| Work Breakdown Structure |
| | Project Name: | District 4 Warehoiuse Move |
| | Project MGR |
| | Date: |
| Work breakdown structure purpose and limitations |
| the purpose of this worksheet is to | | identify the work to be done |
| | | identify the types of resources required for the work |
| | | Develop estimates for each element |
| This worksheet does not address: | | When the work will be completed |
| Use the following table to define the major deliverables and associated task detail for each deliverable. Use the |
| example (in red) for help in determining how to break up the work and identify the Work ID numbers. Expand the |
| Work Package Task |
| ID | Tasks | | | Resource(s) Required | | | Estimated Duration (in days) tasks | | | | Estimated Duration (in days) work package |
| 1 | project kick-off | | | | | | | | | | 4 |
| 1.1 | Book location for meeting | | | ProjectMgr | | | 1 |
| 1.2 | invite stakeholders | | | Project Mgr | | | 1 |
| 1.3 | Prepare presentation | | | Project Mgr | | | 1 |
| 1.4 | Conduct meeting | | | Project Mgr | | | 1 |
| 2 | Project Documents | | | | | | | | | | 13 |
| 2.1 | develop Charter/Scope | | | Project Mgr | | | 2 |
| 2.2 | Develop WBS | | | project mgr & workers | | | 7 |
| 2.3 | develop project Plan | | | Project Mgr | | | 2 |
| 2.4 | develop communication Plan | | | Project Mgr | | | 2 |
| 3 | Status Reports/Meetings | | | | | | | | | | 3 |
| 3.1 | develop status Report | | | Project Mgr | | | 1 |
| 3.2 | set schedulefor team meetings | | | Project Mgr | | | 1 |
| 3.4 | set schedule for stakeholder meeting | | | | | | 1 |
| 4 | Initial Planning meetings/vendors | | | Project Mgr | | | | | | | 5 |
| 4.1 | Meet with framing/Drywall | | | project mgr/Eastside Framing PM | | | 1 |
| 4.2 | meet with Electrical | | | Project mgr/Sparks Electrical PM | | | 1 |
| 4.3 | Meet with Plumbing | | | project mgr/waterwork plumbin | | | 1 |
| 4.4 | meeting with Finish Work | | | project mgr/woodcraft carpentry PM 1 | | | 1 |
| 4.5 | meet with Student workers | | | project mgr/students workers mgr | | | 1 |
| 5 | Electrical Permits | | | | | | | | | | 10 |
| 5.1 | Obtain Electrical permits | | | sparks electrical PM | | | 10 |
| 6 | Plumbing Permits | | | | | | | | | | 10 |
| 6.1 | Obtain Plumbing Permits | | | waterworks plumbing PM | | | 10 |
| 7 | Building Permits | | | | | | | | | | 10 |
| 7.1 | Obtain Building Permits | | | eastside framing/drywall PM | | | 10 |
| 8 | Framing | | | | | | | | | | 24 |
| 8.1 | Framing-Order Supplies | | | eastside framing/drywall Pm | | | 3 |
| 8.2 | Framing-Build | | | eastside framing/drywall | | | 15 |
| 8.3 | Framing-Inspect | | | City & County | | | 5 |
| 8.4 | Framing-project Sign-off | | | Project Mgr | | | 1 |
| 9 | Electrical | | | | | | | | | | 19 |
| 9.1 | Electrical-install | | | sparks electrical Pm | | | 3 |
| 9.2 | ElectricalInstall | | | sparks elecrical | | | 10 |
| 9.3 | Electrical-Inspect | | | City & County | | | 5 |
| 9.4 | Electrical-Project sign-off | | | Project Mgr | | | 1 |
| 10 | Plumbing | | | | | | | | | | 19 |
| 10.1 | Plumbing-order Supplies | | | waterworks plumbing PM | | | 3 |
| 10.2 | Plumbing-Install | | | waterworks plumbing | | | 10 |
| 10.3 | Plumbing-Inspect | | | City & County | | | 5 |
| 10.4 | Plumbing-project sign-off | | | Project Mgr | | | 1 |
| 11 | Drywall | | | | | | | | | | 24 |
| 11.1 | Drywall-Order Supplies | | | Eastside framing & drywall Pm | | | 3 |
| 11.2 | Drywall-Install | | | eastside framing & drywall | | | 15 |
| 11.3 | Drywall-inspect | | | City & County | | | 5 |
| 11.4 | Drywall-project Sign-off | | | Project Mgr | | | 1 |
| 12 | Finish Work | | | | | | | | | | 24 |
| 12.1 | Finish-order Supplies | | | Woodcraft Carpentry PM | | | 3 |
| 12.2 | Finish-Install | | | Woodcraft carpentry | | | 15 |
| 12.3 | Finish-Inspect | | | City & County | | | 5 |
| 12.4 | Finish Project Sign-off | | | Project Mgr | | | 1 |
| 13 | Workbenches | | | | | | | | | | 20 |
| 13.1 | workbenches-Order Supplies | | | Student Workers Manager | | | 2 |
| 13.2 | workbenches-Build | | | Student Workers Manager | | | 15 |
| 13.3 | workbenches-quality inspection | | | Project mgr | | | 2 |
| 13.4 | Workbenches-project sign-off | | | Project Mgr | | | 1 |
| 14 | Equipment Packaging | | | | | | | | | | 5 |
| 14.1 | Pack production equipment | | | City Equipment Movers PM | | | 2 |
| 14.2 | Pack non-production equipment | | | City Equipment Movers PM | | | 2 |
| 14.3 | project-sign-off | | | Project Mgr | | | 1 |
| 15 | Move | | | | | | | | | | 7 |
| 15.1 | Move production equipment | | | Express Moving Company PM | | | 3 |
| 15.2 | Move non-production equipment | | | Express Moving Company | | | 3 |
| 15.3 | project sign-off | | | project Mgr | | | 1 |
| 16 | Procurement Closure | | | | | | | | | | 5 |
| 16.1 | review contract work | | | project Mgr | | | 3 |
| 16.2 | Release Contractors | | | Project Mgr | | | 1 |
| 16.3 | Pay Contractors | | | Project Mgr | | | 1 |
| 17 | Project Closure | | | | | | | | | | 7 |
| 17.1 | Final Report | | | Project Mgr | | | 3 |
| 17.2 | Archive Documentation | | | Project Mgr | | | 3 |
| 17.3 | lessons learned | | | Project Mgr | | | 1 |