itp-4_project_resources_and_costs.xlsx

Team_PMIP

WBS Task Labor Labor Cost Supplies Supplies Cost Duration Start Date Finish Date Total Cost
1 Marley Dental Clinic IT System 117 days October 23, 2015 8:00 AM April 4, 2016 5:00 PM $158,201.65
1.1 Project Initiation/Planning 9.25 days October 23, 2015 8:00 AM November 5, 2015 10:00 AM $6,306.67
1.1.1 Requirements Gathering 5 days October 23, 2015 8:00 AM October 29, 2015 5:00 PM $1,920.00
1.1.1.1 Current process for scheduling Research Manager[50%],Documentation Manager[50%] $240.00 1 day October 26, 2015 8:00 AM October 26, 2015 5:00 PM $240.00
Documentation Manager Documentation Manager $120.00 Mon 10/26/15 Mon 10/26/15 $120.00
Research Manager Research Manager $120.00 Mon 10/26/15 Mon 10/26/15 $120.00
1.1.1.2 Current process for patient records Research Manager[50%],Documentation Manager[50%] $240.00 1 day October 27, 2015 8:00 AM October 27, 2015 5:00 PM $240.00
Documentation Manager Documentation Manager $120.00 Tue 10/27/15 Tue 10/27/15 $120.00
Research Manager Research Manager $120.00 Tue 10/27/15 Tue 10/27/15 $120.00
1.1.1.3 Current process for accounts payables Research Manager[50%],Documentation Manager[50%] $240.00 1 day October 28, 2015 8:00 AM October 28, 2015 5:00 PM $240.00
Documentation Manager Documentation Manager $120.00 Wed 10/28/15 Wed 10/28/15 $120.00
Research Manager Research Manager $120.00 Wed 10/28/15 Wed 10/28/15 $120.00
1.1.1.4 Current process for accounts receivables Research Manager[50%],Documentation Manager[50%] $240.00 1 day October 28, 2015 8:00 AM October 28, 2015 5:00 PM $240.00
Documentation Manager Documentation Manager $120.00 Wed 10/28/15 Wed 10/28/15 $120.00
Research Manager Research Manager $120.00 Wed 10/28/15 Wed 10/28/15 $120.00
1.1.1.5 Current process for dental claims Research Manager,Documentation Manager $480.00 1 day October 29, 2015 8:00 AM October 29, 2015 5:00 PM $480.00
Documentation Manager Documentation Manager $240.00 Thu 10/29/15 Thu 10/29/15 $240.00
Research Manager Research Manager $240.00 Thu 10/29/15 Thu 10/29/15 $240.00
1.1.1.6 Current process for patient billing Research Manager,Documentation Manager $480.00 1 day October 23, 2015 8:00 AM October 23, 2015 5:00 PM $480.00
Documentation Manager Documentation Manager $240.00 Fri 10/23/15 Fri 10/23/15 $240.00
Research Manager Research Manager $240.00 Fri 10/23/15 Fri 10/23/15 $240.00
1.1.2 Project Plan $2,100.00 6 days October 26, 2015 8:00 AM November 2, 2015 5:00 PM $2,100.00
1.1.2.1 Develop Project Manager[50%] $2,000.00 5 days October 26, 2015 8:00 AM October 30, 2015 5:00 PM $2,000.00
Project Manager Project Manager $2,000.00 Mon 10/26/15 Fri 10/30/15 $2,000.00
1.1.2.2 Project Plan Milestone Review Project Manager[13%],Sponsor[13%] $100.00 1 day November 2, 2015 8:00 AM November 2, 2015 5:00 PM $100.00
Sponsor Sponsor $50.00 Mon 11/2/15 Mon 11/2/15 $50.00
Project Manager Project Manager $50.00 Mon 11/2/15 Mon 11/2/15 $50.00
1.1.3 Project Charter $1,566.67 5.25 days October 26, 2015 8:00 AM November 2, 2015 10:00 AM $1,566.67
1.1.3.1 Develop Sponsor[25%],Technical Writer & Engineer[25%],Editor[25%] $1,466.67 5 days October 26, 2015 8:00 AM October 30, 2015 5:00 PM $1,466.67
Sponsor Sponsor $666.67 Mon 10/26/15 Fri 10/30/15 $666.67
Technical Writer & Engineer Technical Writer & Engineer $400.00 Mon 10/26/15 Fri 10/30/15 $400.00
Editor Editor $400.00 Mon 10/26/15 Fri 10/30/15 $400.00
1.1.3.2 Project Charter Milestone Review Sponsor $100.00 0.25 days November 2, 2015 8:00 AM November 2, 2015 10:00 AM $100.00
Sponsor Sponsor $100.00 Mon 11/2/15 Mon 11/2/15 $100.00
1.1.4 Document Business Model Documentation Manager[33%],Technical Writer & Engineer[33%],Editor[33%] $720.00 3 days November 2, 2015 10:00 AM November 5, 2015 10:00 AM $720.00
Documentation Manager Documentation Manager $240.00 Mon 11/2/15 Thu 11/5/15 $240.00
Technical Writer & Engineer Technical Writer & Engineer $240.00 Mon 11/2/15 Thu 11/5/15 $240.00
Editor Editor $240.00 Mon 11/2/15 Thu 11/5/15 $240.00
1.2 Management $5,526.61 111 days November 2, 2015 8:00 AM April 4, 2016 5:00 PM $5,526.61
1.2.1 Project Management $436.61 111 days November 2, 2015 8:00 AM April 4, 2016 5:00 PM $436.61
1.2.1.1 Monitor progress $436.61 111 days November 2, 2015 8:00 AM April 4, 2016 5:00 PM $436.61
1.2.1.1.1 Weekly Project Review Meetings $0.00 111 days November 2, 2015 8:00 AM April 4, 2016 5:00 PM $0.00
1.2.1.1.1.1 Weekly Project Review Meetings 1 $0.00 1 day November 5, 2015 10:00 AM November 6, 2015 10:00 AM $0.00
1.2.1.1.1.2 Weekly Project Review Meetings 2 $0.00 1 day November 2, 2015 8:00 AM November 2, 2015 5:00 PM $0.00
1.2.1.1.1.3 Weekly Project Review Meetings 3 $0.00 1 day November 9, 2015 8:00 AM November 9, 2015 5:00 PM $0.00
1.2.1.1.1.4 Weekly Project Review Meetings 4 $0.00 1 day November 16, 2015 8:00 AM November 16, 2015 5:00 PM $0.00
