Risk Management Plan

Table of Contents

1 Executive Summary..........................................................................................................

1.1 Purpose...........................................................................................................................

2 Risk Management Strategy...............................................................................................

2.1 Risk Identification...........................................................................................................

2.2 Risk Responsibilities.......................................................................................................

2.3 Risk Assessment .............................................................................................................

2.4 Risk Response.................................................................................................................

2.5 Risk Mitigation ...............................................................................................................

2.6 Risk Contingency Planning.............................................................................................

2.7 Tracking and Reporting ..................................................................................................

2.8 Processes to Address Immediate Unforeseen Risks .......................................................

1 Executive Summary

Risk is defined as an event that has a probability of occurring, and could have either a positive or

negative impact to a project should that risk occur. A risk may have one or more causes and, if it

occurs, one or more impacts. For example, a cause may be requiring an environmental permit to

do work, or having limited personnel assigned to design the project. The risk event is that the

permitting agency may take longer than planned to issue a permit, or the assigned personnel

available and assigned may not be adequate for the activity. If either of these uncertain events

occurs, there may be an impact on the project cost, schedule or performance. All projects assume

some element of risk, and it’s through risk management where tools and techniques are applied

to monitor and track those events that have the potential to impact the outcome of a project.

Risk management is an ongoing process that continues through the life of a project. It includes

processes for risk management planning, identification, analysis, monitoring and control. Many

of these processes are updated throughout the project lifecycle as new risks can be identified at

any time. It’s the objective of risk management to decrease the probability and impact of events

adverse to the project. On the other hand, any event that could have a positive impact should be

exploited.

The identification of risk normally starts before the project is initiated, and the number of risks

increase as the project matures through the lifecycle. When a risk is identified, it’s first assessed

to ascertain the probability of occurring, the degree of impact to the schedule, scope, cost, and

quality, and then prioritized. Risk events may impact only one or while others may impact the

project in multiple impact categories. The probability of occurrence, number of categories

impacted and the degree (high, medium, low) to which they impact the project will be the basis

for assigning the risk priority. All identifiable risks should be entered into a risk register, and

documented as a risk statement.

As part of documenting a risk, two other important items need to be addressed.

The first is mitigation steps that can be taken to lessen the probability of the event occurring. The

second is a contingency plan, or a series of activities that should take place either prior to, or

when the event occurs. Mitigation actions frequently have a cost. Sometimes the cost of

mitigating the risk can exceed the cost of assuming the risk and incurring the consequences. It is

important to evaluate the probability and impact of each risk against the mitigation strategy cost

before deciding to implement a contingency plan. Contingency plans implemented prior to the

risk occurring are pre-emptive actions intended to reduce the impact or remove the risk in its

entirety. Contingency plans implemented after a risk occurs can usually only lessen the impact.

Identifying and documenting events that pose a risk to the outcome of a project is just the first

step. It is equally important to monitor all risks on a scheduled basis by a risk management team,

and reported on in the project status report.

1.1 Purpose

This plan documents the processes, tools and procedures that will be used to manage and control

those events that could have a negative impact on the Insert Project Name Here project. It’s the

controlling document for managing and controlling all project risks. This plan will address:

• Risk Identification

• Risk Assessment

• Risk Mitigation

• Risk Contingency Planning

• Risk Tracking and Reporting

Appendix A will present the risk impact assessment matrix and appendix B will present a sample

of the risk register.

2 Risk Management Strategy

2.1 Risk Identification

A risk is any event that could prevent the project from progressing as planned, or from successful

completion. Risks can be identified from a number of different sources. Some may be quite

obvious and will be identified prior to project kickoff.

Others will be identified during the project lifecycle, and a risk can be identified by anyone

associated with the project. Some risk will be inherent to the project itself, while others will be

the result of external influences that are completely outside the control of the project team.

The Insert Project Name Here Project Manager has overall responsibility for managing project

risk. Project team members may be assigned specific areas of responsibility for reporting to the

project manager.

Throughout all phases of the project, a specific topic of discussion will be risk identification. The

intent is to instruct the project team in the need for risk awareness, identification, documentation

and communication.

Risk awareness requires that every project team member be aware of what constitutes a risk to

the project, and being sensitive to specific events or factors that could potentially impact the

project in a positive or negative way.

Risk identification consists of determining which risks are likely to affect the project and

documenting the characteristics of each.

Risk communication involves bringing risk factors or events to the attention of the project

manager and project team.

The Insert Project Name Here project manager will identify and document known risk factors

during creation of the Risk Register.

It is the Insert Project Name Here project manager’s responsibility to assist the project team

and other stakeholders with risk identification, and to document the known and potential risks in

the Risk Register. Updates to the risk register will occur as risk factors change. Risk

management will be a topic of discussion during the regularly scheduled project meetings.

