| WBS | Task Name | Duration | Start | Finish | Predecessors | Resource Names |
| Task1 | Project Kick-off | 1 day | Mon 1/3/11 | Mon 1/3/11 |
| Task 1.1 | Book location for meeting | 1 day | Mon 1/3/11 | Mon 1/3/11 | Task 1 | Project Manager |
| Task 1.2 | Invite stakeholders | 1 day | Mon 1/3/11 | Mon 1/3/11 | Task 1.1 | Project Manager |
| Task1.3 | Prepare presentation | 1 day | Mon 1/3/11 | Mon 1/3/11 | Task 1.2 | Project Manager |
| Task1.4 | Conduct the meeting | 1 day | Mon 1/3/11 | Mon 1/3/11 | Task 1.3 | Project Manager and Attendees |
| Task2 | Project Documents | 7 days | Mon 1/3/11 | Tue 1/11/11 | Task 1 |
| Task2.1 | Develop Charter/Scope | 2 days | Mon 1/3/11 | Tue 1/4/11 | Task 1.3 | Project Manager |
| Task2.2 | Develop WBS | 7 days | Mon 1/3/11 | Tue 1/11/11 | Task 2.1 | Project Manager and Workers |
| Task2.3 | Develop Project Plan | 2 days | Mon 1/3/11 | Tue 1/4/11 | Task 2.2 | Project Manager |
| Task2.4 | Develop Communication Plan | 2 days | Mon 1/3/11 | Tue 1/4/11 | Task 2.3 | Project Manager |
| Task3 | Status Reports/Meetings | 1 day | Mon 1/3/11 | Mon 1/3/11 | Task 2 |
| Task3.1 | Develop Status Report | 1 day | Mon 1/3/11 | Mon 1/3/11 | Task 2.3 | Project Manager |
| Task3.2 | Set schedule for team meetings | 1 day | Mon 1/3/11 | Mon 1/3/11 | Task 3.1 | Project Manager |
| Task3.3 | Set schedule for stakeholder meetings | 1 day | Mon 1/3/11 | Mon 1/3/11 | Task 3.2 | Project Manager |
| Task4 | Initial Planning Meetings with Vendors | 1 day | Mon 1/3/11 | Mon 1/3/11 | Task 3 |
| Task4.1 | Meet with Framing/Drywall | 1 day | Mon 1/3/11 | Mon 1/3/11 | Task 3.2 | Project Manager and East Side Framing PM |
| Task4.2 | Meet with Electrical | 1 day | Mon 1/3/11 | Mon 1/3/11 | Task 4.1 | Project Manager and Sparks Electrical PM |
| Task4.3 | Meet with Plumbing | 1 day | Mon 1/3/11 | Mon 1/3/11 | Task 4.2 | Project Manager and Waterworks Plumbing PM |
| Task4.4 | Meet with Finish Work | 1 day | Mon 1/3/11 | Mon 1/3/11 | Task 4.3 | Project Manager and Woodcraft Carpentry PM |
| Task4.5 | Meet with Student Workers | 1 day | Tue 1/4/11 | Tue 1/4/11 | Task 4.4 | Project Manager and Student Workers Manger |
| Task5 | Electrical Permits | 10 days | Mon 1/3/11 | Fri 1/14/11 | Task 4 |
| Task5.1 | Obtain Electrical Permits | 10 days | Mon 1/3/11 | Fri 1/14/11 | Task 4.4 | Sparks Electrical PM |
| Task6 | Plumbing Permits | 10 days | Mon 1/3/11 | Fri 1/14/11 | Task 5 |
| Task6.1 | Obtain Plumbing Permits | 10 days | Mon 1/3/11 | Fri 1/14/11 | Task 5.1 | Waterworks Plumbing PM |
| Task7 | Building Permits | 10 days | Mon 1/3/11 | Fri 1/14/11 | Task 6 |
| Task7.1 | Obtain Building Permits | 10 days | Mon 1/3/11 | Fri 1/14/11 | Task 6.1 | East Side Framing & Drywall PM |
| Task8 | Framing | 15 days | Mon 1/3/11 | Fri 1/21/11 | Task 7 |
| Task8.1 | Framing-Order Supplies | 3 days | Mon 1/3/11 | Wed 1/5/11 | Task 7.1 | East Side Framing & Drywall PM |
| Task8.2 | Framing-Build | 15 days | Mon 1/3/11 | Fri 1/21/11 | Task 8.1 | East Side Framing & Drywall |
| Task8.3 | Framing-Inspect | 5 days | Mon 1/3/11 | Fri 1/7/11 | Task 8.2 | City & County |
| Task8.4 | Framing-Project Sign-off | 1 day | Mon 1/3/11 | Mon 1/3/11 | Task 8.3 | Project Manager |
| Task9 | Electrical | 10 days | Mon 1/3/11 | Fri 1/14/11 | Task 8 |
| Task9.1 | Electrical-Order Supplies | 3 days | Mon 1/3/11 | Wed 1/5/11 | Task 8.3 | Sparks Electrical PM |
| Task9.2 | Electrical-Install | 10 days | Mon 1/3/11 | Fri 1/14/11 | Task 9.1 | Sparks Electrical |
| Task9.3 | Electrical-Inspect | 5 days | Mon 1/3/11 | Fri 1/7/11 | Task 9.2 | City & County |