1.2.1.1.1.5 Weekly Project Review Meetings 5 $0.00 1 day November 23, 2015 8:00 AM November 23, 2015 5:00 PM $0.00
1.2.1.1.1.6 Weekly Project Review Meetings 6 $0.00 1 day November 30, 2015 8:00 AM November 30, 2015 5:00 PM $0.00
1.2.1.1.1.7 Weekly Project Review Meetings 7 $0.00 1 day December 7, 2015 8:00 AM December 7, 2015 5:00 PM $0.00
1.2.1.1.1.8 Weekly Project Review Meetings 8 $0.00 1 day December 14, 2015 8:00 AM December 14, 2015 5:00 PM $0.00
1.2.1.1.1.9 Weekly Project Review Meetings 9 $0.00 1 day December 21, 2015 8:00 AM December 21, 2015 5:00 PM $0.00
1.2.1.1.1.10 Weekly Project Review Meetings 10 $0.00 1 day December 28, 2015 8:00 AM December 28, 2015 5:00 PM $0.00
1.2.1.1.1.11 Weekly Project Review Meetings 11 $0.00 1 day January 4, 2016 8:00 AM January 4, 2016 5:00 PM $0.00
1.2.1.1.1.12 Weekly Project Review Meetings 12 $0.00 1 day January 11, 2016 8:00 AM January 11, 2016 5:00 PM $0.00
1.2.1.1.1.13 Weekly Project Review Meetings 13 $0.00 1 day January 18, 2016 8:00 AM January 18, 2016 5:00 PM $0.00
1.2.1.1.1.14 Weekly Project Review Meetings 14 $0.00 1 day January 25, 2016 8:00 AM January 25, 2016 5:00 PM $0.00
1.2.1.1.1.15 Weekly Project Review Meetings 15 $0.00 1 day February 1, 2016 8:00 AM February 1, 2016 5:00 PM $0.00
1.2.1.1.1.16 Weekly Project Review Meetings 16 $0.00 1 day February 8, 2016 8:00 AM February 8, 2016 5:00 PM $0.00
1.2.1.1.1.17 Weekly Project Review Meetings 17 $0.00 1 day February 15, 2016 8:00 AM February 15, 2016 5:00 PM $0.00
1.2.1.1.1.18 Weekly Project Review Meetings 18 $0.00 1 day February 22, 2016 8:00 AM February 22, 2016 5:00 PM $0.00
1.2.1.1.1.19 Weekly Project Review Meetings 19 $0.00 1 day February 29, 2016 8:00 AM February 29, 2016 5:00 PM $0.00
1.2.1.1.1.20 Weekly Project Review Meetings 20 $0.00 1 day March 7, 2016 8:00 AM March 7, 2016 5:00 PM $0.00
1.2.1.1.1.21 Weekly Project Review Meetings 21 $0.00 1 day March 14, 2016 8:00 AM March 14, 2016 5:00 PM $0.00
1.2.1.1.1.22 Weekly Project Review Meetings 22 $0.00 1 day March 21, 2016 8:00 AM March 21, 2016 5:00 PM $0.00
1.2.1.1.1.23 Weekly Project Review Meetings 23 $0.00 1 day March 28, 2016 8:00 AM March 28, 2016 5:00 PM $0.00
1.2.1.1.1.24 Weekly Project Review Meetings 24 $0.00 1 day April 4, 2016 8:00 AM April 4, 2016 5:00 PM $0.00
1.2.1.1.2 Weekly Contractor Meeting $436.61 35.13 days November 17, 2015 8:00 AM January 5, 2016 9:00 AM $436.61
1.2.1.1.2.1 Weekly Contractor Meeting 1 Vendor Manager,Network Cabling Contractor $50.86 1 hr November 17, 2015 8:00 AM November 17, 2015 9:00 AM $50.86
Vendor Manager Vendor Manager $30.00 Tue 11/17/15 Tue 11/17/15 $30.00
Network Cabling Contractor Network Cabling Contractor $20.86 Tue 11/17/15 Tue 11/17/15 $20.86
1.2.1.1.2.2 Weekly Contractor Meeting 2 Vendor Manager,Network Cabling Contractor $50.86 1 hr November 24, 2015 8:00 AM November 24, 2015 9:00 AM $50.86
Vendor Manager Vendor Manager $30.00 Tue 11/24/15 Tue 11/24/15 $30.00
Network Cabling Contractor Network Cabling Contractor $20.86 Tue 11/24/15 Tue 11/24/15 $20.86
1.2.1.1.2.3 Weekly Contractor Meeting 3 Vendor Manager,Network Cabling Contractor $50.86 1 hr December 1, 2015 8:00 AM December 1, 2015 9:00 AM $50.86
Vendor Manager Vendor Manager $30.00 Tue 12/1/15 Tue 12/1/15 $30.00
Network Cabling Contractor Network Cabling Contractor $20.86 Tue 12/1/15 Tue 12/1/15 $20.86
1.2.1.1.2.4 Weekly Contractor Meeting 4 Vendor Manager,Network Cabling Contractor $50.86 1 hr December 8, 2015 8:00 AM December 8, 2015 9:00 AM $50.86
Vendor Manager Vendor Manager $30.00 Tue 12/8/15 Tue 12/8/15 $30.00
Network Cabling Contractor Network Cabling Contractor $20.86 Tue 12/8/15 Tue 12/8/15 $20.86
1.2.1.1.2.5 Weekly Contractor Meeting 5 Vendor Manager,Network Cabling Contractor $50.86 1 hr December 15, 2015 8:00 AM December 15, 2015 9:00 AM $50.86
Vendor Manager Vendor Manager $30.00 Tue 12/15/15 Tue 12/15/15 $30.00
Network Cabling Contractor Network Cabling Contractor $20.86 Tue 12/15/15 Tue 12/15/15 $20.86
1.2.1.1.2.6 Weekly Contractor Meeting 6 Vendor Manager,HVAC Contractor $60.77 1 hr December 28, 2015 4:00 PM December 28, 2015 5:00 PM $60.77
Vendor Manager Vendor Manager $30.00 Mon 12/28/15 Mon 12/28/15 $30.00
HVAC Contractor HVAC Contractor $30.77 Mon 12/28/15 Mon 12/28/15 $30.77
1.2.1.1.2.7 Weekly Contractor Meeting 7 Vendor Manager,HVAC Contractor $60.77 1 hr December 29, 2015 8:00 AM December 29, 2015 9:00 AM $60.77
Vendor Manager Vendor Manager $30.00 Tue 12/29/15 Tue 12/29/15 $30.00
HVAC Contractor HVAC Contractor $30.77 Tue 12/29/15 Tue 12/29/15 $30.77
1.2.1.1.2.8 Weekly Contractor Meeting 8 Vendor Manager,HVAC Contractor $60.77 1 hr January 5, 2016 8:00 AM January 5, 2016 9:00 AM $60.77
Vendor Manager Vendor Manager $30.00 Tue 1/5/16 Tue 1/5/16 $30.00
HVAC Contractor HVAC Contractor $30.77 Tue 1/5/16 Tue 1/5/16 $30.77
1.2.2 Documentation Milestone Review 1 day November 5, 2015 10:00 AM November 6, 2015 10:00 AM $140.00
Paper Paper [500 Sheets] $50.00 Thu 11/5/15 Fri 11/6/15 $50.00