The Insert Project Name Here project team will discuss any new risk factors or events, and these

will be reviewed with the Insert Project Name Here project manager.

The project manager will determine if any of the newly identified risk factors or events warrant

further evaluation. Those that do will undergo risk quantification and risk response development,

as appropriate, and the action item will be closed.

At any time during the project, any risk factors or events should be brought to the attention of the

Insert Project Name Here project manager using Email or some other form of written

communication to document the item. The project manager is responsible for logging the risk to

the Risk Register. Notification of a new risk should include the following Risk Register

elements:

• Description of the risk factor or event, e.g. conflicting project or operational initiatives that

place demands on project resources, unexpected study outcomes, delays, etc.

• Probability that the event will occur. For example, a 50% chance that the vendor will not have

an animal colony that meets the criteria available.

• Schedule Impact. The number of hours, days, week, or months that a risk factor could impact

the schedule. As an example, the animals require an additional 3 months to meet age

requirements.

• Scope Impact. The impact the risk will have on the envisioned accomplishments of the project.

Delayed animal delivery may result in a reduction in the number of studies that can be completed

within the contract period of performance.

• Quality Impact. A risk event may result in a reduction in the quality of work or products that

are developed. As an example, lack of funding caused by cost overruns may result in the

reduction of the study size and impact statistical empowerment

• Cost Impact. The impact the risk event, if it occurs is likely to have onthe project budget.

2.2 Risk Responsibilities

The responsibility for managing risk is shared amongst all the stakeholders of the project.

However, decision authority for selecting whether to proceed with mitigation strategies and

implement contingency actions, especially those that have an associated cost or resource

requirement rest with the Project Manager who is responsible for informing the funding agency

to determine the requirement for a contract modification. The following tables details specific

responsibilities for the different aspects of risk management.

Risk Activity Responsibility

Risk Identification: All project stakeholders

Risk Registry: Project Manager

Risk Assessment: All project stakeholders

Risk Response Options Identification: All project stakeholders

Risk Response Approval: PM with concurrence from CO/PO/COTR

Risk Contingency Planning; Project Manager(s)

Risk Response Management; Project Managers

Risk Reporting; Project Manager

2.3 Risk Assessment

Risk assessment is the act of determining the probability that a risk will occur and the impact that

event would have, should it occur. This is basically a “cause and effect” analysis. The “cause” is

the event that might occur, while the “effect” is the potential impact to a project, should the event

occur.

Assessment of a risk involves two factors. First is the probability which is the measure of

certainty that an event, or risk, will occur. This can be measured in a number of ways, but for the

Insert Project Name Here project will be assigned a probability as defined in the table below.

Probability of Occurrences

DefinitionMeaningValue

• Occurs frequently

5

Frequent• Will be continuously experienced unless

Likely

Occasional

Seldom

Improbable

action is taken to change events

Occur less frequently if process is corrected

Issues identified with minimal audit activity

Process performance failures evident to

trained auditors or regulators

Occurs sporadically

Potential issues discovered during focused

review.

Unlikely to occur

Minimal issue identification during focused

review

Highly unlikely to occur

4

3

2

1

The second factor is estimate of the impact on the project. This can be a somewhat subjective

assessment, but should be quantified whenever possible. The estimated cost, the duration of the

potential delay, the changes in scope and the reduction in quality are in most cases factors that

can be estimated and documented in the risk statement and then measured using the standard

project management tools (i.e. project plan, budget, statements of work). Rather than detailed

impact estimates the Risk Register contains five ratings for impact;

Catastrophic (A)

Regulatory/Compliance violations/issues

Inability to validate data

Withdrawal of product manufacturer

Tainted product

Materials breech

Production delays

Technical miscommunications

Security/confidentiality breeches

Critical (B)

A non-compliance finding resulting in process, or operational degradation

A security finding requiring immediate corrective action prior to continued operation

Reoccurring violation of any safety regulation resulting in serious injury

Production errors containing regulatory violations that pose direct consequence to the operation

Moderate (C)

Security finding requiring a Corrective Action Plan

Production element errors that may pose indirect consequences to the operation

Minor (D)

No regulatory action anticipated

No compliance impact anticipated

No evident security threat affected

Minor errors in completed Company policy & procedures

Production errors containing quality system and / or opportunities for improvement

Negligible (E)

No regulatory/compliance violation

No security/confidentiality element affected

On time production

Validated experiments

“Clean” product

Properly executed communications

For each of the impact categories the impact assessment should include consideration of the

following areas of impact also:

• Cost – This impact is usually estimated as a dollar amount that has a direct impact to the

project. However, cost is sometimes estimated and reported as simply additional resources,

equipment, etc. This is true whenever these additional resources will not result in a direct

financial impact to the project due to the fact the resources are loaned or volunteer, the

equipment is currently idle and there is no cost of use, or there are other types of donations that

won’t impact the project budget. Regardless of whether there is a direct cost, the additional

resources should be documented in the risk statement as part of the mitigation cost.

