CASE STUDY 

THE CHUNNEL PROJECT   

Adapted from “The Chunnel Project” case study published by the Project Management Institute 

The original case study was prepared by: 

Frank T. Anbari, PhD, PMP, Paul Giammalvo, MSPM, CCE, PMP, Paul Jaffe, MSPM, PMP,   Craig Letavec, MSPM, PMP and Rizwan Merchant, MSPM 

 

And edited by:  

Frank T. Anbari, PhD, PMP  The George Washington University 

 

 

   

2   

Case Study 

The Chunnel Project 

 

Introduction 

The Channel Tunnel (Chunnel) project, undertaken to create a connection between England 

and France via an underground tunnel, represents one of the largest privately funded construction 

projects  ever  undertaken.  It  required  the  cooperation  of  two  national  governments,  bankers 

underwriting  the  funding  for  the  project,  numerous  contractors,  and  several  regulatory  agencies. 

Further,  the  construction  and engineering of the tunnel required the use of new technology and 

required  significant  modifications  during  the  project  due  to  unexpected  conditions  and  changes 

required by various interested parties. 

The  management  of  a  project  of  this  magnitude  is  a  significant  effort  even  if  everything 

related to the project ran extremely smoothly. As this case study will demonstrate, numerous factors 

came into play during the course of the project that had significant effects on the overall course of 

the project. In the end, the Chunnel project was completed, but it was late and over budget. The 

causes for missing the key cost and schedule deadlines, along with other factors related to Project 

Management  Knowledge  Areas  and  processes,  are  discussed  and  analysed  throughout  the  case 

study. 

The case study covers various Project Management Knowledge Areas (Project Management 

Institute, 2004) within four project phases: inception, development, implementation, and closeout. 

Within each project phase, the activities, accomplishments, and shortcomings of performance in the 

processes of Initiating, Planning, Executing, Monitoring and Controlling, and Closing are discussed. In 

the inception phase, the discussion focuses on the historical background of the project, its overall 

objectives,  political  climate,  and  pre‐feasibility  studies.  In  the  development  phase,  the  discussion 

addresses  the  overall  planning,  feasibility  studies,  financing,  and  conceptual  design.  In  the 

implementation phase, the discussion addresses detailed design, construction, installation, testing, 

and commissioning. Finally,  in the closeout phase, the discussion reflects on overall performance, 

settlement of claims, financial status, and post‐project evaluation. 

The Inception Phase 

During  the  inception  phase,  the  initial  scope  of  the  Chunnel  was  to  create  a  fixed 

transportation link between England and France. The expectation was that this would spur economic 

development,  improve  European  trade,  and  provide  an  alternative  high‐speed  transportation 

method to the existing modes (planes and ferry boats). 

In  1984,  the  British  and  French  governments  agreed  to  some  common  safety, 

environmental, and security concerns prior to opening up the project to bidders. In 1985, the French 

and British governments asked for proposals. Various proposals were submitted, and  in 1986 the 

project  was  awarded  to  the  Channel  Tunnel  Group/FranceManche  (later  to  become  Eurotunnel). 

Their proposal included a 32‐mile (51.5 km) double‐rail tunnel to accommodate both through‐trains 

and special car‐and‐truck‐carrying shuttle trains. Their bid price was US$S.5 billion. 

3   

From  a  project  management  perspective,  it  could  be  said  that  the  high‐level  design  and 

respective rough‐order‐of‐magnitude estimates may have been appropriate. However, not enough 

time  was  provided  to  complete  detailed  design  studies  that  would  have  identified  the  need  for 

tunnel  air‐conditioning,  a  US$200  million  scope  increase  that  was  not  included  within  the  initial 

scope (Veditz, 1993, p. 20). In addition, the process created by the Intergovernmental Commission 

(IGC) for approving designs put additional pressure on project scope, as  it approved design drafts 

that  were  not  considered  within  the  original  concession  agreement.  This  may  indicate  possible 

problems with scope initiation and planning. According to Colin J. Kirkland, Technical Director of the 

Eurotunnel from 1985 through 1991: “When governments announce an  intention to have such a 

huge public utility built, leaving all the details to be determined in the course of the competition, it is 

rather  like  releasing  a  mouse  at  a  Christmas  party‐the  reactions  of  all  those  affected  are 

unpredictable and uncoordinated, and everybody believes that he knows what the end result should 

be” (Kirkland, 1995). 