Pen Pen [25 Pens] $50.00 Thu 11/5/15 Fri 11/6/15 $50.00
Printer Ink Printer Ink $40.00 Thu 11/5/15 Fri 11/6/15 $40.00
1.3 Install Data/VoIP Network Cabling $18,624.56 56.13 days October 23, 2015 8:00 AM January 11, 2016 9:00 AM $18,624.56
1.3.1 Hire Network Technician Contractor Vendor Manager,Project Manager $640.00 2 days October 23, 2015 8:00 AM October 30, 2015 5:00 PM $640.00
Project Manager Project Manager $400.00 Fri 10/23/15 Fri 10/23/15 $400.00
Vendor Manager Vendor Manager $240.00 Fri 10/30/15 Fri 10/30/15 $240.00
1.3.2 Install Data/VoIP Network Cabling Network Cabling Contractor $4,902.93 29.38 days November 6, 2015 10:00 AM December 18, 2015 4:00 PM $6,812.64
CAT6 cable spool CAT6 cable spool [10 Spools] $700.00 Fri 11/6/15 Fri 12/18/15 $700.00
Punch Down Tool Punch Down Tool [2 Punches] $51.76 Fri 11/6/15 Fri 12/18/15 $51.76
Screwdriver Screwdriver [2 Screwdrivers] $22.24 Fri 11/6/15 Fri 12/18/15 $22.24
Termination Kit Termination Kit $14.99 Fri 11/6/15 Fri 12/18/15 $14.99
Laptop Laptop $1,109.00 Fri 11/6/15 Fri 12/18/15 $1,109.00
Network Console Cable Network Console Cable $12.55 Fri 11/6/15 Fri 12/18/15 $12.55
Network Cabling Contractor Network Cabling Contractor $4,902.10 Fri 11/6/15 Fri 12/18/15 $4,902.10
1.3.3 Complete Data/VoIP network cabling installation Network Cabling Contractor $0.00 0 days December 18, 2015 4:00 PM December 18, 2015 4:00 PM $0.00
Network Cabling Contractor Network Cabling Contractor $0.00 Fri 12/18/15 Fri 12/18/15 $0.00
1.3.4 Build IT equipment room $8,316.48 5 days December 18, 2015 4:00 PM December 25, 2015 4:00 PM $8,316.48
1.3.4.1 Identify server closet Infrastructure & Hardware Consultant[50%] $200.00 1 day December 18, 2015 4:00 PM December 21, 2015 4:00 PM $200.00
Infrastructure & Hardware Consultant Infrastructure & Hardware Consultant $200.00 Fri 12/18/15 Mon 12/21/15 $200.00
1.3.4.2 Design rack layout $8,116.48 4 days December 21, 2015 4:00 PM December 25, 2015 4:00 PM $8,116.48
1.3.4.2.1 Establish hot and cold isles Infrastructure & Hardware Consultant $400.00 1 day December 21, 2015 4:00 PM December 22, 2015 4:00 PM $400.00
Infrastructure & Hardware Consultant Infrastructure & Hardware Consultant $400.00 Mon 12/21/15 Tue 12/22/15 $400.00
1.3.4.2.2 Install raised floor Infrastructure & Hardware Consultant 2 days December 22, 2015 4:00 PM December 24, 2015 4:00 PM $5,670.45
Cable Raceways Cable Raceways [3 Trays] $370.95 Tue 12/22/15 Thu 12/24/15 $370.95
Raised Floor Tiles Raised Floor Tiles [50 Tiles] $4,499.50 Tue 12/22/15 Thu 12/24/15 $4,499.50
Infrastructure & Hardware Consultant Infrastructure & Hardware Consultant Tue 12/22/15 Thu 12/24/15 $800.00
1.3.4.2.3 Install server racks $2,046.03 1 day December 24, 2015 4:00 PM December 25, 2015 4:00 PM $2,046.03
Cisco Small Business 200 Series 48-port Switch Cisco Small Business 200 Series 48-port Switch $517.02 Thu 12/24/15 Fri 12/25/15 $517.02
Tripp Lite SRW26US 26U Wall Mount Rack Enclosure Tripp Lite SRW26US 26U Wall Mount Rack Enclosure $706.76 Thu 12/24/15 Fri 12/25/15 $706.76
Rack Power Whips Rack Power Whips [2 Whips] $397.98 Thu 12/24/15 Fri 12/25/15 $397.98
Power Cables Power Cables [3 Cables] $24.27 Thu 12/24/15 Fri 12/25/15 $24.27
Infrastructure & Hardware Consultant Infrastructure & Hardware Consultant $0.00 Thu 12/24/15 Fri 12/25/15 $400.00
1.3.4.3 Server Room Installation Complete $2,855.44 0 days December 25, 2015 4:00 PM December 25, 2015 4:00 PM $0.00
1.3.5 Install Environmental Controls $640.00 10.25 days December 25, 2015 4:00 PM January 11, 2016 9:00 AM $2,855.44
1.3.5.1 Hire HVAC sub contractor Vendor Manager,Project Manager $400.00 1 day December 25, 2015 4:00 PM December 28, 2015 4:00 PM $640.00
Project Manager Project Manager $240.00 Fri 12/25/15 Mon 12/28/15 $400.00
Vendor Manager Vendor Manager $492.32 Fri 12/25/15 Mon 12/28/15 $240.00
1.3.5.2 Perform HVAC capacity planning HVAC Contractor $492.32 2 days December 28, 2015 4:00 PM December 30, 2015 5:00 PM $492.32
HVAC Contractor HVAC Contractor $738.48 Mon 12/28/15 Wed 12/30/15 $492.32
1.3.5.3 Install additional HVAC units HVAC Contractor $738.48 3 days December 31, 2015 8:00 AM January 4, 2016 5:00 PM $738.48
HVAC Contractor HVAC Contractor $492.32 Thu 12/31/15 Mon 1/4/16 $738.48
1.3.5.4 Install cooling ducts and fans to cold isle HVAC Contractor $492.32 2 days January 5, 2016 9:00 AM January 7, 2016 9:00 AM $492.32
HVAC Contractor HVAC Contractor $492.32 Tue 1/5/16 Thu 1/7/16 $492.32
1.3.5.5 Install exhaust ducts and fans to hot isle HVAC Contractor $492.32 2 days January 7, 2016 9:00 AM January 11, 2016 9:00 AM $492.32
HVAC Contractor HVAC Contractor $0.00 Thu 1/7/16 Mon 1/11/16 $492.32
1.3.5.6 Complete installation of environmental controls HVAC Contractor $0.00 0 days January 11, 2016 9:00 AM January 11, 2016 9:00 AM $0.00
HVAC Contractor HVAC Contractor $41,544.05 Mon 1/11/16 Mon 1/11/16 $0.00
