see attached 777A1

profilejoeph2
copy_of_budget.xls

Sheet1

Starbuck process improvement budget
resources required and their narration
Item Description Unit of measure Quantity
business process analyst Meant to oversee the implementation of the entire project Persons 1
personal assistant Assisting the analyst with the scheduling of activities and correspondence Persons 1
Technicians Help in collecting and analyzing data Persons 2
Vehicle To assist in the transportation of team within the firm and from one Branch to anther vehicle 2
Stationery For recording data and information Number of books, pens and other stationery
Computer and presentation equipments Used for recording, analyzing and storing data as well as for presentation in training Number 4
Hotel Accommodating the process improvement team Rooms 4
Expenditure
items Quantity price
Analyst 1 1000 per day for 10 days $ 10,000.00
Personal assistant 1 600 per day $ 60,000.00
Technicians 2 500 per day $ 10,000.00
Vehicle 2 Leased for 100 a day $ 1,000.00
Fuelled at $50 $ 500.00
Stationery As will be used $ 50.00
Computers For each team member Already existing
Accommodation 4 rooms 300 $ 12,000.00
TOTAL $ 93,550.00
TRAINING
Refreshments For the employees a training the training sessions Estimate 30 employees a day each spending $10 $ 3,000.00
Training stationery $ 1,000.00
Total training $ 4,000.00
Miscellaneous To meet any emergency that may arise but was not foreseen as well as the wasted time $ 5,000.00
$ 5,000.00
TOTAL budget Expenditure $ 102,550.00