During the  inception phase, cost estimates were established at US$5.5 billion. As per the 

Channel Tunnel Treaty, the Chunnel project would have to be financed from private sources without 

government  aid  or  loan  guarantees.  In  return,  the  governments  were  prohibited  from  regulating 

prices except  in potential monopoly situations. This would help  in terms of estimating costs amid 

potential  governmental  economic  pressures.  Financing  was  pursued  via  equity  and  loan  capital 

markets. Shareholders seeking equity interest were more readily found in France and eventually in 

Britain as well. Loan financing was raised through a consortium of 206 banks worldwide. This would 

have  great  ramifications  later  in  the  project,  as  refinancing  would  have  to  be  pursued,  should 

negative  variances  in  time  and  cost  estimates  occur.  Another  cost  consideration  is  that  the 

Eurotunnel had secured a concession agreement for a period of 55 years. This gave them the sole 

right to operate the Chunnel for that time. Thus, any delay or cost increases throughout the project 

life would impact the planned cash flow for that period. 

From  a  project  management  perspective,  there  is  a  direct  correlation  between  scope 

definition  and  cost  estimates.  For  a  project  this  large,  there  are  usually  challenges  with  initial 

estimates, scope management, and (as will be discussed) the contract type. Thus,  lack of defined 

scope  makes  resource  planning,  cost  estimating,  and  budgeting  difficult.  In  addition,  return‐on‐

investment  (ROI)  assumptions  made  in  the  planning  stages  may  not  prove  accurate,  which  could 

leave a trail of unhappy investors and stakeholders. Given that the original cost estimate eventually 

increased to US$14.9 billion, opportunities for improvement appear to exist in this area. 

During the inception phase, various milestones were completed. Some may be considered 

false starts in the conceptual period, which included the following (Fairweather, 1998): 

 1974 – Initial tunnel ideas gathered, but efforts abandoned;   1978 – British and French discussions resumed;   1983 – French and British banks and contractors propose tunnel scheme;   1985 – French and British governments ask for fixed‐link proposals;   1985 – Anglo‐French Treaty signed, Transmanche Link (TML) awarded contract, and 

Eurotunnel declared owner of 55‐year concession for the link.  The schedule required planning all activities related to building three tunnels (north, south, 

and service). This was somewhat complicated due to the need to hire 46 contractors to complete 

the design requirements. As it turned out, the time estimate to complete the tunnelling itself was 

4   

materially  accurate,  finishing  three  months  ahead  of  schedule.  However,  ongoing  safety 

requirement changes sought by IGC continued to create negative schedule variances. 

From a project management perspective, schedule planning did include activities related to 

activity  definition,  activity  sequencing,  and  activity  duration  estimates  to  develop  the  baseline 

project  schedule.  This  can  be  further  illustrated  by  the  fact  that  scheduled  activities  included  12 

tunnelling faces (six landward and six seaward) that were excavated by 11 tunnel‐boring machines in 

both directions (Williams, 1993, p. 6). Thus, it can be suggested that the schedule complexity was 

significant and required maturity in logistical planning and experience in work breakdown structure 

(WBS) development. 

During  the  inception  phase,  Eurotunnel  entered  into  a  construction  contract  with  TML  in 

1987 having three cost categories: 

1. Target cost for tunnelling, done on a cost‐plus fixed‐fee basis, with a target cost above or  below which there would be a sharing of the difference. 

2. Lump sum for the terminals and the mechanical and electrical works for the tunnel.  3. The procurement contract for rolling stock and associated major equipment was procured 

on a cost‐plus‐percentage‐fee basis.   

Eurotunnel was responsible for roughly 70% of cost overruns on the original contract and 

TML was responsible for the remaining 30%, capped at a maximum 6% of the total cost. A revised 

agreement in 1990 provided a more equitable distribution of risks with Eurotunnel responsible for 

about £1.58 billion and TML responsible for 30% of everything above that figure. As will be discussed 

later, the types of contracts would prove to be challenging (i.e., ground consistency, fixed equipment 

claims). 

From a project management perspective, contracts are a critical part of the procurement 

management process. They define the scope of work, cost, timeline, and rules of engagement (i.e., 

penalties). As  it relates to this case,  it appears that the procurement planning process was quite 

complex and being completed under vigorous time constraints. Thus, certain assumption errors may 

have been made regarding the ability to have enough resources to complete the contract and, in the 

case  of  a  fixed‐price  contract,  not  enough  was  understood  to  limit  the  impact  of  known  and 

unknown  risks.  In  this  case,  contractual  errors  were  made  in  the  estimates  and  risk  allocation 

method, leading to additional contract claims of US$2.25 billion. 

Relative to risk management, the management team appears to have reviewed the scope of 

the Eurotunnel for initial risks. However, it seems that the focus was on engineering risk as opposed 

to process and approval risks. Those involved appear to have been comfortable with the technical 

nature  of  this  project,  but  less  prepared  to  deal  with  the  level  of  IGC  oversight  and  change 

management controls. At the highest level, both countries were aware of the financial risk, requiring 

that  funding  be  provided  by  non‐governmental  sources.  Business  risk  appears  to  have  been 

addressed to varying degrees via contractual agreements. However, these same contracts were the 

focus of subsequent scrutiny based on their inability to spread the risk among various stakeholders. 