1.4 Equipment $30.00 36 days October 23, 2015 8:00 AM December 11, 2015 5:00 PM $41,544.05
1.4.1 Issue purchase order for new phone system Vendor Manager[13%] $30.00 1 day October 23, 2015 8:00 AM October 23, 2015 5:00 PM $30.00
Vendor Manager Vendor Manager $30.00 Fri 10/23/15 Fri 10/23/15 $30.00
1.4.2 Issue purchase order for new x-ray machines Vendor Manager[13%] $30.00 1 day October 26, 2015 8:00 AM October 26, 2015 5:00 PM $30.00
Vendor Manager Vendor Manager $240.00 Mon 10/26/15 Mon 10/26/15 $30.00
1.4.3 Expedite delivery Vendor Manager $240.00 1 day October 27, 2015 8:00 AM October 27, 2015 5:00 PM $240.00
Vendor Manager Vendor Manager $0.00 Tue 10/27/15 Tue 10/27/15 $240.00
1.4.4 Equipment Acquired $41,244.05 0 days October 27, 2015 5:00 PM October 27, 2015 5:00 PM $0.00
1.4.5 Aquire Hardware $480.00 33 days October 28, 2015 8:00 AM December 11, 2015 5:00 PM $41,244.05
1.4.5.1 Purchase Hardware Vendor Manager $480.00 2 days October 28, 2015 8:00 AM October 29, 2015 5:00 PM $480.00
Vendor Manager Vendor Manager $12,000.00 Wed 10/28/15 Thu 10/29/15 $480.00
1.4.5.2 Receive Hardware Infrastructure & Hardware Consultant $12,000.00 30 days October 30, 2015 8:00 AM December 10, 2015 5:00 PM $12,000.00
Infrastructure & Hardware Consultant Infrastructure & Hardware Consultant Fri 10/30/15 Thu 12/10/15 $12,000.00
1.4.5.3 Install Hardware 1 day December 11, 2015 8:00 AM December 11, 2015 5:00 PM $28,764.05
Gendex GXDP-300 Panorex Panoramix X-Ray Machine Gendex GXDP-300 Panorex Panoramix X-Ray Machine $19,900.00 Fri 12/11/15 Fri 12/11/15 $19,900.00
Cisco SPA 504G IP Phone Cisco SPA 504G IP Phone [5 Phones] $444.95 Fri 12/11/15 Fri 12/11/15 $444.95
Screwdriver Screwdriver $11.12 Fri 12/11/15 Fri 12/11/15 $11.12
Server Server $3,522.98 Fri 12/11/15 Fri 12/11/15 $3,522.98
Workstation Workstation [5 Workstations] $4,485.00 Fri 12/11/15 Fri 12/11/15 $4,485.00
Infrastructure & Hardware Consultant Infrastructure & Hardware Consultant $400.00 Fri 12/11/15 Fri 12/11/15 $400.00
1.5 Office furniture and supplies 5.13 days December 11, 2015 8:00 AM December 18, 2015 9:00 AM $5,445.75
1.5.1 Dental Chairs 5.13 days December 11, 2015 8:00 AM December 18, 2015 9:00 AM $5,445.75
1.5.1.1 Issue purchase order Vendor Manager $240.00 1 day December 11, 2015 8:00 AM December 11, 2015 5:00 PM $240.00
Vendor Manager Vendor Manager $240.00 Fri 12/11/15 Fri 12/11/15 $240.00
1.5.1.2 Receive dental chairs Vendor Manager $480.00 2 days December 15, 2015 9:00 AM December 17, 2015 9:00 AM $480.00
Vendor Manager Vendor Manager $480.00 Tue 12/15/15 Thu 12/17/15 $480.00
1.5.1.3 Setup chairs 1 day December 17, 2015 9:00 AM December 18, 2015 9:00 AM $4,725.75
DentalEZ E-3000 Patient Dental Chair DentalEZ E-3000 Patient Dental Chair $2,936.75 Thu 12/17/15 Fri 12/18/15 $2,936.75
Tech West 1-hp Liquid Ring Vacuum System (2 users) Tech West 1-hp Liquid Ring Vacuum System $1,789.00 Thu 12/17/15 Fri 12/18/15 $1,789.00
1.6 IT System(s) Build Project Manager $23,967.35 38 days October 23, 2015 8:00 AM December 15, 2015 5:00 PM $23,967.35
Project Manager Project Manager $15,200.00 Fri 10/23/15 Tue 12/15/15 $15,200.00
1.6.1 Deploy Software 2 days October 23, 2015 8:00 AM October 26, 2015 5:00 PM $7,567.35
Hiveage - Invoice System Hiveage - Invoice System $299.95 Fri 10/23/15 Mon 10/26/15 $299.95
Umbie Dental Care - Record System Umbie Dental Care - Record System $5,988.00 Fri 10/23/15 Mon 10/26/15 $5,988.00
Schedulicity - Scheduling System Schedulicity - Scheduling System $479.40 Fri 10/23/15 Mon 10/26/15 $479.40
Application & Software Consultant Application & Software Consultant $800.00 Fri 10/23/15 Mon 10/26/15 $800.00
1.6.2 Configure Software Application & Software Consultant[50%],Integration & Interface Consultatnt[50%] $800.00 2 days December 11, 2015 8:00 AM December 14, 2015 5:00 PM $800.00
Application & Software Consultant Application & Software Consultant $400.00 Fri 12/11/15 Mon 12/14/15 $400.00
Integration & Interface Consultatnt Integration & Interface Consultatnt $400.00 Fri 12/11/15 Mon 12/14/15 $400.00
1.6.3 Review System Configuration with Customers Integration & Interface Consultatnt $400.00 1 day December 15, 2015 8:00 AM December 15, 2015 5:00 PM $400.00
Integration & Interface Consultatnt Integration & Interface Consultatnt $400.00 Tue 12/15/15 Tue 12/15/15 $400.00
1.7 IT System(s) Testing Project Manager $4,746.67 6 days December 16, 2015 8:00 AM December 23, 2015 5:00 PM $4,746.67
Project Manager Project Manager $2,400.00 Wed 12/16/15 Wed 12/23/15 $2,400.00
1.7.1 Identify Testing Scenarios Application & Software Consultant[33%],Integration & Interface Consultatnt[33%],Technical Writer & Engineer[33%] $346.67 1 day December 16, 2015 8:00 AM December 16, 2015 5:00 PM $346.67
Technical Writer & Engineer Technical Writer & Engineer $80.00 Wed 12/16/15 Wed 12/16/15 $80.00
Application & Software Consultant Application & Software Consultant $133.33 Wed 12/16/15 Wed 12/16/15 $133.33
