Finance Question - Multiple Choice Quiz
|
Question #2 (1 point) |
|
|
Which of the following is considered an advantage of the IRR method of capital budget analysis? |
|
|
|
the IRR method always works; it always gives the correct answer |
|
|
all of the above |
|
|
assumes cash flows are reinvested at the firm's cost of capital rate |
|
|
recognizes the time value of money |
|
Question #3 (1 point) |
|
|
In most capital budgeting decisions, the emphasis is on reported income, rather than cash flow. |
|
|
|
False |
|
|
True |
|
Question #4 (1 point) |
|
|
As the time horizon for an investment becomes longer, the forecasted standard deviation for the investment remains constant while the expected value increase for each forecast of cash flow. |
|
|
|
True |
|
|
False |
|
Question #5 (1 point) |
|
|
Five investment alternatives have the following returns and standard deviations of returns. Investment A, Expected Return = 1200, Standard Deviation = 300 Investment B, Expected Return = 1600, Standard Deviation = 1040 Investment C, Expected Return = 6000, Standard Deviation = 540 Investment D, Expected Return = 1000, Standard Deviation = 860 Investment E, Expected Return = 60000, Standard Deviation = 13200 Using the coefficient of variation, rank the five alternatives from lowest risk to highest risk. |
|
|
|
A C D B E |
|
|
C E A B D |
|
|
D B A E C |
|
|
E B D C A |
|
Question #6 (1 point) |
|
|
Ian Systems will invest $80,000 in a temporary project that will generate $20,000 at the end of the first year, $35,000 at the end of the second year, and $50,000 at the end of the third year. The firm will be required to spend $10,000 to close down the project at the end of three years. If the cost of capital is 10%, find what is the net present value of the project and should the investment be undertaken? |
|
|
|
$84,673 the project should not be undertaken |
|
|
$77,160 the project should be undertaken |
|
|
$77,160 the project should not be undertaken |
|
|
$84,673 the project should be undertaken |
|
Question #7 (1 point) |
|
|
There is a direct, and financially significant, mathematical relationship between the NPV and IRR of any capital project. |
|
|
|
False |
|
|
True |
|
Question #8 (1 point) |
|
|
You buy a new piece of equipment for $14,250, and you receive a cash inflow of $3,000 per year for 8 years. What is the internal rate of return? |
|
|
|
11.1% |
|
|
13.3% |
|
|
12.2% |
|
|
10.0% |
|
Question #9 (1 point) |
|
|
All of the following are disadvantages of the payback period method of capital budget analysis except |
|
|
|
has a minimum acceptable payback period that is arbitrary |
|
|
it ignores the time value of money |
|
|
it is very complex and difficult to use, understand, and explain |
|
|
ignores any cash flows after payback |
|
Question #10 (1 point) |
|
|
Stephenville Hardware has earnings before depreciation and taxes of $250,000, depreciation of $90,000, and a tax rate of 40 percent. Compute its cash flow. |
|
|
|
$186,000 |
|
|
$96,000 |
|
|
$240,000 |
|
|
$224,000 |
|
Question #11 (1 point) |
|
|
A basic assumption in financial theory is that most investors and managers are risk seeking- that is, for a given situation they would prefer uncertainty to certainty. |
|
|
|
True |
|
|
False |
|
Question #12 (1 point) |
|
|
Overall risk can be reduced by combining risky assets with low or negatively correlated assets. |
|
|
|
False |
|
|
True |
|
Question #13 (1 point) |
|
|
Conflicting rankings from the NPV and IRR techniques may result from differences in the reinvestment rate assumption. |
|
|
|
False |
|
|
True |
|
Question #14 (1 point) |
|
|
LVM Enterprises is considering investing $6,000 in a project that will result in annual cash flows of $1,600 for the next 6 years. What is the payback period for this project? |
|
|
|
4.25 years |
|
|
3.75 years |
|
|
2.75 years |
|
|
3.25 years |
|
Question #15 (1 point) |
|
|
Capital budget decisions by their nature are |
|
|
|
strategic investments in the future of the firm |
|
|
investments that have outcomes that normally are not known for years |
|
|
investments made in the uncertain expectation of increasing the value of the firm |
|
|
all of the above |
|
Question #16 (1 point) |
|
|
Stocks with betas of less than 1.0 are less risky than the market, while stocks with betas greater than 1.0 are more risky than the market. |
|
|
|
True |
|
|
False |