| Work Breakdown Structure Table |
| Provide basic information about the project including: Project Title – The proper name used to identify this project; Project Working Title - The working name or acronym that will be used for the project; Proponent Secretary - The Secretary to whom the proponent agency is assigned or the Secretary that is sponsoring an enterprise project; Proponent Agency – The agency that will be responsible for the management of the project; Prepared by – The person(s) preparing this document; Date/Control Number – The date the plan is finalized and the change or configuration item control number assigned. |
| Project Title: | Automation of Supply Chain Management System | | Project Working Title: | Automation of SCMS |
| Proponent Secretary: | Andrew Ray | | Proponent Agency: | Ray & Young Inc |
| Prepared by: | Vincent Ayam | | Date / Control Number: | SCMS XX001 |
| Element Number | WBS Elements Activity, Task, or Sub-Task Name | Definition of Activity or Task (Description) | Responsible Person or Group | Estimated (E) or Actual (A) Cost (Cross reference to budget) | Project Phase (Cross reference to schedule) |
| SCMS 001 | Initiation | The initiation process kicks off | Andrew Ray | 10400 |
| SCMS 00101 | Charter development |
| SCMS 00102 | Scope definition |
| SCMS 00103 | Defining the objectives |
| SCMS 00104 | Statement of proect missions |
| SCMS 002 | Planning | Planning phase of the project takes off | Andrew Ray | 15400 |
| SCMS 00201 | Setting up the project |
| SCMS 00202 | Scope definition |
| SCMS 00203 | Development of project schedule |
| SCMS 00204 | Development of risk plan |
| SCMS 003 | Execution | The actual implementation of the project begins | Vincent Ayam | 18600 |
| SCMS 00301 | Acquite the porject team |
| SCMS 00302 | Dierct and manage the teams |
| SCMS 00303 | Manage the team performance |
| SCMS 00304 | Quality and contract management |
| SCMS 004 | Monitoring and Completion | The final phase involves the monitoring phase and the completion of the project | Andrew Ray | 24600 |
| SCMS 00401 | Monitoring and quality management |
| SCMS 00402 | Change control |
| SCMS 00403 | Completion |
| SCMS 00404 | Handling over the project |