Proj430 Adv Proj Mgmt Week 3

profilefidelcastro97
question_key.docx

Project Organization, Deliverables, and Milestones

3

Define WBS and Work Packages

Develop the WBS with schedule, resources, and costs using Microsoft Project.

This week, you will be using Microsoft Project to develop the work breakdown structure (WBS) and work packages for your Course Project. You will also be developing the project schedule and project budget. You can access Microsoft Project from the iLab under Course Home.

You will submit your Microsoft Project file to the Week 3 Course Project Dropbox.

Project Title:

Recreations

Project Organization:

Project Manager:

Abc

Executive Sponsor:

Phoenix, Inc.

Project Team Members:

Name

Title

Expertise

Responsibilities

ABC

COE

Finance

Overseeing all operations budgets, accounting, contracts

CDE

General Manager

Human Resources

Overseeing all departments and daily activities

FGH

Production

Craftsman, training

Oversees all craftsmen, production, creative team

ABC

Project Manager

Management of functional areas

PM responsibilities

GTY

Marketing

Community outreach and marketing of creations

Network with community-based organizations and commercial businesses

Project Team Reporting Structure:

See Attachment A

Project Team Communications

The Team will meet weekly. Email will be used sparingly and only for the purpose of confirming appointments, need to meet, forwarding documentation, forms and reports with confidentiality and locked with passcodes. The Organizational Chart will be followed for chain of command with an open-door policy.

Project Team Conflict Resolution

Policy and Procedures Manual will be in place and followed. Organizational Chart will be followed, but the Team will meet weekly to discuss problems, issues, and conflicts. There will be in place a Board of Directors for resolution of conflicts involving COE.

Project Deliverables:

Deliverable Name

Description

Accounting Contract

A/R, A/P, Payroll will be outsourced

IT Contract

IT will be outsourced for all in-house networking, web design, repairs and troubleshooting

Community-based Partners

Contracts in place with the community-based partners

Materials In-Stock

Production will have warehouse stocked with needed materials and equipment

Policies & Procedures Dev.

Recreations will have in place policies & procedures for the training site/production site, business, etc.

Training Manual Dev.

Goals, objectives, time lines, Recreation startup templates, lesson plans, safety will be addressed in the manual.

Project Milestones :.

Milestone Name and Description:

Completion Date

Web Page Developed

90 days

Contracts with Community Based Partners

30 days

Vendors/Suppliers Contracted

30 days

Materials In-Stock

30 days

Training Manual Developed

30 days

Policies and Procedures Manual Developed

30 days

Accounting Out-Sourced

30 days

Attachment A

Board of Directors

Production

Marketing

Project Manager

General Manager

Chief Operating Executive

Version 1, 07/01/11 Page 2 of 4