Project Management
Assignment 1
1) Following are elements of a WBS for a project to build a bunk bed. Using the information supplied here, create a WBS and carry out a bottom-up cost estimate.
Cost($)Rate ($/hr)Time (hrs)
Research: Jimmy' time12
Dad's time252
Materials: Lumber200
Hardware45
Power equipment rental65
Jimmy's time to acquire materials13
Dad's Time to acquire materials153
Construction:Jimmy's time18
Dad's time208
Inspection:Mom's time100.5
2) Following is a listing of items to be considered in costing a PC game development project. Use this data to develop a parametric estimate of the cost of the project.
Cost ($)Rates($/hr)Time (hr)
Resources: Designers 30100
Artists25200
Programmers251000
Work Station3000
Contracted Testing Group50100
Marketing Materials1500
Fringe benefits:30%of Direct Wages
Overhead:70%of (Direct Wages + fringes)
3) For the table below
TaskPredecessor
Duration
(in days)
Latest
start
Earliest
start
Float
(slack)
AStart5
BA,D8
CB9
DStart6
ED12
FStart12
GF7
a) Create a PERT/CPM chart
b) Identify the critical path and compute project duration
c) Compute Latest Start, Earliest Start, and Float (Slack)
1