Do you know anything about Gantt Charts?

profileFancy2015
gantt_chart_excel_2015.xlsx

Sheet1

TASK START DATE DURATION END DATE
Analysis and Design 1-May 14 19-May
Development 21-May 10 31-May
Intergration 3-Jun 4 7-Jun
Testing 16-Jun 3 20-Jun
Maintainance 23-Jun 5 28-Jun
TASK GANTT CHART
START DATE Analysis and Design Development Intergration Testing Maintainance 41760 41780 41793 41806 41813 DURATION Analysis and Design Development Intergration Testing Maintainance 14 10 4 3 5