Operation management (P chart and C charts)

profileThamJam
spc_home_case_2015_summer-3.xlsm

Sheet1

The time that it takes for an insurance claim form to be completed is very important for an institution.
They want to know if there is a change in this process.
20 random samples have been evaluated as shown below.
In each sample, the completion times for four forms have been measured:
Last 5 digits of Student No: 53909
Sample Time it took to complete the forms in this sample in hours
First form Second form Third Fourth
form form Construct a control -chart using the Excel templates available to you.
1 12.7 13.5 5.5 7.6
2 5.9 13 12.2 11.3 Answer the following questions in your excel file and load it to Moodle.
3 9.8 12.2 8 15.7
4 6.4 11.2 15.9 12.9 1-What are the chart types you will use?
5 8.7 9.9 11.1 15.7 Explain Why?
6 11.3 8.4 5.5 3.8
7 14.1 6.6 9.9 6.1 2-Is the average completion time for forms in this process in control? Why?
8 17.3 4.5 6.7 8.8 Explain all reasons.
9 2.8 20.2 3.1 11.8
10 5.6 18.7 18 15.1 3-Is the variation in completion times in control? Why? Mention all your reasons.
11 8.7 10.5 14.6 18.7 Explain all reasons.
12 12.1 19.9 10.7 22.6
13 15.8 8.1 6.5 4.8 4- Summarize the problems of this process and explain how we can fix these problems.
14 19.9 18.3 1.8 8.4
15 24.2 5.3 20.8 12.2
16 3.9 16.1 16.3 16.4
17 18.4 1.9 11.4 5.1
18 20.9 13.5 6.1 7.1
19 23.6 26 0.4 9.3
20 26.4 10.4 23.4 11.6

Sheet2

Sheet3