From  a  project  management  perspective,  risk  planning  and  mitigation  needs  to  be  an 

ongoing part of each project. The hope  is that most material risks are  identified, quantified, and 

prioritised early enough so that an effective risk response strategy can be established. The ability to 

5   

address known and unknown risks requires careful assessment and understanding of the nature of 

each  initiative. For this case, decisions made  in the  inception phase (contract choice and change‐

control methods) could have been more carefully assessed for risk impact. 

From a quality perspective, the  IGC  (made up of  civil servants from France and the  U.K.) 

mandated that where there were differences in the standards of the two countries, the higher of the 

two should prevail (Fairweather, 1998). This was a good idea in theory, but contractors had difficulty 

interpreting differences related to a concrete pour. 

In addition, quality and specification issues could be seen early on as they relate to railway 

width, voltages, and signalling systems. These  incompatibility  issues needed to be  included within 

the  initial  quality  requirements  during  the  inception  phase.  Another  example  of  quality  impacts 

relates to the delay in communicating the requirement that passenger doors be widened from 600 

mm to 700 mm. This was a safety concern with IGC. When IGC did not provide timely approval for 

this change, TML’s manufacturing costs increased from US$9 million to US$70 million. However, the 

extent of quality planning for this initiative cannot be understated, given the scope of this initiative. 

State‐of‐the‐art laser and computer technology was used to bore the tunnel and to test every part of 

the rail system. In fact, the most amazing feat is that the three tunnels could be excavated so close 

together and still meet in the right spot in both countries. 

From a project management perspective, each team member has a responsibility for quality. 

Specific quality requirements must be defined up‐front as part of an overall quality management 

plan. This should include quality planning, quality assurance, and quality control. Given the technical 

challenges related to this project, it can be suggested that quality management was successful. 

During the inception phase, it was understood that the teamwork necessary to complete this 

project  would  be  significant.  The  ability  to  plan  and  execute  as  a  multinational  team  required 

cooperation and efforts at the highest level. Although the general complexity was known, it was not 

realised  until  this  project  was  completed  that  15,000  workers  were  employed  on  the  project 

(Fairweather, 1998). 

Teamwork can be looked at as it relates to those above and below the ground. Above the 

ground, there were politicians, governmental workers, bankers, lawyers, and analysts, all of whom 

leveraged the historical perspectives and economic challenges  into an approved project plan and 

act. Below the ground, thousands of construction workers, machinists, and engineers worked very 

well boring three tunnels for 32 miles (51.5 km) from both borders across the Channel. The fact that 

it took 3.5 years to complete this activity, on time, speaks volumes to the level of cooperation and 

teamwork for this activity alone. 

However, this feat was somewhat overshadowed by issues surrounding the contractual and 

financial obligations between various parties. Once all assumptions, assessments, and commitments 

are in writing, it can be very difficult to come to a mutually agreeable solution to material issues. 

Incomplete requirements, scope changes, and risk response strategies should have been considered 

within these efforts to reduce the likelihood of negative schedule and cost variances. 

From a project management perspective, defining a project team is one thing, but getting 

agreement  on  ownership,  activities,  and  timelines  is  another.  Roles  and  responsibilities  can  be 

6   

defined up‐front to address activities within the WBS. However, the true test of teamwork is how 

well stakeholders move forward with the same objectives, given the inevitable issues that will seek 

to bend or break formal and/or informal agreements. 

From a communications perspective, there was the usual give and take related to project 

planning, negotiations, and communication flow during the inception phase. This was amplified for 

the Eurotunnel project, given the need for communications and agreements at the highest levels of 

governments.  This  case  offers  extensive  evidence  of  the  importance  of  communications  in 

preplanning,  contract  negotiations,  financing,  and  technical  issues.  However,  it  appears  that 

technical problems were solved rather smoothly, whereas those related to organisational structures, 

contracts, and finance were wrought with conflict. 

This project involved 700,000 shareholders, 220 international lending banks (Genus, 1997, p. 

181),  British  and  French  governments,  many  construction  companies,  and  many  suppliers.  This 

complexity  caused  significant  logistical  and  communication  challenges.  The  interdependency  of 

these stakeholders made it difficult to address issues to everyone’s satisfaction. In fact, changes in 

scope due to requirement omissions or changes can be viewed in many ways depending on how it 

impacts  cost,  time,  quality,  and  potential  risk.  It  is  here  where  the  communication  seemed  to 

breakdown, as  issues were not resolved  in a timely manner, resulting  in significant cost and time 

variances. 

