on based on the stakeholder analysis developed in step 1 meetings and review of past transactions with stakeholders.

· Expert judgment

· Meetings

· Analytical Techniques

3. Manage Stakeholder Engagement

· Communication requirements-the following methods will be used to ensure timely communication and continued engagement with important/influential stakeholders.

· Twice weekly email of risk assessment meeting minutes-assistant project manager

· Twice monthly stakeholder meetings chaired by owner, project manager, and finance manager to update stakeholders on progress, and to clarify and address any issues that have been identified. These meetings will also serve the purpose of gauging stakeholder continued level of interest and influence on project.

· Change Log (maintained by project manager) will be reviewed and addressed at each twice monthly stakeholder meeting.

· Minutes of each stakeholder meeting will be taken by assistant project manager and used to revise stakeholder analysis.

4. Control Stakeholder Engagement- Maintain stakeholder confidence and improve stakeholder engagement through project life cycles.

· Monthly reassessment of current stakeholder’s power and influence position gathered from twice monthly stakeholder meetings.

· Project Manager to have ownership and Assistant Project Manager Co-ownership of stakeholder engagement and control process.

References

A guide to the project management body of knowledge: (PMBOK® guide) (5th ed.). (2013). Newtown Square, PA: Project Management Institute. 

Project management: The managerial process (Sixth ed.). Gray, C., & Larson, E. (n.d.).

Retail Store Manager Salary in Miami, Florida (United States) United States Home Change Country (n.d.). Retrieved September 5, 2015

Institue, P. M. (2013). Project Management Body of Knowledge fifth Edition. Newtown Square, PA: project Management Institute, Inc.

Larson, E., & Gray, C. (2014). Project Management: The Managerial Process. New York, NY: McGraw-Hill Education .

Mind Tools. (2013). A Powerful Methodology for Creative Problem Solving. Retrieved from Mind Tools: http://www.mindtools.com/pages/article/newCT_92.htm

TOys, L. E. (2015). Franchise Information. Retrieved August 18th, 2015, from Learning Express Toys: https://learningexpress.com/franchise/

Opening of Lellow's Toys (0)

Business Requirements (2.0)

Detail and Design (3.0)

Inventory and POC Systems (4.0)

Grand Opening (5.0)

Project Management (1.0)

Planning (1.1)

Meetings (1.2)

Administration (1.3)

Location of New Store (2.1)

Employees and Staff (2.2)

Locate Vendors (2.3)

Paint Design (3.1)

Shelving and Racks (3.2)

Product Layout (3.3)

Register Layout (3.4)

Review Toy Catalogues (4.1)

Research Various Products and companies (4.2)

Order Computer System and Registers (4.4)

Put out inventory in associated areas (4.5)

Mail post cards and brochures to local housings, schools, etc. (5.1)

Training Employees and Staff for opening day (5.2)

Payroll/New Hire Paperwork Processing (1.4)

Locate Contractors for building (2.4)

Window Design for window dsiplays (3.5)

Purchase activities for families to do on opening day (5.3)

Order Gift Wrap and Ribbon (4.3)

Area for Gift Wrapping (3.6)

Improvements

Paint137.00$

Furniture700.00$

Lights500.00$

Locks100.00$

Flooring2,000.00$

Equipment

Cashier stations [2]1,000.00$

Shelving units1,400.00$

Registers500.00$

Price Guns120.00$

POS system1,500.00$

Computers [4]3,200.00$

Signage430.00$

Salary

Managers [2]80,000.00$

Employees [4]72,000.00$

Inventory

Toys80,000.00$

Total:243,587.00$

Sheet1

Improvements
Paint $ 137.00
Furniture $ 700.00
Lights $ 500.00
Locks $ 100.00
Flooring $ 2,000.00
Equipment
Cashier stations [2] $ 1,000.00
Shelving units $ 1,400.00
Registers $ 500.00
Price Guns $ 120.00
POS system $ 1,500.00
Computers [4] $ 3,200.00
Signage $ 430.00
Salary
Managers [2] $ 80,000.00
Employees [4] $ 72,000.00
Inventory
Toys $ 80,000.00
Total: $ 243,587.00