• Scope – Whenever there is the potential that the final product will not be completed as

originally envisioned there is a scope impact. Scope impact could be measured as a reduction of

the number of studies completed, or not providing a deliverable such as an IND.

• Schedule – It is very important to estimate the schedule impact of a risk event as this often

results is the basis for elevating the other impact categories. Schedule delays frequently result in

cost increases and may result in a reduction of scope or quality. Schedule delays may or may not

impact the critical path of the project and an associated push out of the final end date.

• Performance/Quality – Performance/Quality is frequently overlooked as an impact category

and too often a reduction in quality is the preferred choice for mitigation of a risk. “Short cuts”

and “low cost replacements” are ways of reducing cost impacts. If not documented appropriately

and approved by the project sponsor, mitigation strategies that rely upon a reduction in quality

can result in significant disappointment by the stakeholders.

Most risks will be assigned one category, but some might be assigned more than one, or all.

2.4 Risk Response

For each identified risk, a response must be identified. It is the responsibility of the project team

to select a risk response for each risk. The project team will need the best possible assessment of

the risk and description of the response options in order to select the right response for each risk.

The probability of the risk event occurring and the impacts will be the basis for determining the

degree to which the actions to mitigate the risk should be taken. One way of evaluating

mitigation strategies is to multiply the risk cost times the probability of occurrence. Mitigation

strategies that cost less than risk probability calculation should be given serious consideration.

The possible response options are:

• Avoidance – Change the project to avoid the risk. Change scope, objectives, etc.

• Transference – Shift the impact of a risk to a third party (like a subcontractor). It does not

eliminate it, it simply shifts responsibility.

• Mitigation – Take steps to reduce the probability and/or impact of a risk. Taking early action,

close monitoring, more testing, etc.

• Acceptance – Simply accept that this is a risk. When choosing acceptance as a response the

IMPD is stating that given the probability of occurring and the associated impact to the project

that results, they are not going to take any actions and will accept the cost, schedule, scope, and

quality impacts if the risk event occurs.

• Deferred – A determination of how to address this risk will be addressed at a later time. The

results of the risk assessment process are documented in each Risk Statement and summarized in

the Risk Register which will be reported on a monthly basis.

2.5 Risk Mitigation

Risk mitigation involves two steps:

• Identifying the various activities, or steps, to reduce the probability and/or impact of an adverse

risk.

• Creation of a Contingency Plan to deal with the risk should it occur.

Taking early steps to reduce the probability of an adverse risk occurring may be more effective

and less costly than repairing the damage after a risk has occurred. However, some risk

mitigation options may simply be too costly in time or money to consider.

Mitigation activities should be documented in the Risk Register, and reviewed on a regular basis.

They include:

• Identification of potential failure points for each risk mitigation solution.

• For each failure point, document the event that would raise a “flag” indicating that the event or

factor has occurred or reached a critical condition.

• For each failure point, provide alternatives for correcting the failure.

2.6 Risk Contingency Planning

Contingency planning is the act of preparing a plan, or a series of activities, should an adverse

risk occur. Having a contingency plan in place forces the project team to think in advance as to a

course of action if a risk event takes place.

• Identify the contingency plan tasks (or steps) that can be performed to implement the mitigation

strategy.

• Identify the necessary resources such as money, equipment and labor.

• Develop a contingency plan schedule. Since the date the plan will be implemented is unknown,

this schedule will be in the format of day 1, day 2, day 3, etc., rather than containing specific

start and end dates.

• Define emergency notification and escalation procedures, if appropriate.

• Develop contingency plan training materials, if appropriate.

• Review and update contingency plans if necessary.

• Publish the plan(s) and distribute the plan(s) to management and those directly involved in

executing the plan(s).

Contingency may also be reflected in the project budget, as a line item to cover unexpected

expenses. The amount to budget for contingency may be limited to just the high probability risks.

This is normally determined by estimating the cost if a risk occurs, and multiplying it by the

probability. For example, assume a risk is estimated to result in an additional cost of $50,000,

and the probability of occurring is 80%. The amount that should be included in the budget for

this one item is $40,000.

Associated with a contingency plan, are start triggers and stop triggers. A start trigger is an event

that would activate the contingency plan, while a stop trigger is the criteria to resume normal

operations. Both should be identified in the Risk Register and can be embedded, example; the

stop trigger can be included in the contingency plan field.