Project communications management is often one of the most important aspects to project 

planning and execution. A communications plan needs to be put in place that will address horizontal 

and  vertical  communication  channel  needs.  This  communications  plan  could  include  information 

distribution,  as  well  as  issue  tracking  and  performance  reporting.  It  appears  that  issues  in  the 

Chunnel  project  may  not  have  been  given  enough  visibility  and/or  managed  or  escalated  to  a 

sufficient extent to mitigate their impact on the overall project plan. 

During the  inception phase, very  little was mentioned  in the way of formal project office 

activities, although it can be assumed that a project of this size had considerable back‐office efforts 

to  support  it.  Clearly,  overall  project  activities  and  progress  were  being  monitored,  given  the 

dependency on funding and accountability to the shareholders. The construction industry is known 

for  its  use  of  advanced  project  management  tools  and  techniques.  Thus,  the  project  should  be 

managed to industry‐specific practices and agreed‐upon international standards. 

One  of  the  challenges  is  that  decision‐making  was  somewhat  fragmented,  sub‐optimising 

the  project  for  the  sake  of  specific  issues.  This  eventually  pitted  project  champions  against  each 

other,  as  contractual  obligations  made  mediation  difficult.  Thus,  although  project  management 

techniques may have been in play, the ability of the project management team to address critical 

issues from a centralised position seemed insufficient. 

It  can  be  questioned  if  enough  effort  was  spent  on  agreeing  to  the  value  of  a  project 

management office prior to the project gaining momentum. Given the international ramifications, it 

can be assumed that general protocols were deemed sufficient. However, given the nature of the 

conflicts and need for effective management, this may be considered a challenge to this initiative. 

7   

From a project management perspective, there  is significant value of an effective project 

management office as it relates to supporting and promoting project management “best practices”. 

The  larger  the  project,  the  greater  the  impact  of  proven  methods  and  processes  will  be  on  the 

bottom line. It is assumed that during the inception phase, the roles and responsibilities of a project 

management office should be validated. This can be difficult to do unless agreed to early with key 

stakeholders. 

The Development Phase 

The  development  phase  of  the  Chunnel  project  consisted  of  detailed  planning, 

communication  agreements,  and  governmental  approvals.  This  was  an  important  phase  for  the 

project because of its sheer size, complexity, and breadth. There were many things that made this 

phase difficult, including the inflexibility of some of the characteristics of the projects, and the cross‐

cultural exchange between two countries that had to take place. Two different companies, on two 

different  sides  of  the  project,  speaking  two  different  languages,  led  by  two  different  managing 

directors, did the planning. The company on the British side was Translink and the company on the 

French side was Transmanche. A large part of the struggles that the project incurred were due to 

failures in the development phase of this project. 

The scope of this project was enormous. The decision to link France and England has been 

considered before, but never completed. The project had no hope of being profitable  in the 20 th  

century. This was the world’s largest privatised project, and scope creep played a large part in the 

substantial increase from its initial cost estimates, and its completion behind schedule. During the 

development phase, the scope was not fully assessed and the proper precautions to prevent scope 

creep were not put in place. The Treaty of Canterbury and setting up of the IGC to coordinate the 

approach, construction, operation, and safety of the tunnel resulted in total loss of control when it 

came to scope (and huge cost increases). 

The project team did a reasonable job when  it came to planning the technical equipment 

that would be needed and understanding the complexity involved. They were able to use previous 

research on the soil, but, in the end, the lack of continued focus on scope resulted in the frustrations 

of trying to do too much. The mistake of allowing IGC to have scope control without the ability of 

IGC to approve additional funding for scope creep affected the management of this project so that 

success became extremely difficult. 

The  results  of  the  Chunnel  project  point  clearly  to  challenges  when  it  comes  to  cost 

management in the development phase. The project finished substantially above budget and led to 

an additional significant claim. Although cost is one of the most difficult aspects to plan for when a 

project  has  such  a  huge  magnitude,  the  project  management  team  had  serious  challenges  in 

planning  and  detailing.  The  chief  project  executive  at  Eurotunnel  from  1990  to  1993  stated,  “... 

perhaps the central problem was the banks’ early involvement in the renegotiation of the contract, 

and the multiple methods of compensation for different parts of the works .... The banks insisted on 

the least defined portions ...” (Fairweather, 1998, pp. 290‐291). 

The difficulties in cost planning during the development phase could be partly blamed for 

the US$2.25 billion claim that was brought against Eurotunnel by the contracting company. 

8   

The schedule planning during the development phase seemed to be adequate. The project 

finished a year late but it was often due to things beyond the project management team’s control. 

