Solving the Issue of Cost Calculation in BPM Workbench

BPM Workbench does not automatically show the cost of the process. The following example shows how to solve

this issue.

1- Double click on each task

2- Click on “Resource Requirements”

3- Go to “Additional Resources”

- Click on the arrow (Step 1 in the figure) to show the list of the available roles.

- From the dropdown list, select the responsible person for this task.

- Click ok