2.7 Tracking and Reporting

As project activities are conducted and completed, risk factors and events will be monitored to

determine if in fact trigger events have occurred that would indicate the risk is now a reality.

Based on trigger events that have been documented during the risk analysis and mitigation

processes, the project team or project managers will have the authority to enact contingency

plans as deemed appropriate. Day to day risk mitigation activities will be enacted and directed by

the project managers.

Contingency plans that once approved and initiated will be added to the project work plan and be

tracked and reported along with all of the other project activities.

Risk management is an ongoing activity that will continue throughout the life of the project. This

process includes continued activities of risk identification, risk assessment, planning for newly

identified risks, monitoring trigger conditions and contingency plans, and risk reporting on a

regular basis. Project status reporting contains a section on risk management, where new risks

are presented along with any status changes of existing risks. Some risk attributes, such as

probability and impact, could change during the life of a project and this should be reported as

well.

2.8 Processes to Address Immediate Unforeseen Risks

The individual identifying the risk will immediately notify the project managers. The individual

notified will assess the risk situation.

If required, the project managers will identify a mitigating strategy, and assign resources as

necessary.

The project risk manager will document the risk factor and the mitigating strategy.

Appendix A – Example Risk Assessment Matrix

Probability of OccurrencesCatastrophic

DefinitionMeaningValue(A)

• Occurs

5

frequently

Will be

continuously

experienced

unless

action is

taken to

change

events

Occur less

frequently if

process is

corrected

Issues

identified

with minimal

audit activity

Process

performance

failures

evident to

trained

auditors or

regulators

Occurs

sporadically

Potential

issues

discovered

during

focused

review.

Unlikely to

occur

Minimal

issue

identification

during

focused

review

Highly

unlikely to

occur

Critical

(B)

Moderate Minor Negligible

(C)(D)(E)

Frequent

5A

5B

5C

5D

5E

4

Likely

4A

4B

4C

4D

4E

3

3A

3B

3C

3D

3E

Occasional

2

2A

2B

2C

2D

2E

Seldom

Improbable

1

1A

1B

1C

1D

1E

Risk Levels:

Risk is High for codes 5A, 5B, 5C, 4A, 4B, 3A

Risk is Medium High for codes 5D, 5E, 4C, 3B, 3C, 2A, 2B

Risk is Medium Low for codes 4D, 4E, 3D, 2C, 1A, 1B

Risk is Low for codes 3E, 2D, 2E, 1C, 1D, 1E

Appendix B – Example Risk Register

Risk Register for "Generic Vaccine"

Gantt

WBS

Risk

Overall Impact

Mitigation

Contingency

FDA does not agree with the

characterization results (non-clinical

and clinical studies planned, example

Occasional +if FDA requires NHP instead of used

Moderate = 3Canimal model)

CSP Impact

Additional

$400,000 for NHP

Model Study

Timing / Option

30 1.3.2.4

Lab unable to produce an adequate

amount of product to conduct all

studies that are currently scheduled

Contract negotiations failure

Manufacturing failure

Contract negotiations failure with

cGMP facility

Tech Transfer failure (lack of detailed

information)

Study Task 2 (subtask studies task

lines 37 and 38) could yield negative

results, not meet success criteria

Study Task 1 (subtask studies task

lines 45 and 46) could yield negative

results, not meet success criteria

Study Task 3 (subtask studies task

lines 52, 53, 54, and 55) could yield

negative results, not meet success

criteria

Update program design with FDA

input, modify SOW, obtain BARDA

Early and frequent meetings with the CO, PO, and Management Approval of Addition of ~9

FDA prior to study execution.new SOW, and provide budget request months

1. Slow the pace of the studies to

accommodate the production

Subcontract negotiations with CMO to availability

produce product for use in non-clinical 2. Use available lab product until CRO

studies.cGMP product is available

1. Use available lab product and

schedule studies based on available

product.

2. Transition financial resources from

subcontract to expansion of lab for

production.

Subcontract negotiations with CMO to 3. Transition financial resources to

produce non-GMP product for use inexpedite the execution of the cGMP

non-clinical studies.subcontract.

1. Second manufacturing attempt

2. Discontinue contract and use lab

product

Complete technical package and3. Discontinue contract and expedite

assistance available from lab.the cGMP manufacturing contract.

Early RFP for evaluation of multiple

Alternate facility RFPCMO facilities

Completion of detailed manufacturing Manufacturing process development,

technical transfer package and SME testing, optimization and validation

provisions during pilot lot preparations requirement

Preliminary studies conducted with

positive results

Preliminary studies conducted with

positive results

Alternate study design and potential

product redesign

Alternate study design and potential

product redesign

Q3, FY11 - BASE

Preliminary studies conducted with

positive results

Alternate study design and potential

product redesign