The IGC mandated that whenever a difference occurred in standards between the two countries, the 

higher of the two standards be kept. Theoretically this made sense, but when it came to the fine 

details  of  the  project,  it  helped  create  schedule  delays.  There  was  much  interpretation  open  for 

agencies like IGC that might have been better off detailed during the planning sessions for schedule 

analysis. The IGC’s decision to force Eurotunnel to change its design from 600 mm doors to 700 mm 

doors by itself cost the project a nine‐month delay. Every three months, a hefty status report was 

prepared  for  all  the  investors  involved  in  this  project,  which  contributed  to  keeping  the  project 

somewhat on track. 

Contracts  during  the  development  phase  of  the  project  included  agreements  for  the 

financial aspects of the project, as well as the logical aspects. The golden rule was followed: “He who 

has  the  gold  makes  the  rules”.  The  banks  were  given  way  too  much  leeway  and  control  in  this 

project. When banks are involved, they often focus on minimising risk, which can be a good thing. 

However, when that is taken to the extreme, as in the Chunnel project, all the efforts to save money 

and minimise risk to the bank are thrown out the window because of things like the claim and award 

settlement  that  went  against  Eurotunnel.  The  agreement  to  create  the  IGC  and  give  it  so  much 

control also contributed to the challenges in this area of the project. Risk was thought to be on the 

banks’  side  during  the  development  phase  of  the  project,  but,  in  hindsight,  the  banks’  plans 

backfired badly. The courts ruled in favour of the contractors’ claims, and cost the project a lot of 

money. 

Risk could have also been better researched and evaluated when it came to the technical 

side  of  the  project.  Due  to  French  fears  about  being  unable  to  grout  on  their  side,  much  more 

sophisticated and advanced equipment was used. Later on, it was found that equipment as old as 

1974 could have been used just as effectively. This is another example of over‐managing risk. 

Because of the free reign given to the IGC, quality aspects of this project were handled well. 

Using the “better of the two methods”, the most advanced technological equipment and very little 

margin for error allowed for quality to be an extremely important attribute while planning during 

the development phase of this project. 

Teamwork  during  the  development  phase  was  helped  by  the  focus  on  fairness  that  was 

followed  by  the  two  governments  involved.  For  every  British  team  member,  the  French  had  a 

matching counterpart. However, there was no method of encouraging teamwork during the  later 

phases of this project. The team could have designed methods by which teamwork across all the 

phases,  teams,  and  team  members  of  this  project  was  emphasised.  Although  the  momentum, 

elation,  and  pride  created  during  the  signing  of  the  treaty  approving  this  project  gave  it  starting 

strength, proper provisions were not put into place to allow that momentum to continue through 

the life of the project. The two governments moved further away from the teamwork concept when 

they refused to guarantee the project financially. That put an additional burden on the privatised 

sector and forced its back to the wall. This caused some level of mistrust because the governments 

created the demands for safety and so forth, but the government guaranteed nothing financially. 

Communication between the French and English sides of this project was limited. Putting the 

two teams on opposite ends and working toward the middle delayed communication until near the 

9   

end  of  the  project.  Each  side  worked  toward  a  common  goal,  and  did  not  feel  the  need  to 

communicate  because  the  assumption  was  that  they  were  both  working  toward  meeting  in  the 

middle. Lack of communication during the development and design of this project in its early stages 

led  to  differences  of  opinion  in  its  later  stages.  Although  the  status  reports  were  helpful  and 

consistent every three months, it was akin to a yearly prospectus that did not foster or accentuate 

communication within the team. It was a report for the financial world just to appease them and 

allow the project to continue. 

The project office did an adequate job during the development phase. It followed some of 

the planning, designing, and detailing phases required in the development phase of a project, but its 

work was far from superior. It did take data from past projects, but perhaps not the lessons learned 

when  planning  the  Chunnel  project.  Project  results  point  to  the  fact  that  there  is  room  for 

improvement in this phase. 

Project  management  in  the  development  phase  of  the  Chunnel  project  was  generally 

hopeful. There was a clear understanding of the immensity of this project, but not enough research 

and detailed planning to back it up. The project management team, in hindsight, could have done a 

better  job  of  detailing,  planning,  and  designing  this  project.  Once  the  project  team  gave  up  the 

majority  of  its  control  to  the  IGC  –  and  had  financial  people  breathing  down  its  neck  and 

emphasising cost cutting and minimal risk, two different cultures, two different management teams, 

and various other challenges – the development phase of this project had already been made so 

difficult that the resulting cost and schedule overruns were just foregone conclusions. 

The Implementation Phase 

The implementation phase of the Chunnel project started in the fourth quarter of 1987, with 

the awarding of a “Concession Contract” in response to the Channel Tunnel Group/FranceManche 

(CTG/FM) bid for US$5.5 billion, and ended on December 15, 1994, with the project being handed 

over fully operational (Genus, 1997, p. 173; Veditz, 1993). 