Integration & Interface Consultatnt Integration & Interface Consultatnt $133.33 Wed 12/16/15 Wed 12/16/15 $133.33
1.7.2 Identify Testing Requirements Application & Software Consultant[50%],Integration & Interface Consultatnt[50%] $400.00 1 day December 17, 2015 8:00 AM December 17, 2015 5:00 PM $400.00
Application & Software Consultant Application & Software Consultant $200.00 Thu 12/17/15 Thu 12/17/15 $200.00
Integration & Interface Consultatnt Integration & Interface Consultatnt $200.00 Thu 12/17/15 Thu 12/17/15 $200.00
1.7.3 Create Test Scripts Application & Software Consultant[50%],Integration & Interface Consultatnt[50%] $800.00 2 days December 18, 2015 8:00 AM December 21, 2015 5:00 PM $800.00
Application & Software Consultant Application & Software Consultant $400.00 Fri 12/18/15 Mon 12/21/15 $400.00
Integration & Interface Consultatnt Integration & Interface Consultatnt $400.00 Fri 12/18/15 Mon 12/21/15 $400.00
1.7.4 System Testing Application & Software Consultant[50%],Integration & Interface Consultatnt[50%] $400.00 1 day December 22, 2015 8:00 AM December 22, 2015 5:00 PM $400.00
Application & Software Consultant Application & Software Consultant $200.00 Tue 12/22/15 Tue 12/22/15 $200.00
Integration & Interface Consultatnt Integration & Interface Consultatnt $200.00 Tue 12/22/15 Tue 12/22/15 $200.00
1.7.5 System Testing Milestone Review Project Manager $400.00 1 day December 23, 2015 8:00 AM December 23, 2015 5:00 PM $400.00
Project Manager Project Manager $400.00 Wed 12/23/15 Wed 12/23/15 $400.00
1.7.6 Testing Complete $0.00 0 days December 22, 2015 5:00 PM December 22, 2015 5:00 PM $0.00
1.8 IT System(s) Training Project Manager $14,560.00 18 days December 23, 2015 8:00 AM January 15, 2016 5:00 PM $14,560.00
Project Manager Project Manager $7,200.00 Wed 12/23/15 Fri 1/15/16 $7,200.00
1.8.1 Identify End User Training Requirements Research Manager[50%],Documentation Manager[50%] $240.00 1 day December 23, 2015 8:00 AM December 23, 2015 5:00 PM $240.00
Documentation Manager Documentation Manager $120.00 Wed 12/23/15 Wed 12/23/15 $120.00
Research Manager Research Manager $120.00 Wed 12/23/15 Wed 12/23/15 $120.00
1.8.2 Create End User Training Plan Documentation Manager[67%],Technical Writer & Engineer[67%],Editor[67%] $480.00 1 day December 24, 2015 8:00 AM December 24, 2015 5:00 PM $480.00
Documentation Manager Documentation Manager $160.00 Thu 12/24/15 Thu 12/24/15 $160.00
Technical Writer & Engineer Technical Writer & Engineer $160.00 Thu 12/24/15 Thu 12/24/15 $160.00
Editor Editor $160.00 Thu 12/24/15 Thu 12/24/15 $160.00
1.8.3 Develop Training Materials Documentation Manager $640.00 1 day December 25, 2015 8:00 AM December 25, 2015 5:00 PM $640.00
Documentation Manager Documentation Manager $240.00 Fri 12/25/15 Fri 12/25/15 $240.00
1.8.3.1 Build Training Domain in IT System Application & Software Consultant $400.00 1 day December 25, 2015 8:00 AM December 25, 2015 5:00 PM $400.00
Application & Software Consultant Application & Software Consultant $400.00 Fri 12/25/15 Fri 12/25/15 $400.00
1.8.4 Train System Users Application & Software Consultant[50%],Integration & Interface Consultatnt[50%] $5,600.00 14 days December 28, 2015 8:00 AM January 14, 2016 5:00 PM $5,600.00
Application & Software Consultant Application & Software Consultant $2,800.00 Mon 12/28/15 Thu 1/14/16 $2,800.00
Integration & Interface Consultatnt Integration & Interface Consultatnt $2,800.00 Mon 12/28/15 Thu 1/14/16 $2,800.00
1.8.5 User Training Milestone Review Project Manager $400.00 1 day January 15, 2016 8:00 AM January 15, 2016 5:00 PM $400.00
Project Manager Project Manager $400.00 Fri 1/15/16 Fri 1/15/16 $400.00
1.9 Install Live System Project Manager $35,320.00 41 days January 18, 2016 8:00 AM March 14, 2016 5:00 PM $35,320.00
Project Manager Project Manager $16,400.00 Mon 1/18/16 Mon 3/14/16 $16,400.00
1.9.1 Create Conversion Plan Project Manager[25%],Documentation Manager[25%],Technical Writer & Engineer[25%],Editor[25%] $280.00 1 day January 18, 2016 8:00 AM January 18, 2016 5:00 PM $280.00
Project Manager Project Manager $100.00 Mon 1/18/16 Mon 1/18/16 $100.00
Documentation Manager Documentation Manager $60.00 Mon 1/18/16 Mon 1/18/16 $60.00
Technical Writer & Engineer Technical Writer & Engineer $60.00 Mon 1/18/16 Mon 1/18/16 $60.00
Editor Editor $60.00 Mon 1/18/16 Mon 1/18/16 $60.00
1.9.2 Communicate Conversion Plan to Vendors Vendor Manager $240.00 1 day January 19, 2016 8:00 AM January 19, 2016 5:00 PM $240.00
Vendor Manager Vendor Manager $240.00 Tue 1/19/16 Tue 1/19/16 $240.00
1.9.3 Communicate Conversion Plan to Customer & Stakeholders Project Manager $400.00 1 day January 19, 2016 8:00 AM January 19, 2016 5:00 PM $400.00
Project Manager Project Manager $400.00 Tue 1/19/16 Tue 1/19/16 $400.00
1.9.4 Approve Conversion Plan with Project Sponsor Project Manager[50%],Sponsor[50%] $800.00 2 days January 20, 2016 8:00 AM January 21, 2016 5:00 PM $800.00
