NEO Project

Employee

Orientation Site

[dur = 92 days]

Controlling [1.4]

[dur = 89 days]

Change reports

[1.4.2]

[dur = 60 days]

Status Report

[1.4.1]

[dur = 80 days]

Executing [1.3]

[dur = 48 days]

Construction

[1.3.6]

[dur = 33.5 days]

Integration and

Testing [1.3.7]

[dur = 6.5 days]

Interface

Requirement [1.3.1]

[dur = 3 days]

Product

Requirements

Review Meeting

[1.3.5]

[dur = 0.5 days]

Software

Requirement [1.3.2]

[dur = 2 days]

Training Materials

[1.3.4]

[dur = 2 days]

Training [1.3.8]

[dur = 1.5 days]

User

Documentation

[1.3.3]

[dur = 2 days]

Initiating [1.1]

[dur = 1 day]

Charter signed

[1.1.3]

[dur = 0 days]

Develop project

charter [1.1.1]

[dur = 1 day]

Review charter

[1.1.2]

[dur = 1 day]

Planning [1.2]

[dur = 4.5 days]

Develop project

plan [1.2.1]

[dur = 3 days]

Kickoff Meeting

[1.2.4]

[dur = 0.5 days]

Project plan

approved [1.2.3]

[dur = 0 days]

Review project plan

[1.2.2]

[dur = 1 day]

Project Close [1.5]

[dur = 0.5 days]

Post Mortem

Lessons Learned

[1.5.1]

[dur = 0.5 days]