The winning proposal was made under a “build‐own‐transfer” (BOT) arrangement, granting 

CTG/FM  the  concession  to  run  the  project  for  a  period  of  55  years  (Morris,  1994),  after  which 

ownership would revert back to the French and British governments. Having won the request for 

proposal (RFP), CTG/FM awarded a “design/build/commission” construction contract to TML. The 

actual  contractor  was  a  consortium  of  construction  companies,  some  of  which  were  investors 

(through joint ventures) with the original CTG/FM winner. Thus, although a normal client‐contractor 

relationship was created, there were instances of real conflicts of interest as the contractors were, in 

many  cases,  direct  or  indirect  investors.  These  conflicts  of  interest  would  cause  problems  as  the 

project  was  implemented.  When  the  construction  contract  was  awarded,  the  cost  estimate  was 

US$4.3 billion and the original completion date was May 15, 1993. When the implementation phase 

was completed, the project was 19 months late and had cost overruns of some US$3 billion (total 

construction costs of US$7.1 billion). The closeout phase explores the total cost impact not only of 

the construction cost overruns but also, more importantly, the lost revenue and carrying costs of the 

project during the 19‐month period. 

10   

It is generally agreed that the Chunnel project presents excellent opportunities for lessons 

learned  in  project  management,  especially  for  capital‐intensive  projects,  using  new  or  proven 

technology, under unusual or new high‐risk conditions. 

Problems  with  politics  started  almost  immediately,  as  the  project  was  being  fast‐tracked 

with design and construction happening simultaneously. This in itself may not have been a problem, 

except that the promoters CTG/FM had to obtain approvals from the governments of both Britain 

and France. The very nature of democratic governments is to be deliberative, thereby causing delays 

and  false  starts  from  the  beginning.  Furthermore,  CTG/FM,  under  pressure  from  the  French  and 

British  governments  to  control  costs,  insisted  that  TML  issue  fixed‐price  contracts  to  their 

subcontractors  and  vendors.  As  the  scope  was  not  well  defined,  using  a  fixed‐price  contract  in  a 

competitive bidding situation inevitably gave rise to claims, as the contractors, in order to have any 

chance of winning the bid in a competitive environment, assumed an optimistic case, and relied on 

“changed  conditions”  to  justify  claims  as  they  arose.  Since  underground  construction  is  rife  with 

changed conditions, the use of fixed‐price contracts (rather than some sort of cost‐plus  incentive 

fee) set the stage for a contentious relationship between the subcontractors and TML, and in turn, 

between  TML  and  CTG/FM.  These  change  orders,  although  many  were  resolved  in  favour  of 

CTG/FM, nonetheless caused cost escalation. More  importantly, as will be shown  in the closeout 

phase,  the  impact  of  cost  overruns  was  nowhere  near  as  serious  as  the  impact  of  delays  to  the 

functional  completion  of  the  project.  It  may  be  that  governments,  particularly  those  requiring 

deliberation  in  order  to  make  decisions,  have  added  challenges  in  managing  projects,  especially 

those that are time constrained. 

Fast tracking, the process of overlapping design and construction in the hope of shortening 

delivery time  is a risky approach under the best of circumstances. However, using this technique 

when the technology is new or unproven makes the risk exponentially greater. Added to this is the 

fact  that  underground  construction  is  arguably  the  most  risky  of  all  construction,  as  changed 

conditions, if proven, stand as prima facie evidence entitling a contractor, subcontractor, or vendor 

to  compensation  both  in  terms  of  actual  costs  plus  extended  overhead.  This  is  in  addition  to  an 

extension of time to complete. As the longest tunnel of its type in the world, the fact that tunnelling 

is the most risky of all construction (and such a project had never been attempted previously with 

available technology), should have alerted the governments not to use the approach they did. 

Several other issues stood out as warning signs: 

1. Some of the rolling stock had not yet been designed (vehicle and freight cars).  2. No contingency was set aside to cover “unknown unknowns”. (In this case, the need for a 

ventilation system in the tunnels.)  3. The specifications for British rolling stock and French rolling stock were not the same. 

  All these  issues should have been early warning signs that the details needed to be agreed to  in 

advance,  and  that  proceeding  without  resolution  would  only  result  in  eventual  delays  and  cost 

overruns. 

Using contract methods inappropriate for the scope definition was another issue (Kerzner, 

2003, p. 826). As previously outlined, TML was attempting to use fixed‐price contracting methods 

when  scope  was  not  sufficiently  defined.  Contractors  who  bid  on  fixed‐price  contracts  under 

11   

competitive bid (low price) “winner takes all” terms have only one choice if they are to win the bid – 

they  must  assume  the  “best  case”  scenario  for  that  amount  of  scope,  which  remains  vaguely 

defined, or risk losing the bid to the next lowest bidder. 