Sponsor Sponsor $400.00 Wed 1/20/16 Thu 1/21/16 $400.00
Project Manager Project Manager $400.00 Wed 1/20/16 Thu 1/21/16 $400.00
1.9.5 Total IT Solution Milestone Review Sponsor[50%],Project Manager[50%] $400.00 1 day January 22, 2016 8:00 AM January 22, 2016 5:00 PM $400.00
Sponsor Sponsor $200.00 Fri 1/22/16 Fri 1/22/16 $200.00
Project Manager Project Manager $200.00 Fri 1/22/16 Fri 1/22/16 $200.00
1.9.6 Go-Live with IT System(s) $0.00 0 days January 22, 2016 5:00 PM January 22, 2016 5:00 PM $0.00
1.9.7 IT System Burn-in Daily Testing $4,800.00 6 days January 25, 2016 8:00 AM February 1, 2016 5:00 PM $4,800.00
1.9.7.1 IT System Burn-in Daily Testing 1 Infrastructure & Hardware Consultant[33%],Application & Software Consultant[33%],Integration & Interface Consultatnt[33%],Project Manager $800.00 1 day January 25, 2016 8:00 AM January 25, 2016 5:00 PM $800.00
Project Manager Project Manager $400.00 Mon 1/25/16 Mon 1/25/16 $400.00
Application & Software Consultant Application & Software Consultant $133.33 Mon 1/25/16 Mon 1/25/16 $133.33
Integration & Interface Consultatnt Integration & Interface Consultatnt $133.33 Mon 1/25/16 Mon 1/25/16 $133.33
Infrastructure & Hardware Consultant Infrastructure & Hardware Consultant $133.33 Mon 1/25/16 Mon 1/25/16 $133.33
1.9.7.2 IT System Burn-in Daily Testing 2 Infrastructure & Hardware Consultant[33%],Application & Software Consultant[33%],Integration & Interface Consultatnt[33%],Project Manager $800.00 1 day January 26, 2016 8:00 AM January 26, 2016 5:00 PM $800.00
Project Manager Project Manager $400.00 Tue 1/26/16 Tue 1/26/16 $400.00
Application & Software Consultant Application & Software Consultant $133.33 Tue 1/26/16 Tue 1/26/16 $133.33
Integration & Interface Consultatnt Integration & Interface Consultatnt $133.33 Tue 1/26/16 Tue 1/26/16 $133.33
Infrastructure & Hardware Consultant Infrastructure & Hardware Consultant $133.33 Tue 1/26/16 Tue 1/26/16 $133.33
1.9.7.3 IT System Burn-in Daily Testing 3 Infrastructure & Hardware Consultant[33%],Application & Software Consultant[33%],Integration & Interface Consultatnt[33%],Project Manager $800.00 1 day January 27, 2016 8:00 AM January 27, 2016 5:00 PM $800.00
Project Manager Project Manager $400.00 Wed 1/27/16 Wed 1/27/16 $400.00
Application & Software Consultant Application & Software Consultant $133.33 Wed 1/27/16 Wed 1/27/16 $133.33
Integration & Interface Consultatnt Integration & Interface Consultatnt $133.33 Wed 1/27/16 Wed 1/27/16 $133.33
Infrastructure & Hardware Consultant Infrastructure & Hardware Consultant $133.33 Wed 1/27/16 Wed 1/27/16 $133.33
1.9.7.4 IT System Burn-in Daily Testing 4 Infrastructure & Hardware Consultant[33%],Application & Software Consultant[33%],Integration & Interface Consultatnt[33%],Project Manager $800.00 1 day January 28, 2016 8:00 AM January 28, 2016 5:00 PM $800.00
Project Manager Project Manager $400.00 Thu 1/28/16 Thu 1/28/16 $400.00
Application & Software Consultant Application & Software Consultant $133.33 Thu 1/28/16 Thu 1/28/16 $133.33
Integration & Interface Consultatnt Integration & Interface Consultatnt $133.33 Thu 1/28/16 Thu 1/28/16 $133.33
Infrastructure & Hardware Consultant Infrastructure & Hardware Consultant $133.33 Thu 1/28/16 Thu 1/28/16 $133.33
1.9.7.5 IT System Burn-in Daily Testing 5 Infrastructure & Hardware Consultant[33%],Application & Software Consultant[33%],Integration & Interface Consultatnt[33%],Project Manager $800.00 1 day January 29, 2016 8:00 AM January 29, 2016 5:00 PM $800.00
Project Manager Project Manager $400.00 Fri 1/29/16 Fri 1/29/16 $400.00
Application & Software Consultant Application & Software Consultant $133.33 Fri 1/29/16 Fri 1/29/16 $133.33
Integration & Interface Consultatnt Integration & Interface Consultatnt $133.33 Fri 1/29/16 Fri 1/29/16 $133.33
Infrastructure & Hardware Consultant Infrastructure & Hardware Consultant $133.33 Fri 1/29/16 Fri 1/29/16 $133.33
1.9.7.6 IT System Burn-in Daily Testing 6 Infrastructure & Hardware Consultant[33%],Application & Software Consultant[33%],Integration & Interface Consultatnt[33%],Project Manager $800.00 1 day February 1, 2016 8:00 AM February 1, 2016 5:00 PM $800.00
Project Manager Project Manager $400.00 Mon 2/1/16 Mon 2/1/16 $400.00
Application & Software Consultant Application & Software Consultant $133.33 Mon 2/1/16 Mon 2/1/16 $133.33
Integration & Interface Consultatnt Integration & Interface Consultatnt $133.33 Mon 2/1/16 Mon 2/1/16 $133.33
Infrastructure & Hardware Consultant Infrastructure & Hardware Consultant $133.33 Mon 2/1/16 Mon 2/1/16 $133.33
1.9.8 User Acceptance Testing Project Manager $12,000.00 30 days February 2, 2016 8:00 AM March 14, 2016 5:00 PM $12,000.00
Project Manager Project Manager $12,000.00 Tue 2/2/16 Mon 3/14/16 $12,000.00
1.10 Closeout Project $2,160.00 15 days March 15, 2016 8:00 AM April 4, 2016 5:00 PM $2,160.00
