project management
13.2 INFORMATION
For purposes of this exercise we will use the Digital Camera project, which was introduced in Chapter 13. In this scenario the project started as planned on March 1 and today's date is March 7. We have received the following information on the work completed to date:
Design Spec.s took 2 days to complete at a total cost of $20.
Shell & Power took 3 days to complete at a total cost of $25.
Memory/Software is in progress with 4 days completed and two days remaining.
Cost to date is $100.
Zoom System took 2 days to complete at a cost of $25.
All tasks started on time.
STEP 1 ENTERING PROGRESS INFORMATION
We enter this progress information in the TRACKING TABLE from the GANTT CHART VIEW image VIEW image TABLES image TRACKING:
Note that the software automatically calculates the percent complete and actual finish, cost, and work. In some cases you will have to override these calculations if they are inconsistent with what actually happened. Be sure to check to make sure the information in this table is displayed the way you want it to be.
The final step is to enter the current status date (March 7). You do so by clicking PROJECT image PROJECT INFORMATION and inserting the date into the status date window.
STEP 2 ACCESSING PROGRESS INFORMATION
MS Project provides a number of different options for obtaining progress information. The most basic information can be obtained from PROJECT image REPORTS image COSTS image EARNED VALUE. You can also obtain this information from GANTT CHART view. Click VIEW image TABLE image MORE TABLES image EARNED VALUE.
TABLE A13.2B Earned Value Table
When you scale this table to 80 percent you can obtain all the basic CV, SV and VAC information on one convenient page.
Note: Older versions of MS Project use the old acronyms:
BCWS = PV
BCWP = EV
ACWP = AC
and the EAC is calculated using the CPI and is what the text refers to as EACf.
STEP 3 ACCESSING CPI INFORMATION
To obtain additional cost information such as CPI and TCPI click from the GANTT CHART view click VIEW image TABLE image MORE TABLES image EARNED VALUE COST INDICATORS, which will display the following information:
STEP 4 ACCESSING SPI INFORMATION
To obtain additional schedule information such as SPI from the GANTT CHART view, click VIEW image TABLE image MORE TABLES image EARNED VALUE SCHEDULE INDICATORS, which will display the following information:
STEP 5 CREATING A TRACKING GANTT CHART
You can create a Tracking Gantt Chart like the one presented on page 460 by simply clicking TASK image GANTT CHART (upper left hand corner) image TRACKING GANTT image TRACKING GANTT.