Under these circumstances, there was no room for contingencies and margins were cut to 

the  barest  minimum.  The  contractor  had  no  choice  but  to  be  aggressive  in  pursuing  any  and  all 

change orders. Thus, anything that differed from the original scope (or that  a reasonable person 

might infer was missing from the scope) had to be pursued. To do otherwise would risk forcing the 

contractor into bankruptcy. In setting up the RFP, the British and French governments set the stage 

for a contentious and adversarial relationship. The sponsoring governments may have avoided many 

of the problems by realising the risks involved and setting up the original RFP with the objective of 

rewarding  the  “promoters”  –  and,  in  turn,  the  contractors  at  all  levels  –  for  achieving  the  goals 

determined by the governments to be important. 

Another  example  was  the  fact  that  the  original  consortium  (CTG/FM)  consisted  of 

construction  companies  and  bankers  whose  primary  objective  was  to  make  money  on  the 

construction and not on the operation. Remembering that this was a 55‐year BOT, it may have been 

better to structure the consortium so that the construction was done at cost, and the only profit 

would come from completing the project at the lowest possible cost, within the framework of the 

quality and safety constraints established by the governments of France and Britain. This model may 

have stood a better chance of being successful. 

Reflecting on the project, Jack K. Lemley, Chief Executive Officer of Transmanche Link from 

1989 to 1993, highlights the importance of cultural matters, communications, and contract issues. 

He states: “There must be one contract, it must be developed and written in one language, and it 

must be based on one legal system. It must all contain clearly defined dispute resolution procedures, 

procedures with which all parties are familiar and with which all parties have agreed to abide.” He 

concludes by stating: “The key element is communication” (Lemley, 1995). 

The  objectives  of  a  project  need  to  be  identified  and  communicated  clearly  from  the 

beginning. This was perhaps the  largest and most damaging failure of the governments of France 

and Britain. The financial model they created was far too optimistic given the risks involved, and the 

fact that the project was essentially run by bankers compounded the problem. By not having the real 

goals,  objectives,  and  scope  defined  early,  and  by  not  implementing  a  contracting  method  that 

directly linked the rewards to contractors at all levels of the procurement chain to those objectives, 

the governments set the stage for the financial challenges of the Chunnel. 

The Closeout Phase 

In the closeout phase, the project would not be expected to gain significant ground in key 

areas of project management. Most notably, the immense amount of litigation and the size of the 

claim against the project showed that even the best attempts at managing critical issues during the 

project did not have a significant effect on the overall outcome. 

In terms of scope, the overall scope of the project was increased due to significant change 

requests throughout the life of the project. Even near the end of the project, the requirement for an 

air conditioning system to cool the tunnel during normal operation represented a significant scope 

12   

modification. In fact, even when the tunnel was deemed to be complete, there were still outstanding 

scope items to be resolved. This meant that the overall scope of the project was still not fixed, even 

at  the  proposed  completion.  It  should  be  noted  that  the  completion  of  the  project  (which  was 

delayed) was even rushed to allow operation to begin before the entire effort was completed. 

Clearly,  cost  and  schedule  management  represented  significant  challenges  during  the 

project. By closeout, the majority of the effort was focused on analysing the sources of cost overruns 

and attempting to assign blame to one or more of the participating organisations. The focus during 

closeout  was  on  attempting  to  minimise  the  amount  of  claims  awarded  rather  than  on  truly 

analysing the causes of cost overruns. Although certain portions of the project were completed early 

(the tunnelling, for example), other areas such as the delivery of key mechanical systems (including 

key components of the rail car system) were delivered late and caused the project implementation 

to slip past its intended completion date and into the time allotted for closeout. 

By the closeout phase of the project, teamwork and communication had broken down  in 

several  key  areas.  The  financial  backers  of  the  project  were  keenly  focused  on  minimising  their 

losses and, as such, refused to accept negotiated arrangements for settling some of the key contract 

disputes.  Several  arbitration  bodies,  including  the  International  Chamber  of  Commerce,  were 

involved to help bring the various competing sides to the bargaining table in an attempt to resolve 

key portions of the very complex claims existing at the end of the project. The concept of “win‐win” 

negotiations was clearly far from the minds of the interested parties by the time the project came to 

a close. Overall, teamwork during closeout was focused on each party meeting its own priorities and 

interests rather than working toward an acceptable solution for all parties involved. However, the 

parties involved in the project seemed to be quite willing to share in the project “success” – even as 

multibillion‐dollar claims were being made against them. From a public relations perspective, it was 

clearly in the best interest of the owning parties and the contracting parties to show that success 

had  been  achieved  and  to  provide  as  much  positive  information  as  possible  to  the  public.  The 

Chunnel  project  was  something  totally  new,  and  a  tainted  view  in  the  eyes  of  the  public  due  to 

management issues would do nothing to help sales of crossings in the Chunnel. 