1.10.1 Evaluate Project Success Measures Project Manager $400.00 1 day March 15, 2016 8:00 AM March 15, 2016 5:00 PM $400.00
Project Manager Project Manager $400.00 Tue 3/15/16 Tue 3/15/16 $400.00
1.10.2 Document Lessons Learned Documentation Manager $480.00 2 days March 16, 2016 8:00 AM March 17, 2016 5:00 PM $480.00
Documentation Manager Documentation Manager $480.00 Wed 3/16/16 Thu 3/17/16 $480.00
1.10.3 Review Project Success Measures & Lessons Learned with Project Sponsor Sponsor[50%],Project Manager[50%] $800.00 2 days March 16, 2016 8:00 AM March 17, 2016 5:00 PM $800.00
Sponsor Sponsor $400.00 Wed 3/16/16 Thu 3/17/16 $400.00
Project Manager Project Manager $400.00 Wed 3/16/16 Thu 3/17/16 $400.00
1.10.4 Create Project Post-Mortem Report Technical Writer & Engineer[33%],Editor[33%],Documentation Manager[33%] $480.00 2 days April 1, 2016 8:00 AM April 4, 2016 5:00 PM $480.00
Documentation Manager Documentation Manager $160.00 Fri 4/1/16 Mon 4/4/16 $160.00
Technical Writer & Engineer Technical Writer & Engineer $160.00 Fri 4/1/16 Mon 4/4/16 $160.00
Editor Editor $160.00 Fri 4/1/16 Mon 4/4/16 $160.00
1.11 End Project 0 days April 4, 2016 5:00 PM April 4, 2016 5:00 PM $0.00

Resources_Team_PMIP

Resource Group Resource Name Scheduled_Work Cost
Facilities Gendex GXDP-300 Panorex Panoramix X-Ray Machine 1 X-Ray Machines $19,900.00
Facilities Install Hardware 1 X-Ray Machines $19,900.00
Facilities DentalEZ E-3000 Patient Dental Chair 1 Chairs $2,936.75
Facilities Setup chairs 1 Chairs $2,936.75
Facilities Tech West 1-hp Liquid Ring Vacuum System (2 users) 1 Vacuum $1,789.00
Facilities Setup chairs 1 Vacuum $1,789.00
Facilities Cisco SPA 504G IP Phone 5 Phones $444.95
Facilities Install Hardware 5 Phones $444.95
Facilities Cisco Small Business 200 Series 48-port Switch 1 Switches $517.02
Facilities Install server racks 1 Switches $517.02
Facilities Tripp Lite SRW26US 26U Wall Mount Rack Enclosure 1 Racks $706.76
Facilities Install server racks 1 Racks $706.76
Facilities Hiveage - Invoice System 1 Invoice System $299.95
Facilities Deploy Software 1 Invoice System $299.95
Facilities Umbie Dental Care - Record System 1 Record System $5,988.00
Facilities Deploy Software 1 Record System $5,988.00
Facilities Schedulicity - Scheduling System 1 Scheduling System $479.40
Facilities Deploy Software 1 Scheduling System $479.40
Consumables Paper 500 Sheets $5,000.00
Consumables Documentation Milestone Review 500 Sheets $5,000.00
Consumables Pen 25 Pens $50.00
Consumables Documentation Milestone Review 25 Pens $50.00
Consumables Printer Ink 1 Cartridges $40.00
Consumables Documentation Milestone Review 1 Cartridges $40.00
Consumables CAT6 cable spool 10 Spools $700.00
Consumables Install Data/VoIP Network Cabling 10 Spools $700.00
Tools Punch Down Tool 2 Tool $51.76
Tools Install Data/VoIP Network Cabling 2 Tool $51.76
Tools Screwdriver 3 Tool $33.36
Tools Install Data/VoIP Network Cabling 2 Tool $22.24
Tools Install Hardware 1 Tool $11.12
Tools Termination Kit 1 Tool $14.99
Tools Install Data/VoIP Network Cabling 1 Tool $14.99
Consumables Cable Raceways 3 Trays $370.95
Consumables Install raised floor 3 Trays $370.95
Consumables Raised Floor Tiles 50 Tiles $4,499.50
Consumables Install raised floor 50 Tiles $4,499.50
Consumables Rack Power Whips 2 Whips $397.98
Consumables Install server racks 2 Whips $397.98
Consumables Power Cables 3 Cables $24.27
Consumables Install server racks 3 Cables $24.27
Tools Laptop 1 Laptops $1,109.00
Tools Install Data/VoIP Network Cabling 1 Laptops $1,109.00
Tools Network Console Cable 1 Cables $12.55
Tools Install Data/VoIP Network Cabling 1 Cables $12.55
Tools Server 1 Servers $3,522.98
Tools Install Hardware 1 Servers $3,522.98
Tools Workstation 5 Workstations $4,485.00
Tools Install Hardware 5 Workstations $4,485.00
Sponsor 36.33h $1,816.67
Project Plan Milestone Review 1h $50.00
Develop 13.33h $666.67
Project Charter Milestone Review 2h $100.00
Approve Conversion Plan with Project Sponsor 8h $400.00
Total IT Solution Milestone Review 4h $200.00
Review Project Success Measures & Lessons Learned with Project Sponsor 8h $400.00
Project Manager 1,223h $61,150.00
Develop 40h $2,000.00
Project Plan Milestone Review 1h $50.00
Hire Network Technician Contractor 8h $400.00
Hire HVAC sub contractor 8h $400.00
IT System(s) Build 304h $15,200.00
IT System(s) Testing 48h $2,400.00
System Testing Milestone Review 8h $400.00
IT System(s) Training 144h $7,200.00
User Training Milestone Review 8h $400.00
Install Live System 328h $16,400.00
Create Conversion Plan 2h $100.00
Communicate Conversion Plan to Customer & Stakeholders 8h $400.00
Approve Conversion Plan with Project Sponsor 8h $400.00
Total IT Solution Milestone Review 4h $200.00
IT System Burn-in Daily Testing 1 8h $400.00
IT System Burn-in Daily Testing 2 8h $400.00
IT System Burn-in Daily Testing 3 8h $400.00
IT System Burn-in Daily Testing 4 8h $400.00
