Project Status Report
To: Dr. Bingbing Li From: Sulaiman alarifi , khalid Alkatheeri , Ali Alsaggaf, Almalki,Abdulaziz Ahmed , Abdullah Bafarat Date: June 30, 2015 Subject: Project II remodeling manufacturing workshop of the Department of MSEM at CSUN
Project Overview The focus of the project is the plan of reorganizing and remodeling of the manufacturing workshop of the Department of MSEM at CSUN(JD-1128). Our main tasks are developing a new comprehensive remodeling plan and design a new efficient convenient floor layout where the full area of is accessible from the main entrance as well as the back door. The following bullet points are summarizing the workflow of planning and layout design.
Work Completed
Dilemmas at the workshop are space utilization efficiency, overcrowded equipment and infrequently used tools taking space. The proposed solution is relocating the machines in a way to maximize space efficiency, tools turnover where big machines can be replaced with smaller one and deliver same quality of work, and relocating and resizing storage area. In addition, a safe walk path is needed for customers to move from workstation to another or move product with the workshop.
The data we have collected are workshop back ground, workshop area and tools dimensions. Full data is appended.
gantt chart
Data collecetion :
Machine list and dimansions
|
Machine |
Width (inch) |
Length (inch) |
|
1- Wilton- Sand paper machine |
1 ft |
1 ft |
|
2- 508 vs Drilling machine (Model 9512484) |
1ft |
1.5ft |
|
3- Acer E-Lathe 1440v |
2.7ft |
1 ft |
|
4- DAKE V-24(Model v-24) |
1ft |
2ft |
|
5- NEF 320 Gildemeister |
4ft |
2-5ft |
|
6- VF3 HAAS |
6ft |
3ft |
|
7- Computer Table area |
|
|
|
8- The Morgan-Press |
0.5ft |
0.6 |
|
9- Hypred layer manufacturing 3D printer |
1ft |
1ft |
|
10- Lincoln Electric |
3.6ft |
1.3ft |
|
11- Millermatic 350P |
0.5ft |
1ft |
|
12- Inductronix power pulse |
1ft |
0.7ft |
|
13- HAAS Mill operators |
4ft |
3ft |
|
14- CMM Machine- Bright-M mitutoyo |
3ft |
2ft |
|
15- Thermoset 3D printer |
3 ft |
1.2 ft |
|
16- Dimension SST 1200 3D Printer |
1ft |
1.3 ft |
|
17- Maker Boot Replicator 3D Printer |
1 ft |
1 ft |
|
18- Cube X DUO 3D Printer |
1 ft |
1ft |
|
19- Ryobi thin line bench grinder |
1ft |
1.3ft |
|
20- Syncowave 180 sd |
0.5ft |
1.5ft |
|
21- E-mill |
3ft |
2.1ft |
|
22- Quill position control |
|
|
|
23- Bal dou |
1ft |
0.5ft |
Work in Progress
Currently we are reviewing the feasibility of our proposed solution and coordinating personal interviews with Roger and workshop customers. In addition, we are reviewing class material to find a quantitative representation of proposed solution and prospect ideas.
Works to Be Completed in Next One Months
There are paramount tasks and milestone need to be done and finalized before the due date. The first one is creating the outline for the final report and auditing the outline against the grading guide line. Write the first draft of the report and review with team. Second task is expanding and detailing the current project plan and objectives. Third task is evaluating the new method versus the current situation of the workshop.
· Objectives Planning:
· Research and analysis
· Identifying workshop customers
· Production type and classification , flow, time, volume
· Production necessities from initial stage to finishing stage
· Identify Production system in the workshop and workstations
· Applying learnings from class to determine type of lab (volume Vs variety)
· Defining objectives and goals based on customer needs and feedback
· Applying formulas to determine number of machines needed
· Feasibility and timeframe
· Current problems the workshop is facing
· Project proposal addressing workshop problems and prioritization criteria
· Feasibility study on actions on the facility new design items
· Defining millstones and dependencies in plan flow
· Anticipating obstacles facing the team and problems may occur with remodeling
· Developing gantt chart
· Risks and advantage assessments
· Compare the new design vs the old design
· First draft of project proposal
· Design layout
· Find the advantages and disadvantages of the new and old design
· Equipment relocation based on prioritization criteria
· Equipment turn over
· Relocating and redesigning the storage area
· Develop a walk path between the machines
· providing maximum flexibility in the final layout to accommodate future expansion
Start Date group meeting and brain storming research and analysis identify objectives and goals project propsal collecting data status report analyzing current work shop layout group meeting and finilizing soltuion create new layout implementation and execution prepare presentation prepare final report final report post review final project due 42171.0 42173.0 42176.0 42178.0 42180.0 42182.0 42186.0 42190.0 42193.0 42202.0 42210.0 42210.0 42217.0 42220.0 Duration group meeting and brain storming research and analysis identify objectives and goals project propsal collecting data status report analyzing current work shop layout group meeting and finilizing soltuion create new layout implementation and execution prepare presentation prepare final report final report post review final project due 1.0 3.0 3.0 2.0 2.0 5.0 4.0 1.0 8.0 8.0 4.0 5.0 2.0 1.0