The overall quality of the delivered project, as measured during closeout, was  impressive. 

The  final  tunnel  was  an  engineering  feat  that  was  extremely  complex  and  there  were  immense 

hurdles to success. Despite these factors, the tunnel operated essentially as designed. Through an 

effective quality and safety program, even the workplace accident rates during the project were well 

below the industry average. 

One of the greatest impacts on the project that did not materialise until closeout was the 

impact of the late delivery of the project on the project’s overall ROI. The initial cost models detailed 

an expected return based on use of the tunnel assuming that the tunnel was completed on time. The 

delivery  delay  and  corresponding  impact  on  the  beginning  of  operations  meant  that  the  parties 

“owning” the tunnel were faced with numerous litigation items and no source of income from the 

operation of the tunnel. The “bare minimum” approach to cost estimating and contract awarding in 

the fixed‐price model meant that there were no significant operational reserves available to provide 

additional funding  in the  interim. Thus, project shareholders could not expect to see a return on 

their  investments  until  significantly  longer  than  had  been  initially  expected.  From  a  project 

management point of view, there were numerous factors beyond the control of the project team 

13   

that led to this situation. In a sense, bankers and other parties that demanded deviations from the 

proven methods of managing the project “shot themselves in the foot”, and set up a situation that 

was detrimental not only to the project itself, but also to the public perception of the project. 

From a project management perspective, the closeout phase is an excellent example of why 

effective change management must be in place for projects. The ability of a party to make demands 

for changes in the design of the deliverable without corresponding funding for making those changes 

provides a perfect setup for challenged results. In the case of the Chunnel, the “health and safety” 

commission  (known  as  the  IGC)  had  broad  authority  to  demand  changes,  but  had  no  means  to 

provide  additional  funding  to  implement  the  changes.  This,  combined  with  very  slow  decision‐

making, led to situations where significant budget overruns occurred not due to bad estimating or 

controlling, but rather due to out‐of‐control change management processes. 

Summarising his thoughts on the project, Kirkland (1995) states: “We should seek to advise 

future generations contemplating the creation of very large infrastructure developments not to get 

carried  away  by  the  excitement  of  the  design  and  construction  process  before  they  have  clearly 

established  the  rationale,  the  relationships  among  the  key  players,  and  the  means  by  which  the 

totality of the process is to be managed.” 

The Chunnel can be viewed as “either one of the greatest engineering and political feats of 

the twentieth century, or, a project that never should have happened. However, irrespective of the 

opinion  taken,  it  is  clear  that  the  Europeans  are  proud  of  their  Chunnel”  (Serich,  Bale,  Kwasny, 

Patneaude, & Stack, 2001). 

 

References 

Fairweather, V. (1998). The Channel Tunnel: Larger than life, and late. In D. I. Cleland, K. M. Bursic, R.  Puerzer, & Y. A. Vlasak (Eds.), Project Management Casebook (pp. 289‐296). Newtown Square,  PA: Project Management Institute. 

  Genus, A. (1997). Managing large scale technology and inter‐organizational relations: The case of the 

Channel Tunnel. Research Policy, 26, 169‐189.  Kerzner, H. (2003). Project management: A systems approach to planning, scheduling and controlling 

(8th ed.). New York: John Wiley & Sons.    Kirkland, C. J. (1995). The Channel Tunnel – Lessons learned. International Tunnelling Association 

(ITA). Originally published in the journal Tunneling and Underground Space Technology, 10(1), 5‐ 6. Retrieved October 16, 2005 from                                                                                     http://www.ita‐aites.org/applications/30th/PDF/TUST_95_v10_n1_5‐29.pdf 

  Lemley, J. K. (1995). Managing the Channel Tunnel‐Lessons learned. International Tunnelling 

Association (ITA). Originally published in the journal Tunneling and Underground Space  Technology, 10(1), 9‐11. Retrieved October 16, 2005 from                                             http://www.ita‐aites.org/applications/30th/PDF/TUST_95_v10_n1_5‐29.pdf 

  Morris, P. W. G. (1994). The management of projects. London: Thomas Telford.   

14   

Project Management Institute. (2004). A guide to the project management body of knowledge (3rd  ed.). Newtown Square, PA: Author. 

  Serich, S., Bale, G., Kwasny, M. K., Patneaude, S., & Stack, J. (2001). The Chunnel: The channel tunnel 

project. Unpublished manuscript, Washington, DC: The George Washington University.    Veditz, L. A. (1993). The Channel Tunnel: A case study. Executive Research Report (pp. 1‐22). 

Washington, DC: The Industrial College of the Armed Forces.    Williams, C. L. (1993). DoD contracting in a global environment. Washington, DC: The Industrial 

College of the Armed Forces.