Module 4 Assignment 2 Project Schedule Change

profileBigieg
lasa_m3a2.xlsx

Sheet1

WBS Task Name Duration Start Finish Predecessors Resource Names
Task1 Project Kick-off 1 day Mon 1/3/11 Mon 1/3/11
Task 1.1 Book location for meeting 1 day Mon 1/3/11 Mon 1/3/11 Task 1 Project Manager
Task 1.2 Invite stakeholders 1 day Mon 1/3/11 Mon 1/3/11 Task 1.1 Project Manager
Task1.3 Prepare presentation 1 day Mon 1/3/11 Mon 1/3/11 Task 1.2 Project Manager
Task1.4 Conduct the meeting 1 day Mon 1/3/11 Mon 1/3/11 Task 1.3 Project Manager and Attendees
Task2 Project Documents 7 days Mon 1/3/11 Tue 1/11/11 Task 1
Task2.1 Develop Charter/Scope 2 days Mon 1/3/11 Tue 1/4/11 Task 1.3 Project Manager
Task2.2 Develop WBS 7 days Mon 1/3/11 Tue 1/11/11 Task 2.1 Project Manager and Workers
Task2.3 Develop Project Plan 2 days Mon 1/3/11 Tue 1/4/11 Task 2.2 Project Manager
Task2.4 Develop Communication Plan 2 days Mon 1/3/11 Tue 1/4/11 Task 2.3 Project Manager
Task3 Status Reports/Meetings 1 day Mon 1/3/11 Mon 1/3/11 Task 2
Task3.1 Develop Status Report 1 day Mon 1/3/11 Mon 1/3/11 Task 2.3 Project Manager
Task3.2 Set schedule for team meetings 1 day Mon 1/3/11 Mon 1/3/11 Task 3.1 Project Manager
Task3.3 Set schedule for stakeholder meetings 1 day Mon 1/3/11 Mon 1/3/11 Task 3.2 Project Manager
Task4 Initial Planning Meetings with Vendors 1 day Mon 1/3/11 Mon 1/3/11 Task 3
Task4.1 Meet with Framing/Drywall 1 day Mon 1/3/11 Mon 1/3/11 Task 3.2 Project Manager and East Side Framing PM
Task4.2 Meet with Electrical 1 day Mon 1/3/11 Mon 1/3/11 Task 4.1 Project Manager and Sparks Electrical PM
Task4.3 Meet with Plumbing 1 day Mon 1/3/11 Mon 1/3/11 Task 4.2 Project Manager and Waterworks Plumbing PM
Task4.4 Meet with Finish Work 1 day Mon 1/3/11 Mon 1/3/11 Task 4.3 Project Manager and Woodcraft Carpentry PM
Task4.5 Meet with Student Workers 1 day Tue 1/4/11 Tue 1/4/11 Task 4.4 Project Manager and Student Workers Manger
Task5 Electrical Permits 10 days Mon 1/3/11 Fri 1/14/11 Task 4
Task5.1 Obtain Electrical Permits 10 days Mon 1/3/11 Fri 1/14/11 Task 4.4 Sparks Electrical PM
Task6 Plumbing Permits 10 days Mon 1/3/11 Fri 1/14/11 Task 5
Task6.1 Obtain Plumbing Permits 10 days Mon 1/3/11 Fri 1/14/11 Task 5.1 Waterworks Plumbing PM
Task7 Building Permits 10 days Mon 1/3/11 Fri 1/14/11 Task 6
Task7.1 Obtain Building Permits 10 days Mon 1/3/11 Fri 1/14/11 Task 6.1 East Side Framing & Drywall PM
Task8 Framing 15 days Mon 1/3/11 Fri 1/21/11 Task 7
Task8.1 Framing-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11 Task 7.1 East Side Framing & Drywall PM
Task8.2 Framing-Build 15 days Mon 1/3/11 Fri 1/21/11 Task 8.1 East Side Framing & Drywall
Task8.3 Framing-Inspect 5 days Mon 1/3/11 Fri 1/7/11 Task 8.2 City & County
Task8.4 Framing-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Task 8.3 Project Manager
Task9 Electrical 10 days Mon 1/3/11 Fri 1/14/11 Task 8
Task9.1 Electrical-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11 Task 8.3 Sparks Electrical PM
Task9.2 Electrical-Install 10 days Mon 1/3/11 Fri 1/14/11 Task 9.1 Sparks Electrical
Task9.3 Electrical-Inspect 5 days Mon 1/3/11 Fri 1/7/11 Task 9.2 City & County