| Task9.4 | Electrical-Project Sign-off | 1 day | Mon 1/3/11 | Mon 1/3/11 | Task 9.3 | Project Manager |
| Task10 | Plumbing | 10 days | Mon 1/3/11 | Fri 1/14/11 | Task 9 |
| Task10.1 | Plumbing-Order Supplies | 3 days | Mon 1/3/11 | Wed 1/5/11 | Task 9.3 | Waterworks Plumbing PM |
| Task10.2 | Plumbing-Install | 10 days | Mon 1/3/11 | Fri 1/14/11 | Task 10.1 | Waterworks Plumbing |
| Task10.3 | Plumbing-Inspect | 5 days | Mon 1/3/11 | Fri 1/7/11 | Task 10.2 | City & County |
| Task10.4 | Plumbing-Project Sign-off | 1 day | Mon 1/3/11 | Mon 1/3/11 | Task 10.3 | Project Manager |
| Task11 | Drywall | 15 days | Mon 1/3/11 | Fri 1/21/11 | Task 10 |
| Task11.1 | Drywall-Order Supplies | 3 days | Mon 1/3/11 | Wed 1/5/11 | Task 10.3 | East Side Framing & Drywall PM |
| Task11.2 | Drywall-Install | 15 days | Mon 1/3/11 | Fri 1/21/11 | Task 11.1 | East Side Framing & Drywall |
| Task11.3 | Drywall-Inspect | 5 days | Mon 1/3/11 | Fri 1/7/11 | Task 11.2 | City & County |
| Task11.4 | Drywall-Project Sign-off | 1 day | Mon 1/3/11 | Mon 1/3/11 | Task 11.3 | Project Manager |
| Task12 | Finish Work | 15 days | Mon 1/3/11 | Fri 1/21/11 | Task 11 |
| Task12.1 | Finish-Order Supplies | 3 days | Mon 1/3/11 | Wed 1/5/11 | Task 11.3 | Woodcraft Carpentry PM |
| Task12.2 | Finish-Install | 15 days | Mon 1/3/11 | Fri 1/21/11 | Task 12.1 | Woodcraft Carpentry |
| Task12.3 | Finish-Inspect | 5 days | Mon 1/3/11 | Fri 1/7/11 | Task 12.2 | City & County |
| Task12.4 | Finish-Project Sign-off | 1 day | Wed 1/3/11 | Wed 1/5/11 | Task 12.3 | Project Manager |
| Task13 | Workbenches | 15 days | Mon 1/3/11 | Fri 1/21/11 | Task 12 |
| Task13.1 | Workbenches-Order Supplies | 2 days | Mon 1/3/11 | Tue 1/4/11 | Task 12.3 | Student Workers Manager |
| Task13.2 | Workbenches-Build | 15 days | Mon 1/3/11 | Fri 1/21/11 | Task 13.1 | Student Workers |
| Task13.3 | Workbenches-Quality inspection | 2 days | Mon 1/3/11 | Tue 1/4/11 | Task 13.2 | Project Manager |
| Task13.4 | Workbenches-Project Sign-off | 1 day | Mon 1/3/11 | Mon 1/3/11 | Task 13.3 | Project Manager |
| Task14 | Equipment Packing | 2 days | Mon 1/3/11 | Tue 1/4/11 | Task 13 |
| Task14.1 | Pack production equipment | 2 days | Mon 1/3/11 | Tue 1/4/11 | Task 13.3 | City Equipment Movers PM |
| Task14.2 | Pack non-production equipment | 2 days | Mon 1/3/11 | Tue 1/4/11 | Task 14.1 | City Equipment Movers |
| Task14.3 | Project Sign-off | 1 day | Mon 1/3/11 | Mon 1/3/11 | Task 14.2 | Project Manager |
| Task15 | Move | 3 days | Mon 1/3/11 | Wed 1/5/11 | Task 14 |
| Task15.1 | Move production equipment | 3 days | Mon 1/3/11 | Wed 1/5/11 | Task 14.2 | Express Moving Company PM |
| Task15.2 | Move non-production equipment | 3 days | Mon 1/3/11 | Wed 1/5/11 | Task 15.1 | Express Moving Company |
| Task15.3 | Project Sign-off | 1 day | Mon 1/3/11 | Mon 1/3/11 | Task 15.2 | Project Manager |
| Task16 | Procurement Closure | 3 days | Mon 1/3/11 | Wed 1/5/11 | Task 15 |
| Task16.1 | Review contract work | 3 days | Mon 1/3/11 | Wed 1/5/11 | Task 15.2 | Project Manager |
| Task16.2 | Release contractors | 1 day | Mon 1/3/11 | Mon 1/3/11 | Task 16.1 | Project Manager |
| Task16.3 | Pay contractors | 1 day | Mon 1/3/11 | Mon 1/3/11 | Task 16.2 | Project Manager |
| Task17 | Project Closure | 3 days | Mon 1/3/11 | Wed 1/5/11 | Task 16 |
| Task17.1 | Final report | 3 days | Mon 1/3/11 | Wed 1/5/11 | Task 16.2 | Project Manager |
| Task17.2 | Archive documentation | 3 days | Mon 1/3/11 | Wed 1/5/11 | Task 17.1 | Project Manager |
| Task17.3 | Lessons Learned | 1 day | Mon 1/3/11 | Mon 1/3/11 | Task 17.2 | Project Manager |