Task List

IT Consultant Business Startup 55 days Special Notes:
Design Phase 27 days
Visit Manager of Facility 1 day Chris Walters
Discuss Company Requirements 1 day 3 Chris Walters,George Richards
Survey Facility for Setup 1 day 4 Bill Young,Dan Thomas,Harold Park Must have 1 Software, 1 Hardware, and 1 Network Engineer
Draft Layout Designs for Facility 1 week 5 Bill Young,Dan Thomas,Harold Park Must have 1 Software, 1 Hardware, and 1 Network Engineer
Discuss Layout Designs with Company 1 day 6 Chris Walters,George Richards
Get Approval on Layout Design 1 day 7FS+1 wk
Draft Equipment Requirements 1 week 4,8 Bill Young,Dan Thomas,Harold Park Must have 1 Software, 1 Hardware, and 1 Network Engineer
Discuss Equipment Requirements with Company 1 day 9 Chris Walters,George Richards
Get Approval on Equipment 1 day 10FS+1 wk
Setup Phase 14 days 2
Order Equipment 1 day Adam Zurich,Fred Smith,Jared Oliver,George Richards Must have 1 Software, 1 Hardware, and 1 Network Engineer and Financial Advisor
Order Computer Systems 1 day Computer System[20]
Order Computer Monitors 1 day Computer Monitor[20]
Order Computer Accessories 1 day Computer Accessories[20]
Order Battery Backups 1 day Battery Backup[20]
Order Printers and Fax 1 day Printers[10]
Order Network Equipment 1 day Networking Hardware[5]
Order Network Cables 1 day Network Cables[50]
Order Operating System 1 day OS Software[20]
Order Other Software 1 day Other Software[20]
Receive Equipment 1 week 13
Prepare Equipment for Install 1 week 23 Adam Zurich,Fred Smith,Jared Oliver Must have 1 Software, 1 Hardware, and 1 Network Engineer
Install Software 2 days 24 Adam Zurich,Harold Park Must be 2 Software Engineers
Install Network 2 days 24 Bill Young,Fred Smith Must be 2 Network Engineers
Install Printers and Fax 1 day 24 Dan Thomas,Jared Oliver Must be 2 Hardware Engineers
Test Complete Setup 1 day 25,26,27 Bill Young,Dan Thomas,Harold Park,Adam Zurich,Fred Smith,Jared Oliver Must have 2 Software, 2 Hardware, and 2 Network Engineers
Finalize and Train Phase 14 days 12
Give Orientation to Client Company Employees 8 days Chris Walters
First Orientation Session 4 days Bill Young,Dan Thomas,Harold Park Must have 1 Software, 1 Hardware, and 1 Network Engineer
Second Orientation Session 4 days 31 Fred Smith,Adam Zurich,Jared Oliver Must have 1 Software, 1 Hardware, and 1 Network Engineer
Check Back with Company 1 day 30FS+1 wk Chris Walters

Resource Sheet

Resource Name Type Group Max. Units Std. Rate
Adam Zurich Work Software Engineer 100% $25.50/hr
Bill Young Work Network Engineer 100% $23.00/hr
Chris Walters Work Company Manager 100% $50.00/hr
Dan Thomas Work Hardware Engineer 100% $23.50/hr
Fred Smith Work Network Engineer 100% $22.50/hr
George Richards Work Financial Advisor 100% $35.00/hr
Harold Park Work Software Engineer 100% $22.00/hr
Jared Oliver Work Hardware Engineer 100% $24.50/hr
Larry Montague Work Network Engineer 100% $20.00/hr
Michael Norse Work Hardware Engineer 100% $20.00/hr
Nathan Lee Work Software Engineer 100% $20.00/hr
OS Software Material $250.00
Other Software Material $300.00
Computer System Material $1,000.00
Computer Monitor Material $250.00
Computer Accessories Material $150.00
Printers Material $100.00
Networking Hardware Material $75.00
Network Cables Material $5.00
Battery Backup Material $125.00

Sheet3