IT System Burn-in Daily Testing 5 8h $400.00
IT System Burn-in Daily Testing 6 8h $400.00
User Acceptance Testing 240h $12,000.00
Evaluate Project Success Measures 8h $400.00
Review Project Success Measures & Lessons Learned with Project Sponsor 8h $400.00
Documentation Manager 80.67h $2,420.00
Current process for scheduling 4h $120.00
Current process for patient records 4h $120.00
Current process for accounts payables 4h $120.00
Current process for accounts receivables 4h $120.00
Current process for dental claims 8h $240.00
Current process for patient billing 8h $240.00
Document Business Model 8h $240.00
Identify End User Training Requirements 4h $120.00
Create End User Training Plan 5.33h $160.00
Develop Training Materials 8h $240.00
Create Conversion Plan 2h $60.00
Document Lessons Learned 16h $480.00
Create Project Post-Mortem Report 5.33h $160.00
Technical Writer & Engineer 36.67h $1,100.00
Develop 13.33h $400.00
Document Business Model 8h $240.00
Identify Testing Scenarios 2.67h $80.00
Create End User Training Plan 5.33h $160.00
Create Conversion Plan 2h $60.00
Create Project Post-Mortem Report 5.33h $160.00
Research Manager 36h $1,080.00
Current process for scheduling 4h $120.00
Current process for patient records 4h $120.00
Current process for accounts payables 4h $120.00
Current process for accounts receivables 4h $120.00
Current process for dental claims 8h $240.00
Current process for patient billing 8h $240.00
Identify End User Training Requirements 4h $120.00
Editor 34h $1,020.00
Develop 13.33h $400.00
Document Business Model 8h $240.00
Create End User Training Plan 5.33h $160.00
Create Conversion Plan 2h $60.00
Create Project Post-Mortem Report 5.33h $160.00
Configuration Manager 0h $0.00
Vendor Manager 82h $2,460.00
Weekly Contractor Meeting 1 1h $30.00
Weekly Contractor Meeting 2 1h $30.00
Weekly Contractor Meeting 3 1h $30.00
Weekly Contractor Meeting 4 1h $30.00
Weekly Contractor Meeting 5 1h $30.00
Weekly Contractor Meeting 6 1h $30.00
Weekly Contractor Meeting 7 1h $30.00
Weekly Contractor Meeting 8 1h $30.00
Hire Network Technician Contractor 8h $240.00
Hire HVAC sub contractor 8h $240.00
Issue purchase order for new phone system 1h $30.00
Issue purchase order for new x-ray machines 1h $30.00
Expedite delivery 8h $240.00
Purchase Hardware 16h $480.00
Issue purchase order 8h $240.00
Receive dental chairs 16h $480.00
Communicate Conversion Plan to Vendors 8h $240.00
Application & Software Consultant 122.67h $6,133.33
Deploy Software 16h $800.00
Configure Software 8h $400.00
Identify Testing Scenarios 2.67h $133.33
Identify Testing Requirements 4h $200.00
Create Test Scripts 8h $400.00
System Testing 4h $200.00
Build Training Domain in IT System 8h $400.00
Train System Users 56h $2,800.00
IT System Burn-in Daily Testing 1 2.67h $133.33
IT System Burn-in Daily Testing 2 2.67h $133.33
IT System Burn-in Daily Testing 3 2.67h $133.33
IT System Burn-in Daily Testing 4 2.67h $133.33
IT System Burn-in Daily Testing 5 2.67h $133.33
IT System Burn-in Daily Testing 6 2.67h $133.33
Integration & Interface Consultatnt 106.67h $5,333.33
Configure Software 8h $400.00
Review System Configuration with Customers 8h $400.00
Identify Testing Scenarios 2.67h $133.33
Identify Testing Requirements 4h $200.00
Create Test Scripts 8h $400.00
System Testing 4h $200.00
Train System Users 56h $2,800.00
IT System Burn-in Daily Testing 1 2.67h $133.33
IT System Burn-in Daily Testing 2 2.67h $133.33
IT System Burn-in Daily Testing 3 2.67h $133.33
IT System Burn-in Daily Testing 4 2.67h $133.33
IT System Burn-in Daily Testing 5 2.67h $133.33
IT System Burn-in Daily Testing 6 2.67h $133.33
Infrastructure & Hardware Consultant 300h $15,000.00
Identify server closet 4h $200.00
Establish hot and cold isles 8h $400.00
Install raised floor 16h $800.00
Install server racks 8h $400.00
Receive Hardware 240h $12,000.00
Install Hardware 8h $400.00
IT System Burn-in Daily Testing 1 2.67h $133.33
IT System Burn-in Daily Testing 2 2.67h $133.33
IT System Burn-in Daily Testing 3 2.67h $133.33
IT System Burn-in Daily Testing 4 2.67h $133.33
IT System Burn-in Daily Testing 5 2.67h $133.33
IT System Burn-in Daily Testing 6 2.67h $133.33
Network Cabling Contractor 240h $5,006.40
Weekly Contractor Meeting 1 1h $20.86
Weekly Contractor Meeting 2 1h $20.86
Weekly Contractor Meeting 3 1h $20.86
Weekly Contractor Meeting 4 1h $20.86
Weekly Contractor Meeting 5 1h $20.86
Install Data/VoIP Network Cabling 235h $4,902.10
Complete Data/VoIP network cabling installation 0h $0.00
HVAC Contractor 75h $2,307.75
Weekly Contractor Meeting 6 1h $30.77
Weekly Contractor Meeting 7 1h $30.77
Weekly Contractor Meeting 8 1h $30.77
Perform HVAC capacity planning 16h $492.32
Install additional HVAC units 24h $738.48
Install cooling ducts and fans to cold isle 16h $492.32
Install exhaust ducts and fans to hot isle 16h $492.32
Complete installation of environmental controls 0h $0.00