Task9.4 Electrical-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Task 9.3 Project Manager
Task10 Plumbing 10 days Mon 1/3/11 Fri 1/14/11 Task 9
Task10.1 Plumbing-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11 Task 9.3 Waterworks Plumbing PM
Task10.2 Plumbing-Install 10 days Mon 1/3/11 Fri 1/14/11 Task 10.1 Waterworks Plumbing
Task10.3 Plumbing-Inspect 5 days Mon 1/3/11 Fri 1/7/11 Task 10.2 City & County
Task10.4 Plumbing-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Task 10.3 Project Manager
Task11 Drywall 15 days Mon 1/3/11 Fri 1/21/11 Task 10
Task11.1 Drywall-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11 Task 10.3 East Side Framing & Drywall PM
Task11.2 Drywall-Install 15 days Mon 1/3/11 Fri 1/21/11 Task 11.1 East Side Framing & Drywall
Task11.3 Drywall-Inspect 5 days Mon 1/3/11 Fri 1/7/11 Task 11.2 City & County
Task11.4 Drywall-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Task 11.3 Project Manager
Task12 Finish Work 15 days Mon 1/3/11 Fri 1/21/11 Task 11
Task12.1 Finish-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11 Task 11.3 Woodcraft Carpentry PM
Task12.2 Finish-Install 15 days Mon 1/3/11 Fri 1/21/11 Task 12.1 Woodcraft Carpentry
Task12.3 Finish-Inspect 5 days Mon 1/3/11 Fri 1/7/11 Task 12.2 City & County
Task12.4 Finish-Project Sign-off 1 day Wed 1/3/11 Wed 1/5/11 Task 12.3 Project Manager
Task13 Workbenches 15 days Mon 1/3/11 Fri 1/21/11 Task 12
Task13.1 Workbenches-Order Supplies 2 days Mon 1/3/11 Tue 1/4/11 Task 12.3 Student Workers Manager
Task13.2 Workbenches-Build 15 days Mon 1/3/11 Fri 1/21/11 Task 13.1 Student Workers
Task13.3 Workbenches-Quality inspection 2 days Mon 1/3/11 Tue 1/4/11 Task 13.2 Project Manager
Task13.4 Workbenches-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Task 13.3 Project Manager
Task14 Equipment Packing 2 days Mon 1/3/11 Tue 1/4/11 Task 13
Task14.1 Pack production equipment 2 days Mon 1/3/11 Tue 1/4/11 Task 13.3 City Equipment Movers PM
Task14.2 Pack non-production equipment 2 days Mon 1/3/11 Tue 1/4/11 Task 14.1 City Equipment Movers
Task14.3 Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Task 14.2 Project Manager
Task15 Move 3 days Mon 1/3/11 Wed 1/5/11 Task 14
Task15.1 Move production equipment 3 days Mon 1/3/11 Wed 1/5/11 Task 14.2 Express Moving Company PM
Task15.2 Move non-production equipment 3 days Mon 1/3/11 Wed 1/5/11 Task 15.1 Express Moving Company
Task15.3 Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Task 15.2 Project Manager
Task16 Procurement Closure 3 days Mon 1/3/11 Wed 1/5/11 Task 15
Task16.1 Review contract work 3 days Mon 1/3/11 Wed 1/5/11 Task 15.2 Project Manager
Task16.2 Release contractors 1 day Mon 1/3/11 Mon 1/3/11 Task 16.1 Project Manager
Task16.3 Pay contractors 1 day Mon 1/3/11 Mon 1/3/11 Task 16.2 Project Manager
Task17 Project Closure 3 days Mon 1/3/11 Wed 1/5/11 Task 16
Task17.1 Final report 3 days Mon 1/3/11 Wed 1/5/11 Task 16.2 Project Manager
Task17.2 Archive documentation 3 days Mon 1/3/11 Wed 1/5/11 Task 17.1 Project Manager
Task17.3 Lessons Learned 1 day Mon 1/3/11 Mon 1/3/11 Task 17.2 Project Manager